A .crbx file is an exchange archive: a compressed, ZIP-type container that bundles the data of a tender so it can be passed from one software package to another. The contractor who receives it by email does not necessarily have the software that produced it. The usual outcome: the file stays closed, the pricing is done on the attached PDF and the quantities are copied one by one, unit errors included.
The studio opens the .crbx archive in the browser, on Mac or PC, without uploading anything. It displays the tree: chapters, groups, items and sub-items, with quantities, units and descriptive texts, which the reader does not alter. It indicates whether the reading is structured or heuristic. You then type in your unit prices, sub-item by sub-item when an item contains any, and set the discount and the VAT. If the file received is not an archive but a renamed PDF, the reader says so.
Worked example: a .crbx tender for sanitary installations, five lines to price
A plumbing contractor receives the tender for a bathroom renovation in a small rental building. The .crbx archive contains one chapter and four items, one of which is split into two sub-items. The unit prices and amounts below are example amounts, deliberately round and entirely fictitious: they reflect no market price.
| Item | Quantity | Unit | Example unit price | Amount |
|---|---|---|---|---|
| Item 1: pipework | 24 | m | 10.00 | 240.00 |
| Item 2, sub-item a: appliances | 6 | pce | 100.00 | 600.00 |
| Item 2, sub-item b: connections | 6 | pce | 20.00 | 120.00 |
| Item 3: pipe insulation | 85 | m | 10.00 | 850.00 |
| Item 4: commissioning | 1 | gl | 500.00 | 500.00 |
| Total of items | 2’310.00 |
Each amount is the quantity read in the archive multiplied by the unit price entered: 24 × 10.00 = CHF 240.00, 6 × 100.00 = CHF 600.00, 6 × 20.00 = CHF 120.00, 85 × 10.00 = CHF 850.00 and 1 × 500.00 = CHF 500.00. Item 2 has no price of its own: its two sub-items carry the quantities, and therefore the prices. The total of items is CHF 2’310.00.
The contractor grants an overall discount of 2%: 2’310.00 × 2% = CHF 46.20, which gives a net amount excluding VAT of CHF 2’263.80. VAT at 8.1% is added: 2’263.80 × 8.1% = CHF 183.37. The total including VAT is CHF 2’447.17.
Key point: five priced lines give CHF 2’310.00 of items, CHF 2’263.80 net excluding VAT and CHF 2’447.17 including VAT, without a single quantity copied by hand.
3 common mistakes with a .crbx tender file
Mistaking a renamed PDF for a .crbx archive
Some files received with the “.crbx” extension are in fact PDFs: there is then no structured data to extract. The reader points this out. In that case, ask the author of the tender for the original exchange file.
Trusting a heuristic reading without checking it
When the structure of the .crbx archive is not fully recognised, the studio switches to a heuristic reading and says so. Compare the quantities and units with the original document: a misread unit changes the amount with nothing on screen to show it.
Forgetting a sub-item
An item split into sub-items is priced line by line. If the connections sub-item is left without a price, the chapter looks complete although CHF 120.00 is missing in the example. The list of anomalies shows the items without a price: go through it before printing.
How to price a .crbx tender in 3 steps
- Drop the .crbx archive
Drag the file into the studio. Read the reliability indication, then expand the chapters to check that the items, quantities and units match the document you received. - Enter the prices of the tender
Go to the first line and type your unit prices: Tab or Enter confirms and moves to the next one, the arrow keys move the selection. Items of the “alternative” type are flagged in the list. - Set discount and VAT, then print
Enter the chapter discount and the overall discount, leave VAT at 8.1% or adjust it, then deal with the anomalies. Print the tender summary. The browser's print function lets you save it as a PDF.
What the free .crbx tender reader does not do
The reader is tolerant, but it has not been validated on every .crbx archive in circulation: the original document remains the reference and the comparison is up to you. The free version exports no return file, no CSV and no Excel file. The printed summary carries an Art Construction watermark and nothing is saved from one session to the next. Art Construction is a publisher independent of SIA and CRB.
The Soumissions software exports the return file: the original file completed with your prices, to be validated with your trade software before sending. It also saves the file per construction site and produces tender documents without a watermark.
Frequently asked questions
What is a .crbx file?
It is a compressed, ZIP-type exchange archive that carries the data of a tender between software packages: structure in chapters and items, quantities, units and descriptive texts.
My .crbx file will not open: why?
The most common case is a PDF that has been given the .crbx extension. The reader points this out. Ask the author of the tender for the original exchange file.
Is the content of the .crbx tender sent to a server?
No. The archive is read in your browser and its content stays on your computer. Closing the tab erases the session, including the prices entered.
Can I return my tender in .crbx format from the free studio?
No. The free studio prints a tender summary. Export of the return file belongs to the Soumissions software and should be checked with your trade software before sending.