Table of contents
The 3 Major Site Risks
- Financial / Margin: Direct margin loss through unilateral rejection of works performed without a prior instruction. On unforeseen earthworks or underpinning items, failure to observe contractual formalities results in payment refusals ranging from 15 000 CHF to over 60 000 CHF, the contractor remaining bound by the agreed price under art. 373 CO in the absence of a formal agreement.
- Legal / Joint Body / SUVA: Sanctions in the event of non-compliance with working hours during emergency daywork operations. Art. 12 LTr caps overtime at two hours per worker per day during extraordinary work surges, while joint monitoring committees review timesheet traceability and the application of collective agreement travel or tooling allowances.
- Administrative / Acceptance: Blocking of final account verification and postponement of preliminary steps prior to acceptance of the work under standard SIA 118. An accumulation of unsigned daywork sheets creates an overarching dispute that paralyses the release of retainage and fuels disputes regarding the authority of the site management under art. 32 CO.
Managing daywork is a critical aspect of financial construction site management in Switzerland. Intended for work whose exact scope cannot be determined in advance when awarding the contract, payment on a daywork basis departs from the standard mechanism of unit prices or lump-sum pricing. Within the definition of the contract for work and services set out in art. 363 CO, work executed on a daywork basis requires strict evidential discipline. Site management, site managers and clients must structure every step: from issuing the prior instruction through to the systematic signing of daily reports, while keeping close control over the wage rates, machinery charges and material prices applied.
The most common pitfall lies in launching unscheduled works without a formal instruction or on directions from individuals lacking the necessary representative authority under art. 32 CO. Where the price is not fixed in advance within the meaning of art. 374 CO, valuation is based on actual expenditure and the value of the work, provided that the performance of the service is proven through proper timesheets and delivery dockets. This guide details the notification duties, daily report review deadlines and dispute protocols provided by standard SIA 118 to prevent any invoice rejection.
Contractual framework for daywork under standard SIA 118
Under the framework of a construction contract governed by standard SIA 118, daywork is never a default performance method. It applies exclusively when essential works cannot be priced using unit prices or lump sums upon concluding the contract, or when an unforeseen technical issue demands emergency intervention. Under the definition of the contract for work and services set out in art. 363 CO, the contractor undertakes to produce a work in return for a price that the client undertakes to pay. When this price has not been set in advance pursuant to art. 373 CO, or if it was agreed to apply the daywork rate, art. 374 CO provides that the amount is determined according to the value of the work and the contractor's expenses. However, standard SIA 118 imposes strict procedural safeguards to prevent cost overruns.
Executing daywork strictly requires prior agreement from the site management or the client. Submitting an upfront estimate protects the contractor against subsequent disputes. If the actual amount excessively exceeds the agreed approximate quote through no fault of the client, the latter may invoke the options granted by art. 375 CO, including requesting an appropriate price reduction. Consequently, any unscheduled intervention must be covered by a documented site instruction before operations begin, except in an absolute emergency affecting the stability of the structure or public safety.
Duty of notification and daily sign-off formalities
The disciplined administration of daywork relies on the daily daywork report. The contractor is required to record accurately the actual working hours of personnel, trade classifications, machines used along with their actual operating time, as well as the materials installed. Swiss site formalities require immediate transmission of these accounting records to the site management. The cardinal rule is daily submission or, at the latest, weekly submission if expressly agreed in the contract.
The signature or countersignature affixed by the site management serves a critical evidentiary purpose: it certifies the physical reality of the works delivered, the presence of workers and the use of plant on site. Under Swiss law of evidence, signing a daywork report does not automatically imply acceptance of a financial obligation if the site management registers written reservations regarding the principle of the instruction itself or the appropriateness of the resources deployed. Conversely, the absence of an objection within the time limits set by standard SIA 118 establishes a presumption that the recorded facts are accurate. A site management team receiving a daily report must examine it, correct it jointly if required, and return it either approved or accompanied by a reasoned refusal.
To ensure full compliance for personnel assigned to daywork, firms must enforce statutory working conditions. Pursuant to art. 9 LTr, the maximum weekly working time is 45 hours or 50 hours depending on the category of activity. Art. 12 LTr governs exceptional overtime beyond maximum hours, while art. 13 LTr defines the remuneration framework for overtime work. Construction site organisation must also incorporate mandatory breaks prescribed by art. 15 LTr. Complying with these provisions ensures that submitted time records reflect lawful, verified site activity.
Handling unordered daywork and emergency operations
One of the most frequent disputes involves daywork carried out spontaneously by the contractor without prior written instruction from the site management. In principle, work performed without a mandate is rejected outright by project financial management. A contractor taking the unilateral initiative to modify a construction method or add scope cannot claim additional remuneration based on the daywork rate.
A strict exception applies in the event of imminent danger or absolute technical necessity. If the contractor uncovers a situation posing an immediate threat to the structural integrity of the work or to safety, it must intervene to protect the client's interests. Under art. 365 CO, if materials supplied by the client or the building ground designated by the client are found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, failing which it must bear the consequences. In terms of safety, art. 82 LAA requires the employer to implement all measures proven necessary by experience, feasible under current technology, and suited to the prevailing conditions, while workers are bound to cooperate. When emergency shoring or protective works are ordered to ward off a hazard, the daywork report must explicitly indicate the emergency and be served on the site management on the very same day.
Comparative table of daywork statuses and procedures
| Site situation | Prerequisite | Reporting frequency | Effect of site management sign-off | Main financial risk |
|---|---|---|---|---|
| Standard contractual daywork | Written instruction or signed addendum | Daily (24 h to 48 h) | Recognition of quantities and billing approval | Uncontrolled overrun of the cost estimate |
| Daywork for geotechnical surprises | Prior joint inspection record | Daily with photographs | Validation of specific plant and labour deployed | Dispute over whether ground conditions were unforeseen |
| Emergency safety intervention | Immediate notice pursuant to art. 365 CO | Immediate (same day) | Proof of the physical reality of measures taken | Refusal of payment if imminent hazard is unproven |
| Unsolicited work without an instruction | No formal agreement | Late (at month-end) | Formal rejection or sign-off under express reservation | Total direct loss for the contractor |
| Daywork following variation orders | Variation order | Weekly by agreement | Inclusion in monthly advance payments | Confusion between contract unit prices and daywork rate |
Common management errors and financial impacts
The primary error observed is the accumulation of unsigned daywork sheets. When a site manager submits batched reports at the end of the month without daily validation, the site management finds it materially impossible to verify the accuracy of crane operating hours or labourer time. In such cases, disputed sums frequently reach amounts between 20 000 CHF and 85 000 CHF per monthly application, creating prolonged administrative deadlocks.
The second pitfall is the failure to distinguish between work included in the bill of quantities unit prices and additional daywork. A contractor billing routine work area cleaning or collective shaft protection on a daywork basis commits a contractual breach: these tasks are an integral part of trade contractor general duties or Site Installations. Protection requirements for floor openings are strictly defined by art. 25 OTConst, which mandates perimeter guardrails or securely fastened, load-bearing covers. The site management systematically corrects these unwarranted charges when auditing site records.
Finally, the lack of immediate joint sign-off exposes the contractor to contractual preclusion under the particular conditions of contract. If the contract stipulates a forfeiture deadline for submitting daywork sheets, any report delivered past the deadline may be dismissed without right to compensation, directly eroding the net margin of the trade package.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios presented below are illustrative examples developed for technical and contractual analysis.
Scenario 1: Discovery of a perched water table during excavation in the Canton of Vaud
On an apartment building site in the Canton of Vaud, an earthmoving contractor deploys a crew of 4 plant operators and drivers. During excavation adjacent to a trench governed by art. 68 OTConst, unforeseen water ingress threatens the stability of battered trench slopes. Art. 75 OTConst requires slope angles to match ground resistance and appropriate measures to be taken if stability is compromised. The site manager immediately applies art. 365 CO and notifies the site management of water ingress jeopardising the proper execution of earthworks.
The site management issues a written instruction for emergency dewatering on a daywork basis and silt clearance. The contractor logs the operation of a motor pump set and the hours of two operatives daily. The daily report is signed every evening on the construction site. The daywork total, amounting to some 14 500 CHF over 6 working days, is approved in full within the monthly advance payment without dispute, thanks to rigorous joint traceability.
Scenario 2: Unordered underpinning works in the Canton of Geneva
In the Canton of Geneva, during the conversion of a commercial building, a bricklayer identifies unstable rubble masonry in the basement. Without referring the matter to the site management, the crew carries out underpinning concrete pours over the weekend, mobilising 3 operatives for 16 hours and billing quick-setting concrete. The daywork report is delivered ten days later with a payment claim of around 18 200 CHF.
Site management refuses to sign off, citing the complete absence of a prior order and the lack of any joint inspection record of the subsoil condition before concreting. The contractor's financial claim is rejected. This case illustrates the financial risk of uncommissioned daywork carried out outside a proven immediate emergency.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
What is the deadline for submitting daywork reports to site management?
Under standard SIA 118, the contractor submits daywork reports weekly, unless agreed otherwise. This document details labour hours, machinery and supplies. Regular filing prevents contractual forfeiture and secures joint verification for monthly provisional statements of around 15 000 CHF.
What risk does a contractor run by carrying out daywork without a prior order?
Without a formal order from site management, the client can refuse payment based on the works contract. Under art. 374 CO, compensation remains possible only if the contractor proves the objective utility of the work or tacit ratification under art. 6 CO to protect the structure.
What deadline applies to site management for returning an annotated report?
Standard SIA 118 gives site management seven days to return the signed report or provide written grounds in case of dispute. Without a formal response within this time frame, the hours worked and material deliveries are deemed accepted for calculating the advance payment.
How should urgent safety measures carried out as daywork be documented?
To prevent a cave-in under art. 68 OTConst, the contractor immediately deploys the required resources. They then draw up a detailed report outlining the risks to bodily integrity under art. 229 CP. This record substantiates the necessity of the intervention with the agent during financial approval.
Does a dispute over the daywork hourly rate withhold the advance payment?
No. Disputing a unit price does not justify withholding payment for accepted hours. Site management signs off on the actual quantities and reserves the applicable rate. The undisputed amount, for instance 8 000 CHF, is paid in accordance with the works contract.
Does the site foreman's signature on the report bind the client?
No. Signing on the construction site merely certifies that the work was materially performed. Only site management, acting as representative under art. 32 CO and vested with the appropriate authority under art. 398 CO, confirms the financial obligation to pay on behalf of the principal.
Rigorous daywork management demands seamless documentation between the site supervisor and site management. Strict enforcement of work order forms and adherence to signature deadlines safeguard the project's financial stability and prevent disputes at final settlement.
To further explore financial tracking and contractual management on your Swiss construction sites, consult our specialist guides:
- Financial Site Management: Joint Measurement Surveys, Daywork and Addenda (SIA 118 / ACIP)
- Order Amendments and the ± 20% Rule on CAN Quantities (SIA 118): Renegotiating a Unit Price
- Joint On-Site Quantity Surveying vs As-Built Plans (SIA 118): Procedures and Forfeiture
- Checking Advance Payments, Performance Bonds (10% / 5% - SIA 118) and KBOB Price Fluctuations
