Validly Interrupting the 5-Year Limitation Period in Switzerland: Payment Summons (LP) or Written Waiver

How to interrupt the 5-year limitation period for construction defects under Swiss law: payment summons and written waiver.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Permanent loss of the client's rectification rights once the limitation period expires, leading to a direct net loss that can amount to roughly 10 % to 15 % of the total value of the building, subject to warranties under the Code of Obligations (CO).
  2. Legal / Joint body / SUVA: Procedural error when drafting the waiver declaration or improper service of the payment summons leading to invalidation of the interruption under art. 135 CO and art. 141 CO, depriving the creditor of any legal recourse.
  3. Administrative / Acceptance: Loss of warranty rights for hidden defects after acceptance of the work due to the absence of a formal act of interruption recorded in the construction site file before the five-year expiry date set under art. 371 CO.

In the context of construction site monitoring and site management in Switzerland, managing statutory deadlines is a core requirement to protect the client's rights. Under art. 371 CO, the client's rights arising from defects in an immovable work become time-barred five years after the acceptance of the work. When hidden defects emerge or when negotiations with the contractor or technical consultants drag on, letting this period elapse without taking formal action exposes the client to a complete forfeiture of its rights. Mastering the mechanisms of interruption is therefore essential for any construction practitioner.

To prevent the five-year deadline from expiring without necessarily filing a full lawsuit on the merits, two main routes are preferred in Swiss practice: serving a payment summons through debt enforcement under art. 135 CO and having the debtor sign a written waiver of the defence of the statute of limitations pursuant to art. 141 CO. The local site management must accurately identify which method to apply in order to prevent any forfeiture detrimental to the warranty of the work.

Mechanisms for interrupting the limitation period: Payment summons vs written waiver

On a Swiss construction site, monitoring defects and safeguarding the client's rights require absolute procedural rigour. The five-year limitation period provided by the Code of Obligations (CO) for immovable works begins to run upon acceptance of the work. To avoid losing rights simply through the passage of time, the site management or the client's representative must act before the deadline expires. Two main instruments are used in Swiss contractual practice: serving a payment summons through debt enforcement and obtaining the signature on a formal declaration waiving the defence of the statute of limitations.

Serving a payment summons (LP)

Under art. 135 CO, the limitation period is interrupted when the creditor asserts its rights through debt enforcement. The debt enforcement request filed with the competent debt enforcement office leads to the service of a payment summons on the debtor. This measure has the direct effect of starting a new limitation period of the same duration. Its main advantage lies in its unilateral nature: no agreement is required from the contractor or the design professional. However, this step can strain business relationships and requires paying cost advances to the debt enforcement office.

Written waiver of the defence of the statute of limitations

Pursuant to art. 141 CO, the debtor may waive the defence of the statute of limitations, in writing, each time for a maximum of ten years. This negotiated solution is frequently chosen during technical discussions or joint expert appraisals aimed at identifying the cause of a defect on a work. It avoids initiating debt enforcement proceedings while maintaining legal leverage over the general contractor or subcontractor. The declaration must be in writing and signed by an individual properly authorised to represent the debtor company.

Comparative analysis of methods to interrupt the 5-year period

Choosing between debt enforcement action and a negotiated waiver depends on the quality of inter-company relationships, the construction schedule, and the willingness of the parties to reach an agreement on remediation. The following table details the operational criteria of each option.

Enforceability and agreement required Unilateral (without the debtor's consent) Contractual (written agreement mandatory) Form and formalities Official debt enforcement request form Written document drafted and signed by hand Risk of dispute Possible objection by the debtor Dispute over the validity of signatory powers Effect on deadline New 5-year period upon service Suspension or new deadline agreed (max. 10 years) Direct administrative cost Statutory fee advances to the debt enforcement office No official fees (internal handling) Relational impact on site Perceived as an aggressive legal step Preserves dialogue and amicable negotiation Operational validity High if exact address is verified Subject to the accuracy of the legal wording
Assessment criterionPayment summons (LP)Waiver of the defence (CO)

Common deadline management errors and financial consequences

Analysing disputes arising during site management shows that simple formal oversights can neutralise the effects of interrupting the limitation period. Particular care is required when drafting legal documents and exchanging correspondence.

Formal defects and incomplete representation powers

Under art. 32 CO, the rights and obligations arising from a contract concluded in the name of another party by an authorised representative pass to the represented party. A frequent mistake involves accepting a waiver signed by a project manager or a site manager who does not hold signing powers registered in the commercial register or an express power of attorney. If the representative lacks proper authority, the waiver is void and the limitation period continues to run, causing the irreparable loss of remediation claims. Likewise, a mere reminder letter or site minutes not signed by the debtor do not constitute an acknowledgement of debt under art. 135 CO.

Inaccuracies in describing claims and amounts

A payment summons that fails to specify the precise cause of the claim or the estimated amount of damages risks being successfully contested. Amounting to tens of thousands of francs, the cost of repairing defective waterproofing or cladding can fall entirely on the client if the debt enforcement request is declared void due to vagueness. Using vague wording such as "site balance" without referring to the works contract or the acceptance report creates harmful legal uncertainty.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following scenarios are illustrative examples designed to show how rules on interrupting the limitation period are applied in the Swiss context.

Scenario 1: Water ingress on a flat roof in a building in Lausanne (VD)

In a residential building under condominium ownership delivered in 2021, leaks appear in 2025 on the flat roof. The estimated remediation cost is around 180 000 CHF. The five-year limitation period is set to expire a few months later. The waterproofing firm denies liability and refuses to sign a waiver. The site management requests debt enforcement through the Lausanne debt enforcement office. Under art. 135 CO, serving the payment summons interrupts the limitation period, starting a new five-year period and preserving the client's rights without risking forfeiture of its claims.

Scenario 2: Screed cracking in a commercial complex in Meyrin (GE)

During post-completion warranty monitoring of a shopping centre, severe cracking appears in the basement concrete screeds. The general contractor agrees to carry out a joint technical appraisal to determine whether the defect stems from the materials or the installation. To avoid initiating debt enforcement while investigations are underway, the general contractor agrees to sign a waiver of the defence of the statute of limitations. Under art. 141 CO, a written declaration is executed for a period of 24 months, signed by two directors holding joint signature powers according to the commercial register. Technical discussions continue without jeopardising the client's future legal options.

Proactive strategy for site management

To ensure effective warranty monitoring, the site management must set up a centralised schedule of deadlines as soon as acceptance of the work takes place. Key dates to record include the end of the notice of defects period under standard SIA 118, the expiry of the five-year period under the Code of Obligations (CO), and the release dates of warranty retentions. If a serious defect arises, the decision between a written waiver and debt enforcement via a payment summons must be made at least six months before the legal deadline to counter any dilatory tactics from the opposing party.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

How do you validly interrupt the 5-year limitation period under Swiss law?

To interrupt the 5-year limitation period under art. 135 CO, the client can serve a payment summons through debt enforcement (LP) or obtain a written waiver from the debtor under art. 141 CO, thereby preventing the forfeiture of rights.

Is a notice of defects sufficient to interrupt the limitation period?

No. Reporting a defect signals the problem but does not interrupt the limitation period. Under art. 135 CO, only an acknowledgement of debt, debt enforcement, a request for conciliation, or a lawsuit interrupts the five-year period set out in art. 371 CO.

What is the maximum duration of a waiver of the limitation period?

Under art. 141 CO, waiving the defence of the statute of limitations is valid for up to ten years per declaration. It must strictly be made in writing to be legally enforceable against the contractor, architect, or engineer.

Does standard SIA 118 alter the 5-year limitation period?

Standard SIA 118 defines the terms for inspecting the work, but the limitation period for the client's rights regarding defects in an immovable work remains five years under art. 371 CO. Art. 371 CO specifies that this period cannot be shortened to the client's detriment.

How much does it cost to issue a payment summons to protect rights?

The fees for issuing a payment summons depend on the tariff schedule under the federal debt enforcement and bankruptcy act (LP). For an illustrative claim of 50 000 CHF, official fees amount to around 73 CHF, advanced by the creditor.

Does an email from the contractor promising repairs interrupt the limitation period?

Yes, if the email represents a clear acknowledgement of the debt or defect by the contractor, art. 135 CO provides that acknowledgement interrupts the limitation period. For evidentiary purposes, however, a signed written document under art. 141 CO remains preferable.

Rigorous deadline management requires continuous foresight from both the site management and the client. To explore technical and contractual tracking and safeguard rights on your construction sites, consult our dedicated resources: