SIA 118 Final Account: 2-Month Deadline, 30-Day Check & the Discharge Trap

Master the final account under SIA 118: submission and verification deadlines, balance management and dispute prevention on Swiss building sites.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Outright cash loss due to inadvertent forfeiture of claims when signing a receipt in full settlement without express reservations, impacting around 5% to 12% of the final work total under Code of Obligations (CO) rules governing contracts for work and services.
  2. Legal / Joint body / SUVA: Release of financial guarantees and retention money frozen if quantity surveys are formally disputed or if hour reconciliations fail to match the requirements of the National Collective Agreement for the principal construction sector.
  3. Administrative / Handover: Forfeiture of claims for additional work or daywork unapproved when the strict verification deadlines under standard SIA 118 expire, preventing final close-out of project accounts.

Financial close-out on a Swiss construction project is a decisive phase in which the contractor's profit margins clash with the budget-monitoring duties of the site management. Governed by standard SIA 118 and the Code of Obligations (CO), the final account procedure establishes a strict timeline starting as soon as the works are completed. The contractor must submit its detailed final invoice within a contractual deadline of two months, incorporating all joint quantity surveys, previous advance payment statements, any change orders, and countersigned daywork sheets. This submission turns the outstanding claim into an enforceable debt while formally starting the review window reserved for the client's professional representatives.

Upon receipt of the full file, the site management has a 30-day verification window to review arithmetical accuracy, check unit prices, and verify the validity of extra costs claimed. The key challenge at this stage is joint agreement on the balance due and the execution of the final discharge receipt. Affixing a statement of full settlement without explicit reservations extinguishes every financial claim arising from the contract for work and services (art. 363 CO). Site managers and project leads must master these mechanisms to avoid procedural forfeitures and safeguard payment rights (art. 372 CO) against the risk of unilateral deductions.

Preparation Procedure and Timeline for the Account Under SIA 118

The financial close-out of a contract for work and services follows a strict sequence of verifiable actions. The physical completion of the work and the handover of the structure trigger mutual obligations. Under standard SIA 118, the contractor has a contractual deadline of two months after completion to submit its full final account. This dossier summarises every contract item: mature advance payment applications, definitively approved joint quantity surveys, countersigned daywork sheets, and accepted price addenda.

Once the site management receives the file, the verification clock starts running. The site management has a contractual period of one month, or thirty days, to audit supporting documents, match calculations with construction site records, and notify the contractor of its findings. Under Swiss law, the price of the work becomes due under the principle set out in art. 372 CO, which states that the price is payable upon delivery. However, contractual incorporation of standard SIA 118 amends this timing by conditioning payment of the final balance on the joint verification of the final account.

Where the contract for work and services is agreed as a lump-sum price under art. 373 CO, the contractor performs the work for the fixed sum and cannot claim any increase, even if the work required more labour or expenditure. Conversely, if the price was fixed approximately under art. 374 CO or based on a bill of quantities with unit prices, verification requires meticulous scrutiny of actual measurements. Where an approximate quote is exceeded disproportionately without the client's doing, art. 375 CO grants the client rights of reduction or termination, making the final account phase critical for resolving disputed line items.

The Receipt in Full Settlement: Legal Scope and Extinguishing Effect

The contractor's acceptance of the final account or the signature of a document bearing the note "in full and final settlement" constitutes a legal act with definitive property consequences. Under the general rules on contract formation set out in art. 1 CO, mutual and concordant agreement on the balance irrevocably extinguishes all claims arising from the executed work. Signing a receipt without reservation amounts to a waiver of any subsequent claim regarding quantity adjustments, omitted daywork, or price increases.

For the contractor, the main hazard lies in rushing to sign a receipt under pressure for quick cash. Once the receipt is signed without explicit written reservations, the client is discharged from every monetary claim tied to the performance of the works. If a dispute persists over items contested by the site management, the contractor must issue a partial receipt or record specific reservations stating the reserved items, the amount claimed in CHF, and the referenced schedules.

Comparative Table of Financial and Contractual Provisions

Financial phase Statutory regime under the Code of Obligations (CO) Standard SIA 118 regime Operational and cash-flow impact
Submission deadline General maturity upon delivery (art. 372 CO) Contractual deadline of 2 months after completion Practical loss of rights for undocumented claims
Verification deadline Audit as soon as practicable (art. 367 CO) Contractual deadline of 30 days for site management Temporary freeze on the balance during joint audit
Fixed-price project Lump sum remains unalterable except for unforeseen events (art. 373 CO) Lump sum remains fixed outside change orders Systematic rejection of supplements not pre-approved
Quote cost overrun Client's right to reduce the price (art. 375 CO) Mandatory prompt notice as soon as overrun is known Obligatory adjustment before submitting final account
Late payment Default interest of 5% p.a. from formal notice (art. 104 CO) Formal notice required to trigger interest Financial penalty in CHF against the defaulting debtor
Payment security Statutory mortgage lien within 4 months (art. 839 CC) Retention money or joint and several guarantee Risk of lien expiry if settlement negotiations drag on

Common Close-Out Errors and Financial Consequences

The first operational error is confusing contractual verification deadlines with the statutory limitation period for the statutory mortgage lien of craftsmen and contractors. Under art. 839 CC, the mortgage lien must be registered in the land register within four months following completion of the work. If final account talks exceed three months without an agreement, the contractor risks losing this property security for good, as settlement talks do not pause the statutory clock.

The second pitfall is failing to issue a formal demand when the balance is not paid on the agreed date. Under art. 102 CO, the debtor is placed in default by formal notice from the creditor, which triggers default interest of 5% per annum under art. 104 CO. Failing to deliver a written formal notice forfeits the contractor's right to claim this interest on an improperly withheld balance, costing several thousand CHF on larger construction sites.

Finally, on the site management side, informal sign-offs or prolonged silence regarding a final account can create contractual ambiguity. While art. 6 CO states that silence implies acceptance only in very specific situations where an express reply was not expected, letting the 30-day window elapse without written notice exposes the client to aggressive contractor claims and complicates any subsequent review of contested items.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following scenarios are illustrative examples designed to examine financial close-out mechanisms on Swiss construction sites, using representative figures and settings.

Scenario 1: Forfeiture of Statutory Mortgage Lien During a Measurement Dispute in the Canton of Vaud

On an office building construction site in the Canton of Vaud, a masonry general contractor with twenty-two workers completes the structural work on 30 June. The total contract sum is 1 850 000 CHF. The contractor submits its final account on 15 August, claiming a remaining balance of 145 000 CHF, which includes 42 000 CHF for additional earthworks.

The site management challenges the excavation quantities on 10 September and starts informal talks without drafting formal meeting minutes. Meetings continue until 15 November. The contractor then realises that the four-month window under art. 839 CC to register the statutory mortgage lien expired on 30 October. Having failed to seek provisional entry with the competent court or secure equivalent security from the property owner, the firm has no in rem security to recover its 145 000 CHF balance from a client that has become insolvent.

Scenario 2: Signing a Full Discharge Receipt and Forfeiting Daywork Claims in the Canton of Geneva

In Geneva, a finishing work firm handles the thermal retrofit of an apartment complex. The initial approved quote stands at 380 000 CHF. During the project, acoustic remediation works are completed via daywork vouchers totaling 28 500 CHF.

At the final account meeting, the site management offers an immediate settlement payment of 35 000 CHF, while rejecting the daywork vouchers on the grounds that they were not properly signed. Eager to collect cash quickly, the business owner signs the financial statement stamped "in full and final settlement of all accounts under this contract". Two weeks later, the accounting team tries to bill the 28 500 CHF for daywork separately. Under art. 1 CO, this mutual concordant agreement permanently discharged the debt, leaving the daywork claim legally unrecoverable.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

What does the contractor risk if it fails to submit the final account on time?

The site management sets a reasonable grace period. If the contractor remains inactive, the client may have the final account drawn up by an independent third party at the defaulting firm's expense under standard SIA 118. The contractor then risks deductions for third-party fees, which can reach 5 000 CHF for illustrative purposes.

What should be done if the site management fails to review the account within 30 days?

The contractor issues a formal notice citing standard SIA 118 and art. 102 CO on debtor default. If no joint audit takes place, it demands immediate settlement of the mature balance, with default interest running under art. 104 CO.

Does accepting a partial bank transfer count as a full discharge receipt?

No, provided the contractor states an express written reservation upon receipt of payment. Under art. 1 CO governing the concordant expression of intent, failing to make a reservation on a reduced balance—such as a disputed difference of 25 000 CHF—can amount to tacit acceptance. A written, itemised dispute preserves all claims in full.

Does the 4-month deadline for a statutory mortgage lien run from delivery of the final account?

No, the strict deadline set by art. 839 CC runs from the completion of the physical work, regardless of subsequent accounting discussions. Waiting for the final account to be approved exposes the contractor to the forfeiture of their real estate lien securing an outstanding claim, for instance 80 000 CHF.

Can disputed daywork be included directly in the final account?

Yes, but each daywork item must be backed by valid daywork sheets in accordance with standard SIA 118. In the absence of a prior price agreement, remuneration is assessed under art. 374 CO based on the value of the work and the actual expenditure, supported by payroll and material receipts.

Does signing the final account extinguish the warranty for defects in the work?

Not at all. The final account settles only the financial aspects of the work. The client's rights regarding defects remain governed by art. 367 CO and art. 371 CO concerning the five-year limitation period applicable to immovable structures, as well as by the warranty provisions of standard SIA 118.

Mastering the financial closeout of a Swiss construction site safeguards your firm's profitability while preventing financial disputes over discharge receipts. To take your contractual management of quantity surveys and daywork further in line with professional standards, explore our dedicated resources: