- Legal / Joint Body / SUVA: Inability to meet social security contributions and collective agreement wages of installation personnel on paydays due to validation delays on monthly progress claims, exposing the company to penalties from the joint commissions established by extended collective agreements via the federal act on the extension of the scope of collective labour agreements.
- Administrative / Acceptance: Cash flow blockages at the end of the project following unjustified deductions on interim statements, forcing the contractor to initiate legal security proceedings through a statutory mortgage lien of craftsmen and contractors under art. 837 CC before the statutory deadline following completion expires.
When submitting a tender in French-speaking Switzerland, estimators and business owners often focus on the unit price and technical award criteria, leaving the payment schedule as a secondary concern. Yet, without an explicit contractual derogation, the works contract defined in art. 363 CO provides in art. 372 CO that the price is only payable upon delivery of the work, forcing the contractor to single-handedly bear the pre-financing of factory orders, raw material bookings, and engineering studies.
To maintain a positive cash flow as soon as work begins on site, the contractor must negotiate the formal incorporation of standard SIA 118 or agree on a schedule of advance payments backed by an initial advance payment when finalising the works contract. This approach safeguards the operational balance of the business against verification delays by the site management and secures the cash flow required to meet commitments to suppliers and production teams.
Mechanisms for Derogating from the Legal Framework and Structuring Advance Payments
The principle established by the Code of Obligations (CO) makes payment of the price conditional upon the full completion of the works. In construction contracts, this rule exposes the contractor to an unsustainable cash advance given the purchasing pace for bespoke supplies and the wages of installation crews. Agreement between the parties on an advance and progress payment schedule departs from this requirement upon conclusion of the contract under art. 1 CO. Incorporating standard SIA 118 provides a balanced framework that sets periodic advance payments calculated on the value of work completed and supplies delivered to the construction site.
For projects requiring substantial upstream factory orders, such as structural steelwork or prefabricated facades, ordinary procurement advances prove insufficient. The contractor must negotiate a pure order advance payment, paid upon signature of the agreement or notification of the award. In return for this financial advance, the client routinely demands a bank guarantee for repayment or a joint guarantee issued in the form governed by art. 492 CO. This instrument protects the client's funds against the risk of insolvency while providing the firm with the liquidity essential for paying deposits to its own suppliers.
In public procurement governed by the LMP, paying an initial advance requires total transparency right from the tender submission. The tender evaluation criteria set out in art. 29 LMP penalise any offer whose financial balance undermines profitability or breaches the conditions of the specifications. Contractors who formulate a financial condition during the finalisation stages of a public contract must ensure compliance with art. 11 LMP, which prohibits price negotiations in order to preserve equal treatment among tenderers.
Developing a Payment Schedule Aligned with the Expenditure Curve
Sustainable cash flow depends on aligning interim billings with physical production milestones. Two methods for calculating advance payments coexist on Swiss construction sites: measuring quantities actually executed through periodic site measurements, or using a projected milestone schedule based on measurable and undeniable physical stages. Monthly statements supported by joint inspection records guarantee payment in line with the actual volume built, thereby preventing disputes regarding the extent of the work performed.
When the parties agree on a fixed milestone schedule, each payment tranche must correspond to a verifiable physical stage: completion of special foundations, installation of the slab above the ground floor, or weatherproofing of the roof. This phasing eliminates subjective quantity disputes and allows for direct issuance of progress claims. The contractual retention money, typically fixed in the special conditions or under standard SIA 118, applies to each interim invoice until the joint verification of the work.
The following table analyses the financing methods used when contracting works in Switzerland:
| Financing Method | Basis and Trigger | Advantages for the Contractor | Requirements and Constraints for the Client | Risk Level for Cash Flow |
|---|---|---|---|---|
| Mobilisation advance | Signing of the works contract | Access to liquidity without an operating overdraft | Frequent requirement for a joint and several guarantee | Low (positive cash flow) |
| Monthly measurement-based advance payments | Joint inspection record of completed works | Payment aligned with actual outlays for the month | Heavy technical verification by site management | Controlled (30 to 60 days lag) |
| Milestone-based payment schedule | Completion of defined physical stages | Complete predictability of incoming cash flows | Direct visual verification without complex measurement sheets | Moderate (depends on adherence to schedule) |
| Advance payments on procured materials | Delivery to construction site or factory storage | Coverage of supplies prior to actual assembly | Verification of ownership of materials and insurance | Moderate (secures major purchases) |
| Single payment upon delivery | Final acceptance without contractual advance payments | No financial advantage for the contractor | Reduced administrative management during the execution phase | Critical (total pre-financing by the contractor) |
Common Negotiation Mistakes and Financial Deviations
Failing to specify payment deadlines coupled with default interest is a widespread oversight. When the agreement remains silent on processing times for interim claims, the client may defer payment without committing an immediate breach. Under art. 102 CO, the debtor is only placed in default through a formal reminder from the creditor or upon the expiry of a contractually agreed deadline. Without a formal due date, the contractor risks having to finance weeks of additional work before being entitled to claim the 5 % default interest provided for in art. 104 CO.
Another pitfall lies in accepting clauses that grant the architect excessive review periods for progress measurement claims. An accumulation of unapproved statements deprives the contractor of cash inflows, even though statutory duties towards subcontractors mandate regular payments. Under art. 364 CO, the contractor is responsible for carrying out the work diligently and procuring their own operating resources; bearing the cost of bank borrowing alone erodes operating margins by 4 % to 8 % over the entire project.
Furthermore, granting an advance without clearly formalising the rules for its progressive recovery creates frictions during the project. The contract must specify the percentage deducted from each monthly statement to amortise the initial amount. An improperly calibrated deduction right from the first month cancels out the benefit of the advance and plunges the financial balance back into deficit just as on-site staffing reaches peak activity.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and situations below are illustrative examples developed for the analysis of contractual management mechanisms.
Scenario 1: Structural work for an office building in the Canton of Vaud
A masonry and reinforced concrete contractor in Vaud with 28 employees is awarded a contract worth a total of 1 850 000,00 CHF. The initial specifications issued by the client's representative stipulated standard payment based on monthly statements checked within 60 days, without any advance. The immediate purchase of reinforcing steel and the booking of special formwork required an upfront outlay of 260 000,00 CHF.
During the contract finalisation meeting, the contractor proposed a mobilisation advance of 10 %, i.e. 185 000,00 CHF, accompanied by the provision of a bank joint and several guarantee compliant with statutory requirements. The parties agreed on phased recovery through a 15 % deduction on each monthly advance payment starting from the third progress claim, along with a payment period reduced to 30 days net. This adjustment preserved a positive bank balance throughout the superstructure phase, avoiding costly reliance on operating credit facilities.
Scenario 2: Curtain wall and metalwork installation in the Canton of Geneva
A steel construction SME employing 15 technicians and fitters is involved in a residential building project in Geneva for a total contract value of 920 000,00 CHF. The workshop manufacturing phase for sections and insulating glazing spans four months before any installation takes place on the construction site. The client refused any payment statement before on-site assembly work started.
The company highlighted the necessity of indexing the payment schedule to procurement and machining stages. The formal agreement established three preliminary tranches: 15 % upon submission of approved engineering working drawings, 25 % upon receipt of powder-coated sections in the fabrication workshops, and 20 % upon delivery of the first batch of complete units to the construction site. The balance was spread across actual installation and standard inspections. This sequencing eliminated the risk of negative cash flow during the 120 days of off-site manufacturing, ensuring timely raw material orders without compromising the firm's liquidity.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
How can an order advance payment be justified to the client?
Ordering specialised materials requires significant capital lock-up. Present a cash flow forecast demonstrating initial outlays in the region of 80 000.00 CHF. Under art. 364 CO, the contractor provides the tools and manages procurements, justifying an advance covered by a bank joint and several guarantee.
What does the Code of Obligations provide for the payment of advance payments?
Under art. 372 CO, the price of the work is payable at the time of delivery. Without an explicit contractual agreement for periodic advance payments, the contractor finances the entire project. It is essential to agree on monthly payment dates under art. 1 CO to safeguard the company's operating cash flow.
What guarantee can be offered to the client in exchange for an advance payment?
The initial advance, such as 50 000.00 CHF, is generally secured by a guarantee within the meaning of art. 492 CO. Issued by a bank or a recognised insurance company in Switzerland, this commitment protects the client against default without tying up the general contractor's day-to-day liquidity.
Does the statutory mortgage lien protect unpaid advance payments during construction?
Yes, pursuant to art. 837 CC, craftsmen and contractors may request the registration of a statutory mortgage lien for their claims relating to materials and labour. This step must be initiated no later than four months after the completion of the work, in accordance with art. 839 CC.
How should you react when site management delays the validation of an advance payment?
If payment is delayed on a monthly statement of 120 000.00 CHF, send a written reminder to put the client in default under art. 102 CO. Art. 104 CO grants default interest of 5 % per annum from the date of the formal notice, encouraging adherence to payment deadlines.
Can you suspend performance in the event of prolonged non-payment of an advance payment?
If an advance payment is overdue and unpaid, set a reasonable grace period for compliance pursuant to art. 107 CO. Once this deadline expires, the contractor may waive performance or terminate the contract, relying on the general rules governing contractual non-performance under art. 97 CO.
Contractually Securing Financial Flows in Works Contracts
Pre-contractual negotiation of mobilisation advances and monthly advance payments forms the fundamental pillar of positive cash flow balance. By aligning cash inflows with procurement orders and formalising a strict payment schedule, the contractor prevents the risk of financial distress. To explore the legal and contractual framework of your future tenders in Switzerland in greater depth, consult our specialised guides:
- Final Negotiation, SIA 1023 Contract Review, and Handover to Site Operations
- Explicitly Incorporating Standard SIA 118 into the Works Contract: It Is Not Automatic
- Auditing a Works Contract Form: Derogations Introduced by the Architect
- Unit Price, Lump Sum or Fixed Sum: Choosing the Remuneration Method Under Standard SIA 118