Construction Cost Code (CFC): Structure and Chapters 0 to 9

Master the CRB Construction Cost Code (CFC chapters 0 to 9) structure to price your tenders accurately without omissions or margin losses in Switzerland.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Incorrect allocation between chapters CFC 1, CFC 2, and CFC 3 leads to omissions in site installations or earthworks, causing non-recoverable cost overruns of around 5 % to 12 % of the total bid amount, with the contractor remaining bound by its price under art. 373 CO for a lump-sum price.
  2. Legal / Joint Body / SUVA: Omitting collective health and safety measures listed under chapter CFC 1 weakens compliance with worker protection requirements, exposing the bidder to joint-commission contractual penalties and exclusion from the procurement procedure under art. 44 LMP for failure to meet social criteria.
  3. Administrative / Acceptance: Incorrectly assigning three-digit codes when submitting the detailed quote disrupts the formal examination of bids under art. 38 LMP, risking distortions in the site management's comparative assessment and blocking administrative approval of the award file.

The Construction Cost Code published by the CRB forms the standardised financial framework of every property project in Switzerland. Intended for estimators, site managers, and business owners responding to public or private calls for tenders, this benchmark structures all project costs from chapter 0 (Land) to chapter 9 (Furnishings and equipment). Mastering this one-, two-, or three-digit hierarchy guarantees a rigorous review of tender packages, prevents the omission of ancillary services, and ensures quotes align perfectly with client requirements.

Within the scope of a works contract governed by art. 363 CO or subject to public procurement rules under the LMP, alignment between bill of quantities line items and CFC chapters determines the technical and financial accuracy of your bid. Understanding the link between structural work in CFC 2, external works in CFC 4, and secondary costs in CFC 5 shields your firm from budget allocation errors during the call for tenders.

Overall architecture of the CFC: logic of chapters 0 to 9

The Construction Cost Code structures project finances according to a sequential execution and trade-by-trade logic. For the tendering contractor, this classification is not merely an accounting nomenclature, but the cost allocation framework that sets the boundaries of contractual liabilities. Under the definition of a works contract in art. 363 CO, the contractor undertakes to produce a specific work in return for payment of an agreed price. Breaking down costs into single-digit chapters (CFC 0 to 9) groups expenditure by functional macro-lots, with each group then subdivided into two-, three-, or four-digit sub-chapters depending on the level of detail in the bills of quantities.

Breakdown of the ten main groups

The standardised CRB nomenclature is structured as follows:

  • CFC 0: Land. Land acquisition, easement compensation, transfer fees, notary costs, transfer taxes, and initial administrative boundary-survey procedures.
  • CFC 1: Preparatory work. Geological boreholes, contaminated site remediation, demolition, utility diversions, preliminary earthworks, excavation shoring, and shared site installations.
  • CFC 2: Building. All structural work and finishing work trades, including reinforced concrete load-bearing structures, masonry, structural steel or timber framing, waterproofing, facades, HVACSE installations (heating, ventilation, air conditioning, sanitary, electrical), and interior finishes.
  • CFC 3: Operating equipment. Fixed installations specific to the building's designated use, such as commercial kitchens, communal laundry facilities, hospital installations, or industrial machinery.
  • CFC 4: External works. Landscape retaining walls, external grading earthworks, private roads, buried pipes outside the building footprint, planting, fencing, and surface street furniture.
  • CFC 5: Ancillary costs. Building permit fees, construction-period insurance premiums, cantonal or municipal authorizations, temporary connections, and project legal or administrative expenses.
  • CFC 6: Contingencies and modifications. Financial reserves set aside for geotechnical uncertainties, site contingencies, and programme adjustments approved by the client.
  • CFC 7: (Reserved). Unallocated chapter traditionally retained for specific purposes or sectoral methodological expansions.
  • CFC 8: (Reserved). Reserved chapter in the standard building construction nomenclature.
  • CFC 9: Furnishings and fittings. Moveable furniture, demountable fittings, wayfinding signage, curtains, free-standing light fixtures, and interior decoration elements not fixed to the structure.

Allocation matrix and interfaces between related chapters

During tender price calculations, the risks of double counting or omission arise along the interface boundaries between chapters. The table below details the technical and financial demarcation rules that estimators must apply to safeguard company margins.

CFC HeadingScope of included worksFormally excluded worksCritical tendering interface
CFC 111 / 112Temporary access tracks, perimeter hoarding, shared site huts, temporary utility hook-ups.Trade-specific facade scaffolding serving a single trade, cranes dedicated exclusively to precast element erection.Interface with CFC 211 (Masonry) and CFC 214 (Scaffolding) for the breakdown of site logistics costs.
CFC 131 / 171Bulk excavation, general earthworks, trench shoring, groundwater lowering.Trench excavation for strip footings of the building, backfilling against subterranean walls.Interface with CFC 211.1 (Earthworks for building foundations).
CFC 211 / 212Raft foundation, slabs, in-situ cast concrete walls, load-bearing masonry, reinforcing steel.Waterproofing beneath raft foundation, external below-grade thermal insulation, heavy timber prefabrication.Interface with CFC 226 (Waterproofing and insulation) and CFC 214 (Prefabricated works).
CFC 232 / 242Boilers, heat pumps, fluid distribution, domestic water risers, indoor wastewater drainage.Buried collector drainage runs extending more than 1,00 m beyond exterior foundation walls.Direct interface with CFC 411 (External piping and connections to the public main).
CFC 412 / 421External paving, kerbs, asphalt wearing courses for vehicles, shrub planting, turf seeding.Paving slabs on pedestals located on a flat roof terrace of the building.Interface with CFC 226.3 (Waterproofing and protective surfacing on flat roofs).

Common breakdown errors and financial impacts on the offer

Misinterpreting the CFC breakdown leads to severe legal repercussions. Under art. 373 CO, when the price of the work is agreed as a lump sum, the contractor is required to execute the work for the agreed amount and cannot claim any increase, even if the works entailed higher expenditure than anticipated. If an item is described in the particular conditions of the bill of quantities under an incorrect CFC code and the bidder fails to price it, the bidder cannot cite chapter confusion to claim an addendum.

In public procurement governed by the LMP, art. 38 LMP provides that the contracting authority checks compliance with formal requirements and corrects obvious calculation errors ex officio, without the bidder being permitted to alter the substantive content of its tender. An incorrect allocation between CFC items can compromise the compliance check and result in the bid being excluded under art. 44 LMP if it appears abnormally low without substantive justification.

Typical financial variances encountered in practice involve:

  • Omitting temporary water and electricity connections (CFC 1): unexpected costs in the range of 14 500,00 CHF to 38 000,00 CHF on a medium-sized construction site.
  • Confusion regarding the disposal of contaminated soil (CFC 138 versus CFC 211): extra disposal costs at licensed landfills reaching 45 000,00 CHF to 120 000,00 CHF, borne entirely by the contractor if the overall lump sum does not expressly separate soil classifications.
  • Failing to account for waterproof penetrations in subterranean walls (CFC 226 versus CFC 250): retrospective remedial works costing approximately 18 500,00 CHF.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures set out in the cases below are illustrative examples intended to clarify technical choices and the application of CFC allocation rules.

Scenario 1: Multi-family residential building in the Canton of Vaud

On a 24-unit new residential construction project in the Canton of Vaud, the open-procedure tender package awards the structural work macro-lot to a mid-sized general contractor employing 35 site operatives. The bill of quantities lists the entire groundwater lowering work under chapter CFC 112 (Contractor's Site Installations), whereas general earthworks are listed under CFC 131.

The estimating team observes that the continuous six-month pumping volume was not broken down in the bill of quantities under a dedicated CAN daywork item. If the estimator includes this scope as a lump sum within CFC 112 without submitting a written reservation, the firm assumes the financial risk of excessive pumping costs calculated at 52 450,00 CHF in the event of heavy rainfall, pursuant to art. 373 CO.

The selected strategy consists of isolating dewatering pumping in the tender and requesting formal clarification from the site management during the question period of the LMP procedure, ensuring the item is paid based on a measured unit price under art. 374 CO, preventing any dispute regarding the final allocation of energy costs.

Scenario 2: Commercial building refurbishment in the Canton of Geneva

An invited public call for tenders in Geneva involves the thermal and technical refurbishment of a four-storey commercial building. The successful bidder deploys a team of 12 finishing work tradespeople. The tender documentation assigns raised access floors to CFC 281 (Floor Finishes) instead of CFC 272 (Raised Access Floor Systems and Service Ducts).

During the examination of tenders under art. 38 LMP, the contracting authority identifies a price anomaly within the interior flooring package. Through a meticulous CFC analysis, the bid manager demonstrates that the low-voltage cabling associated with floor boxes falls under CFC 232 (Heavy Current Installations) and cannot be assigned to the flooring contractor. This corrected breakdown protects the bid's financial integrity by maintaining a consistent price of 186 250,00 CHF for the interior finishes package, without risk of dispute during execution of the works contract.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

How should shared site installations be allocated between CFC chapters 1 and 2?

CFC 1 covers initial preparatory works, whereas CFC 2 encompasses building operational installations. An incorrect allocation distorts lump-sum pricing under art. 373 CO, creating a direct margin loss of around 45 000,00 CHF, including 8,1 % VAT.

Can the client require a CFC breakdown for a lump-sum offer?

Yes, based on the freedom of contract principle in art. 1 CO. Contracting authorities frequently require a breakdown by CFC chapters to assess the financial plausibility of the tender under the LMP, even if the total lump sum of 850 000,00 CHF remains agreed under art. 373 CO.

Does misallocating a CAN item to the wrong CFC chapter alter the contractor's obligation?

No. Under art. 364 CO, the contractor is responsible for the complete performance of their commitment. A structural element inadvertently classified under CFC 28 instead of CFC 21 still requires the successful bidder to execute the planned work, without unilateral additional costs for the client.

How does CFC 9 handle contingency reserves in public procurement?

CFC 9 contains the overall financial reserves managed by the client. In a public tender governed by the LMP, a contractor cannot add a contingency line to CFC 9: their price schedule must solely reflect the actual work priced with their fixed unit prices.

In the event of a dispute over a CFC 211 quantity survey, what notice period applies to the client?

For immovable work, the client has 60 days to report defects under art. 367 CO. If the masonry quantity surveys reveal defective work, the contractor must repair it, any clause limiting this right being strictly void under art. 368 CO.

Can the statutory mortgage lien under art. 837 CC secure work spread across multiple CFCs?

Yes, art. 837 CC protects all of the tradesperson's claims for the work performed. Whether the amounts fall under CFC 21 or CFC 22, entry in the land register must take place no later than four months after completion, in accordance with the requirements of art. 839 CC.

Operational mastery of the CFC 0 to 9 structure

Rigorously structuring bids according to Chapters 0 to 9 of the Code des frais de construction ensures contractual alignment between technical specifications and the financial breakdown of projects in Switzerland. To further streamline the compliance of your tenders and leverage standardised data exchange tools, consult our dedicated guides: