Skip to content
Art ConstructionTenders
Practical guide

Internal Handover Protocol: From Estimator to Site Manager

Internal handover protocol from estimator to site manager in Switzerland. Safeguard margins, CAN assumptions, and SIA 118 compliance.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Gross margin loss estimated for illustration purposes at between 4 % and 12 % of the contract award sum (i.e. in the range of 40 000 to 120 000 CHF for a 1 000 000 CHF work package), caused by omitting works priced outside the bill of quantities or misinterpreting a lump-sum price agreed under art. 373 CO without transmitting the detailed price breakdowns.
  2. Legal / Joint Committees / SUVA: Non-compliance of subcontractors declared during tendering leading to disputes with joint committees or contractor civil liability, not to mention breaches of duty of care under art. 364 CO requiring the contractor to secure the necessary tools and resources on the construction site.
  3. Administrative / Acceptance: Rejection of change orders or reservations on site due to failure to notify the client under art. 365 CO, compromising compliance with contractual requirements and future acceptance under standard SIA 118.

In Swiss building and civil engineering companies, the transition from tender award to actual construction site start is a major operational vulnerability. When the estimator finalises the bid based on a CAN specification or an estimated bill of quantities, critical data is gathered: selected technical variants, supplier discounts negotiated locally, productivity assumptions, and reservations stated in the tender submission. If this volume of information is not transferred to the site manager through a formal protocol, the site management and the client impose their own reading of the contract documents, eroding planned margins.

This internal handover protocol structures the full transfer of the technical and financial file from the estimating department to site management. It defines the critical review of specification items, the recalibration of labour outputs against applicable collective agreements, and the precise tracking of exclusions stated at tender closeout. By clarifying respective responsibilities right from the signing of the works contract governed by standard SIA 118 and art. 363 CO, the company ensures that the site manager holds the vital evidence to defend quantities, anticipate formal notices under art. 365 CO, and safeguard the final profitability of the works.

Operational structure of the internal handover file

The internal handover protocol between estimator and site manager anchors the accuracy of the estimated bid against contractual commitments. Under Swiss construction law, entering into a works contract pursuant to art. 363 CO obliges the contractor to deliver works in accordance with recognised trade standards while safeguarding financial balance. When the tender was drawn up using a bill of quantities based on the Standard Item Catalogue (CAN) or estimated quantities, the handover structures the transfer of contract documents, cost breakdowns, and logistical planning assumptions.

Composition of the technical handover file

The estimator provides a complete technical file containing annotated tender documents, minutes of clarification meetings with site management, and the full log of written confirmation requests. This package includes tender drawings, the data exchange file in standard SIA 451 format, and technical datasheets of proposed materials used to justify equivalences. The site manager also receives the inventory of priced technical alternatives, making it possible to identify technical leeway immediately prior to procurement negotiations.

Breakdown of unit prices and estimated productivities

The financial handover relies on sharing detailed calculation breakdowns by CFC code. The site manager must know the exact labour share, applied gross hourly rates, material wastage allowances, and estimated installation rates. If the contract is awarded on a lump-sum price basis under art. 373 CO, the contractor is bound to perform the works for the agreed sum and cannot claim extra payment for unforeseen work. The site manager must therefore clearly understand the limits of included services to identify any subsequent change orders.

Status of supplier quotes and selected subcontractors

The estimator formalises pricing commitments secured from local suppliers and partner firms during the call for tenders phase. Each external quote is transferred with its validity period, delivery terms, and negotiated discount level. Regarding subcontracting, the file includes certificates confirming compliance with minimum working conditions and minimum wages under the applicable collective labour agreement, allowing the site manager to satisfy administrative site inspection requirements without delay.

Comparative table: elements of the internal handover protocol

The transmission method must organize the handover systematically to prevent any contractual disputes with the client or site management.

Handover areaEstimator source documentSite manager operational targetConsequence of omission
CAN pricing structurePriced bill of quantities and calculation exportsMonitoring output rates and tracking hoursUncontrolled labour cost overruns
Remuneration structureWorks contract and tenderQuantity surveying or securing the lump sumInability to invoice works outside the lump sum
Material suppliersFirm quotes and technical datasheetsIssuing procurement purchase ordersFinancial losses from raw material price increases
SubcontractingSigned declarations and agreementsIntervention planning and site safetyBarred construction site access or contractual dispute
Tender reservationsLetters appended to the tenderProtecting interests against site managementTacit acceptance of unforeseen constraints

Common handover mistakes and their financial impacts

Omitting a formal handover meeting is the most damaging pitfall for company profit margins. A site manager deployed without reviewing tender reservations frequently accepts demands from site management that were originally priced as billable extras. For example, if the schedule of rates provided for the disposal of non-contaminated excavated material and the ground contains a different waste class, the lack of documentation prevents issuing an immediate notice under art. 365 para. 3 CO, leaving the contractor to absorb costs in the range of 25 000,00 CHF to 60 000,00 CHF.

A second error is the failure to communicate validity dates for subcontractor quotes. If subcontract prices were negotiated subject to placing orders within thirty days of tender award, site manager delays lead to unfavourable renegotiations. On a technical finishing work package, the resulting cost overrun commonly reaches around 15 000,00 CHF to 45 000,00 CHF, directly cutting into operating income.

Lastly, a mismatch between estimated production rates and workforce allocation leads to understaffing. If the project schedule requires reinforced teams to meet the delivery date under threat of contractual penalties or liquidated damages under art. 160 CO, the company is forced into emergency temporary hiring, generating unexpected extra costs in the region of 30 000,00 CHF.

Illustrative practical cases (typical scenarios on Swiss construction sites)

Figures presented in the following scenarios are illustrative examples intended to show the application of contractual management principles.

Scenario 1: Major refurbishment of an administrative complex in the canton of Vaud

On a structural work renovation and masonry contract awarded for 2 450 000,00 CHF under standard SIA 118, the average workforce planned by the estimator was eight workers. During the tender phase, the estimator had logged a written reservation regarding the client maintaining existing building services during demolition phases. The internal handover protocol enabled the site manager to refuse uncompensated temporary disconnections demanded by site management. By producing the reservation letter included in the handover file, an addendum for a change order of 48 500,00 CHF was approved, safeguarding work package profitability.

Scenario 2: Multi-family housing construction in the canton of Geneva

Under an earthworks and Special Foundations contract awarded as a lump-sum price for 1 180 000,00 CHF, the estimator had factored in using a local concrete plant with an 8,5 % volume discount. During the handover meeting, the site manager received full details of purchasing agreements along with the initial geotechnical report. When local excavation instability occurred, the site manager notified the client immediately pursuant to art. 365 para. 3 CO instead of carrying out trench shoring at the contractor's expense. This rigorous record tracking prevented absorbing an unplanned cost estimated at 37 800,00 CHF.

Scenario 3: Municipal civil engineering project in the canton of Fribourg

For an 820 000,00 CHF public roadwork contract awarded under an open procedure governed by cantonal rules harmonised with the LMP, the tender was based on precise asphalt quantity estimates. The handover protocol showed that paving rates were strictly conditioned on full night-time road closures. The site manager coordinated these requirements with municipal road services during the initial preparation meeting, avoiding crew downtime that would have caused daily losses of approximately 6 500,00 CHF.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

How should the transfer of estimator assumptions to the site manager be formalised?

Handover relies on a joint review meeting recording the specification, the data exchange file, and the list of reservations. On a project worth around 450 000,00 CHF, the site manager reviews production rates and subcontractor quotes to prevent discrepancies against initial productivity estimates.

What procedure should be followed if a quantity discrepancy is detected during internal handover?

The site manager verifies whether the works contract is based on a unit price or a lump-sum price. Under art. 373 CO, a lump sum binds the contractor, whereas a variance of around 35 000,00 CHF under unit pricing warrants an adjustment according to actual quantities executed.

Who verifies subcontractor compliance before the construction site opens?

The estimator forwards the tender inquiry files, then the site manager applies the checks required by the LDét. Art. 8c ODét requires putting organizational measures in place to demand proof of compliance with working conditions and net minimum wages by subcontractors.

How should a technical omission in the quote be handled before signing the works contract?

The estimator reports the variance to site management via a written addendum. Art. 1 CO states that a contract is concluded by mutual and concordant expressions of intent. Including this adjustment avoids financial disputes of around 18 500,00 CHF at project startup.

How does incorporating standard SIA 118 alter handover management?

Standard SIA 118 does not apply automatically; the parties must expressly stipulate it. It structures quantity measurement, time limits for notice of defects, and advance payment statements. This contractual standard protects a gross margin of around 42 000,00 CHF against on-site variances.

What is the estimator's liability if unrealistic deadlines are accepted?

The tender schedule binds the contractor as soon as the contract is awarded. In the event of a culpable delay without documented technical reservations, the client may invoke art. 160 CO if a contractual penalty was agreed upon, exposing the contractor to a contractual deduction that could reach, for example, 15 000,00 CHF.

The rigorous handover of the award file between the tenders department and operational site management ensures that margins are preserved and contractual commitments are strictly honoured. To explore in depth each legal and technical stage governing your contracts, consult our dedicated analyses:

Art Construction is an independent company: it is not affiliated with the SIA, CRB, SUVA, or KBOB. Referenced norms and standards point to publications from these bodies; only official versions are legally binding.