Skip to content
Art ConstructionTenders
Practical guide

Pricing the Annex Schedule and Daywork Rates in a Tender

Method for pricing the annex schedule and setting your daywork rates in Swiss tenders under standard SIA 118 and the CO, without eroding margins.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Underestimating hourly rates or handling surcharges leads to a gross loss of around 15% to 25% on unforeseen work, as the price is subsequently locked pursuant to art. 374 CO.
  2. Legal / Joint Body / SUVA: Proposing daywork wages below mandatory minimum scales exposes the tender to scrutiny under art. 38 LMP for abnormally low prices, or to exclusion from the procedure under art. 44 LMP in the event of non-compliance with art. 12 LMP.
  3. Administrative / Acceptance: Submitting an incomplete schedule or one that fails to comply with the contracting authority's requirements jeopardises the approval of daily site reports by the site management and delays the final account under standard SIA 118.

Pricing the annex schedule of daywork rates is a strategic step when submitting a tender in Romandy. This document sets the remuneration basis for labour, plant and materials for interventions that cannot be incorporated into measured bill items or initial lump sums. Too often neglected by estimators, an ill-calibrated daywork rate compromises the company's financial balance as soon as site contingencies arise, while also risking damage to the overall evaluation score in public procurement subject to the LMP.

To secure this component, the bid manager must align calculations with actual direct costs, social security contributions under the National Agreement and recognised trade practice under standard SIA 118. Complete consistency between primary unit prices and daywork schedules guarantees the technical credibility of the tender while protecting your operating margin.

Calculation method and structure of the daywork rate schedule

The annex schedule of daywork rates is a critical contractual document appended to the tender. In the Swiss procurement system, this document establishes the hourly and unit amounts payable for unforeseen or modified work ordered during construction. Once the offer is accepted pursuant to art. 1 CO, these rates become binding on the parties and apply to the contractor for any intervention not covered by a measured unit price or a lump sum.

Setting an hourly daywork rate does not mean applying an indicative rate sheet disconnected from the firm's real accounting data. The hourly selling price is the sum of four rigorously established components: base wages and statutory social security contributions set by extended collective labour agreements under the LECCT, operating overheads of the business, specific site overheads and the profit margin incorporating execution risk coverage. For tenders subject to the LMP, compliance with provisions on worker protection and working conditions under art. 12 LMP is a prerequisite for awarding the contract to tenderers and their subcontractors.

Analytical breakdown of the labour hourly rate

Daywork labour is broken down into precise categories within the price schedules of Swiss tenders. Tender forms traditionally distinguish between the foreman, the skilled plant operator, the mason or installer holding a CFC, and the labourer. The estimator must base the hourly rate strictly on the actual cost price, otherwise they risk operating at a loss when executing variation orders issued by the site management under standard SIA 118.

Calculating the hourly cost incorporates annual contractual working hours, statutory holidays, paid public holidays, contributions to early retirement funds such as FAR for the main construction trade or RESOR for finishing work in Romandy, as well as compulsory accident insurance under the LAA. Costs for personal small tools, personal protective equipment and staff transport are also included in the direct cost base before applying mark-up coefficients for overheads.

Remuneration of plant and machinery

Machinery provided on a daywork basis must be priced using two distinct methods in the schedule: per hour with a qualified operator, or per day excluding fuel and operator. The rate must cover the accounting depreciation of the machine, routine maintenance expenses, wear-and-tear repairs, fluids and lubricants, as well as civil liability and machinery breakdown insurance premiums. Omitting high-wear costs on heavy equipment such as backhoes or compressors leads to a steady drain on cash flow during long-running construction sites.

Supplies, materials and handling mark-up

For materials supplied under daywork that are not listed in the tender specifications, the contractor invoices net purchasing costs backed by supplier invoices, plus a percentage for procurement, handling, temporary storage, administrative overheads and profit. The customary percentage varies depending on local practice and specific clauses of the contracting authority, typically ranging between 10% and 15%. Any clause that arbitrarily caps this mark-up below real management costs must be thoroughly scrutinised during tender preparation to assess its economic viability.

Comparison of standard items in the daywork schedule

The table below illustrates the typical structure of an annex schedule for a structural work or civil engineering tender in Switzerland, as well as the financial impact of underestimating rates on the firm's execution margins:

Service categoryMandatory calculation componentsOperational risk or driftIllustrative financial consequence
Team leader or site foremanCLA wage, LPP, LAA, FAR contributions, site supervision, company vehicleMistaken for a skilled tradesman's wage without responsibility bonusUnderestimation of around 18,50 CHF per working hour
CFC-qualified tradesmanSkilled base wage, joint-body contributions, personal tools, safety PPEOmission of paid absenteeism costs and collective agreement bridging daysMargin loss of around 12,00 CHF per daywork hour
Site assistant or labourerMandatory minimum wage under the CLA, social security contributions, basic safety trainingFailure to comply with mandatory agreement scales monitored by the joint commissionRisk of tender rejection under art. 44 LMP for abnormally low prices
Tracked excavator (8 to 15 t)Financial depreciation, wear parts (teeth, tracks), fuel, hydraulic oilUnderestimating real consumption and on-site transport costsBilling shortfall of around 45,00 CHF per operating hour
Materials and miscellaneous suppliesNet purchase price invoiced by the supplier, site transport, unloadingAcceptance of a handling mark-up coefficient lower than actual overheadsGross loss of 8% to 12% on unscheduled purchasing volumes

Critical methodological errors when pricing the schedule

A common mistake among tenderers is blindly copying trade association rate schedules without adapting them to their own actual operating costs. An indicative rate sheet reflects neither the specific overhead rate of an SME nor its productivity constraints on a given site. Public contracting authorities check the consistency of daywork prices under art. 38 LMP, which mandates the review of tenders presenting abnormally low prices to ensure participation conditions are met and the call for tenders was properly understood.

A second pitfall lies in applying identical hourly rates to standard new-build work and to basement or confined-space operations. Where safety requirements mandate extended break times or dedicated ventilation, productivity drops dramatically. A contractor who failed to provide a dedicated item for these working constraints cannot unilaterally demand a price increase after signing, pursuant to art. 373 CO on lump-sum prices and general rules governing contracts for work and services under art. 363 CO.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures presented in the following scenarios are illustrative examples intended to clarify decision-making mechanisms when preparing a tender.

Scenario 1: Special underpinning work in the Canton of Vaud

Under an invited call for tenders for the refurbishment of an administrative complex in Lausanne, the contracting authority specifies a daywork schedule including an estimated 180 hours of skilled tradesmen for unforeseen core drilling and propping. The bidding firm calculates its direct hourly cost at 62,50 CHF, including social security contributions and paid leave. Factoring in 22% overheads and a 6% safety margin, the unit selling price is set at 80,00 CHF per hour.

A competing contractor submits an aggressive rate of 55,00 CHF per hour to boost its overall evaluation score. During execution, the site management orders 240 hours of actual variations under standard SIA 118. The company that priced its schedule properly secures a sound gross margin of 4 200,00 CHF on these operations, whereas the competitor incurs a direct loss of 1 800,00 CHF on labour, with no legal recourse against the client.

Scenario 2: Earthworks and slope stabilisation in the Canton of Valais

For a road infrastructure public contract in Sion, the contracting authority requests daywork rates for a 14-tonne excavator with operator and hydraulic rock breaker. The model firm breaks down its hourly plant cost into 110,00 CHF for the machine and 75,00 CHF for the CFC-certified operator, arriving at a combined quoted rate of 185,00 CHF per hour. This precise valuation safeguards its profitability when 85 hours of unforeseen rock clearing arise, generating total billings of 15 725,00 CHF (including 8,1% VAT), fully substantiated by site records and countersigned daywork sheets.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

Can you set a single flat daywork rate in a tender?

No, annex schedules require a detailed breakdown by trade category and equipment. The calculation is based on the value of work under art. 374 CO. An arbitrary single rate of 95,00 CHF exposes the tender to a request for clarification under art. 38 LMP for abnormally low prices.

How should travel allowances be included in hourly rates?

Allowances mandated by the collective labour agreement must either be integrated into the hourly rate or billed as a dedicated allowance line item of around 25,00 CHF. Art. 12 LMP requires compliance with local working conditions at the time the tender is submitted.

Can the client reject daywork rates after contract award?

No, acceptance of the tender constitutes a contractual agreement under art. 1 CO. The rates in the annex schedule apply automatically to work ordered outside the initial bill of quantities, pursuant to contract rules under art. 363 CO and standard SIA 118 provisions.

How does an overall tender discount affect the daywork schedule?

Unless expressly stated in the tender conditions, an overall tender discount does not automatically apply to hourly daywork rates. Contractors must verify whether the tender form enforces this deduction, which could otherwise erode their gross margin by around 5,00 CHF per hour.

What supporting documents should be prepared if the adjudicator audits daywork prices?

The contractor must present payslips complying with mandatory minimum wages, tool depreciation schedules and details of social security contributions. Art. 38 LMP allows the adjudicator to verify cost consistency before confirming the award under art. 41 LMP.

How should operating equipment not specified in the schedule be invoiced?

Unlisted materials are invoiced based on the contractor's actual expenses supported by accounting receipts, in accordance with the principle of art. 374 CO. Swiss practice applies an agreed surcharge factor to cover overheads, typically in the range of 10,00 % to 15,00 %.

Contractual control and profitability of annex schedules

Rigorous pricing of the annex schedule and daywork rates protects the contractor against financial losses when works are modified. To consolidate your price breakdowns and optimize your responses to calls for tenders in Switzerland, consult our specialized methodological guides:

Art Construction is an independent company: it is not affiliated with the SIA, CRB, SUVA, or KBOB. Referenced norms and standards point to publications from these bodies; only official versions are legally binding.