SIA 118 vs Code of Obligations 2026 Comparator (Deadlines, Defects & Guarantees)
Compare the SIA 118 standard and the revised Code of Obligations: deadlines, notices of defects and guarantees.
Interactive tool
A Legal situation simulator and warranty period calculator
1 Regime stated in the quote or contract
2 Date the contract was concluded
6 Nature of the defect (revised Code of Obligations)
Deadline for giving notice of defects
Other deadlines
- End of the 2-year notification period (art. 172 SIA 118)
- 5-year limitation period (art. 371 CO, art. 180 SIA 118)
SIA 118 guarantees on this amount
- Retention money on advance payments (Art. 150)
- Joint and several guarantee (Art. 181)
B Filterable comparison table: 10 key points
| Legal criterion | Former CO (contracts up to 31.12.2025) | New revised CO (from 01.01.2026) | SIA 118 standard (if incorporated into the contract) |
|---|
Indicative information prepared from the text of the revision of the Code of Obligations (FF 2025 18) and the SIA 118 standard (2013 edition). It does not replace a lawyer's advice.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="3.1"] in the content of a page on the site.
📄 Files and templates linked to this tool (free)
- PDFDOCX Works Acceptance Report (PV) (SIA 118 compliant) Complete 7-page guide (PDF) and Word template. Acceptance of the work (réception des travaux): legal basis, deadlines, start of the warranties and of the surety, three report templates (no defects, minor defects, postponed acceptance) and three letters. See the file, its mini-tool and the pack →
- PDFDOCX ⚖️ Pure Law Summary Table of Guarantees (CO 2026 vs SIA 118) & Rejection of a Late Claim Complete 6-page guide (PDF) and Word template. Notice of defects (avis des défauts), warranty and limitation, before and after 1 January 2026: CO and SIA 118 table, three letters including the rejection of a late claim, evidence and procedure in case of dispute. See the file, its mini-tool and the pack →
- DOCXPDF Defect Notice Templates & Duty to Notify (art. 25 SIA 118) Complete 7-page guide (PDF) and Word template. The contractor's duty to notify (devoir d'avis) before installation, the client's notice of defects (avis de défauts) after delivery, deadlines before and after 1 January 2026, the client's rights and four letters. See the file, its mini-tool and the pack →
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
What changes on 1 January 2026 in the Code of Obligations (Reform of art. 367, 368 and 370 CO)
The reform of contract-for-work law 2026 Switzerland (Act of 20 December 2024, "Construction defects", FF 2025 18) strengthens the client's position on three points: the time limit for reporting defects, the right to repair and the limitation period. It applies, in principle, to contracts concluded from 1 January 2026; earlier contracts remain subject to the old law. Many tradesmen and clients look for the difference between SIA 118 and the code of obligations: it is detailed below, line by line.
1. The end of the "immediate" notice (2 to 7 days): the new statutory 60-day period for reporting defects in real estate
Before 2026, the Code of Obligations required immediate notice of defects, with no numerical time limit: case law tolerated a few days, in the order of 2 to 7 working days, failing which the client lost his rights. For a building work, the revised law now gives 60 days to report defects (art. 367 para. 1bis CO) and 60 days from their discovery for hidden defects (art. 370 para. 4 CO). Any agreement imposing a shorter period is void.
This is the answer to the search "time limit notice of defects 60 days art 367 370 CO": the period is 60 calendar days; it also applies to defects of a movable work integrated into the structure and to those of an architect's or engineer's plan serving as the basis for construction. The calculator above gives you the exact deadline from your acceptance or discovery date.
2. The mandatory right to free repair (art. 368 para. 2bis CO) and the nullity of warranty exclusion clauses
The mandatory right to free repair is the second novelty: any clause agreed in advance that restricts or excludes the right to have defects repaired is void if the defect concerns a construction (art. 368 para. 2bis CO). The nullity targets free repair; the other warranty rights (price reduction, rescission) remain governed by the usual rules. The limitation period 5 years art 371 CO is maintained and can no longer be modified to the client's detriment (art. 371 para. 3 CO).
Practical consequence: an "exclusion of all warranty" clause in the general conditions of a contract concluded from 2026 no longer protects the contractor for the repair of a construction defect. It is better to take care over execution and over the acceptance report (PV).
Why the application of the SIA 118 standard is never automatic (and when it works against the tradesman)
The SIA 118 standard ("General conditions for the execution of construction works", 2013 edition) does not have the force of law: it applies only if the quote or the contract expressly incorporates it. Even when incorporated, it ranks after the text of the contract, the offer and the special conditions (art. 21). Before calculating a period, check the text of your contract: "Code of Obligations only" or "SIA 118 incorporated"? The tool above handles both cases.
1. The burden-of-proof trap during the 2-year guarantee period (Art. 172 to 174 SIA 118 vs Art. 367 CO)
SIA 118 gives the client a notification period 2 years from acceptance (art. 172) during which he may invoke defects at any time (art. 173). Above all, during this period the reversal of the burden of proof SIA 118 art 174 works against the contractor: in a dispute, it is for him to prove that a noted fact is not a defect (art. 174 para. 3). Under the Code of Obligations alone (art. 367 CO), the client must prove the defect.
After the 2 years, hidden defects are to be reported immediately after their discovery (art. 179 para. 2) and the client must prove that they constitute a breach of contract (art. 179 para. 5). The client's rights are time-barred after 5 years from acceptance, or 10 years for a deliberately concealed defect (art. 180).
2. Formal acceptance of the work (Art. 158 SIA 118), guarantee retention (Art. 149–152) and joint and several surety of 5% or 10% (Art. 181 SIA 118)
SIA 118 provides for a formal acceptance: the contractor notifies the site management of completion, the joint inspection takes place within one month and is recorded in a signed report (PV) (art. 158). During the works, the client retains 10% of the value of the services; if the consideration exceeds 500'000 CHF, the retention is 5%, at least 50'000 CHF, and at most 2'000'000 CHF unless otherwise agreed (art. 150). Before receiving the retention, the contractor provides a joint and several surety: 10% of the total sum, or 5% (at least 30'000 and at most 2'000'000 CHF) if it exceeds 300'000 CHF (art. 181).
| Contract amount excl. TVA (HT) | Retention money (Art. 150) | Joint and several guarantee (Art. 181) |
|---|---|---|
| 100'000 CHF | 10'000 CHF | 10'000 CHF |
| 250'000 CHF | 25'000 CHF | 25'000 CHF |
| 300'000 CHF | 30'000 CHF | 30'000 CHF |
| 500'000 CHF | 50'000 CHF | 30'000 CHF |
| 600'000 CHF | 50'000 CHF | 30'000 CHF |
| 1'000'000 CHF | 50'000 CHF | 50'000 CHF |
| 5'000'000 CHF | 250'000 CHF | 250'000 CHF |
Under the Code of Obligations alone, there is neither retention nor surety without a contract clause: the price is due on delivery (art. 372 CO). To date the deadlines of a specific site, use the calculator above; to claim an unpaid balance, see the statutory lien deadline calculator, and for quantities that change, the variation order calculator (art. 86 SIA 118).
Official Line-by-Line Comparison Table: Statutory CO Regime (before 2026) vs New CO (from 01.01.2026) vs SIA 118 Standard
| Legal criterion | Former CO (contracts up to 31.12.2025) | New revised CO (from 01.01.2026) | SIA 118 standard (if incorporated into the contract) |
|---|---|---|---|
| Acceptance of the work | After delivery, the client checks the condition of the work as soon as the normal course of business allows (art. 367 para. 1 CO). No formal acceptance procedure. | Unchanged: inspection and notice of defects after delivery (art. 367 para. 1 CO). The revision does not introduce formal acceptance. | Formal acceptance: the contractor notifies the site management of completion, the joint inspection takes place within one month and is recorded in a signed report (PV) (art. 158); the work is accepted at the end of the inspection if it has no defect (art. 159). |
| Notice of defects | Immediate notice: apparent defects from the inspection, hidden defects immediately after their discovery (art. 367 para. 1 and 370 para. 3 CO). Case law tolerates a few days (in the order of 2 to 7 working days). | Building work: 60 days to report defects (art. 367 para. 1bis CO); hidden defects: 60 days from their discovery (art. 370 para. 4 CO). Any agreement imposing a shorter period is void. | During the 2-year notification period from acceptance, defects can be invoked at any time (art. 172 and 173). Beyond that, hidden defects are to be reported immediately after their discovery (art. 179 para. 2); the minimum period of 60 days of the revised CO remains reserved. |
| Burden of proof | The client proves the existence of the defect after delivery of the work. | Unchanged: the client proves the existence of the defect after delivery. | During the 2 years, in a dispute, it is for the contractor to prove that a noted fact is not a defect (art. 174 para. 3). For a hidden defect discovered after the 2 years, it is for the client to prove it (art. 179 para. 5). |
| Right to rectification | The client may demand free repair if it does not entail excessive expense (art. 368 para. 2 CO). A clause may in principle limit or exclude it. | Right to repair maintained, and mandatory: any clause agreed in advance that restricts or excludes the right to have defects repaired is void if the defect concerns a construction (art. 368 para. 2bis CO). | The client first demands repair within a reasonable time (art. 169 para. 1 no. 1 and 174 para. 2); the costs are borne by the contractor (art. 170). Failing that: price reduction or rescission of the contract (art. 169). |
| Limitation of warranty rights | 5 years from acceptance for a building work (art. 371 para. 2 CO). | 5 years (art. 371 para. 2 CO). This period cannot be modified to the client's detriment (art. 371 para. 3 CO). | 5 years from acceptance (art. 180 para. 1); 10 years for defects that the contractor deliberately concealed (art. 180 para. 2). |
| Retention money on advance payments | No retention without a contract clause: the price is due on delivery (art. 372 CO). | Unchanged: no retention without a contractual clause. | Retention of 10% of the value of the services; 5% (at least 50'000 CHF) if the consideration exceeds 500'000 CHF; cap of 2'000'000 CHF unless otherwise agreed (art. 150). It secures performance until acceptance (art. 149). |
| Guarantee after acceptance | No bank guarantee without a contractual clause. | Unchanged: no guarantee without a contractual clause. | Joint and several surety (bank, insurance company or professional organisation) of 10% of the total sum; as soon as this exceeds 300'000 CHF, of 5% of the total sum (and not by bands), at least 30'000 and at most 2'000'000 CHF. It remains in force until the end of the 2-year notification period (art. 181). |
| Change orders and order modifications | No rule equivalent to art. 86 SIA 118: the agreed price applies, subject to the cases of art. 373 para. 2 and 374 CO. | Unchanged. | Quantity variation: the unit price remains valid between 80% and 120% (art. 86 para. 1). Beyond that, each party may demand an additional price for the quantity exceeding 120% or falling short of 80% (art. 86 para. 2), by variation order. New services: art. 87. |
| Daywork | No specific regulation: remuneration follows the contract or custom (art. 374 CO). | Unchanged. | Daily report drawn up and signed by the contractor; the site management returns it signed within 7 days and deals with discrepancies within one month (art. 47). Monthly invoices (art. 55), with no retention (art. 149 para. 2). |
| Payment terms | Price due on delivery (art. 372 para. 1 CO), unless otherwise agreed; default interest of 5% from the formal notice (art. 102 and 104 CO). | Unchanged. | Payment within 30 days (art. 190 para. 1); after this period, the client loses the right to the discount and the formal notice by demand starts default interest running. |
Sources: text of the revision of the Code of Obligations (FF 2025 18) and SIA 118 standard (2013 edition). Specialist sources point to an adaptation of SIA 118 to the reform (SIA 118-C1:2026): check the edition cited in your contract. Indicative information that does not replace a lawyer's advice.
Frequently Asked Questions on Defect Warranty and SIA 118 (FAQ)
1. What does the reform of the Code of Obligations change on 1 January 2026 for construction defects?
For contracts concluded from this date, four rules change (Act of 20 December 2024, FF 2025 18): notice of defects in a building work is given within 60 days (art. 367 para. 1bis CO); hidden defects are reported within 60 days of their discovery (art. 370 para. 4 CO); any agreement imposing a shorter period is void; and any clause agreed in advance that restricts or excludes the right to have defects repaired is void if the defect concerns a construction (art. 368 para. 2bis CO).
The limitation period remains 5 years, but it can no longer be shortened to the client's detriment (art. 371 para. 3 CO). Contracts concluded before 1 January 2026 remain in principle subject to the old law: immediate notice, for which case law tolerates a few days.
2. Does the SIA 118 standard apply automatically to my contract?
No. SIA 118 is only a set of general conditions: it applies only if the contract or the offer expressly incorporates it. Otherwise only the Code of Obligations applies, with its shorter rules and a different burden of proof. Even when incorporated, SIA 118 ranks after the text of the contract, the offer and the special conditions (art. 21).
Check therefore what your quote or your contract says: "according to the SIA 118 standard (2013)" or no mention. Specialist sources point to an adaptation of SIA 118 to the reform of the Code of Obligations (SIA 118-C1:2026): check the edition cited in your contract.
3. Who must prove the defect: the contractor or the client?
Under the Code of Obligations alone, it is for the client to prove the existence of the defect after delivery. Under SIA 118, during the 2 years following acceptance, in a dispute, it is for the contractor to prove that a noted fact is not a defect (art. 174 para. 3). After these 2 years, for a hidden defect, the burden of proof returns to the client (art. 179 para. 5).
Hence the contractor's interest in having the condition of the work recorded in the acceptance report (art. 158) and in documenting his services.
4. How much do the guarantee retention and the SIA 118 surety amount to on a contract?
For a contract of 250'000 CHF: retention of 10% on the interim payments, i.e. 25'000 CHF (art. 150), and joint and several surety of 10% of the total sum, i.e. 25'000 CHF (art. 181). For a contract of 600'000 CHF: the retention is 5%, with a minimum of 50'000 CHF, i.e. 50'000 CHF; the surety is 5% with a minimum of 30'000 CHF, i.e. 30'000 CHF.
The retention is capped at 2'000'000 CHF unless otherwise agreed. The surety (bank, insurance company or professional organisation) replaces the retention after acceptance and remains in force until the end of the 2-year notification period. Under the Code of Obligations alone, there is neither retention nor surety without a clause.
Indicative information that does not replace a lawyer's advice. Deadlines and amounts: see the articles cited.