The welfare block brings together changing rooms, mess room, toilets and the site office. Its size depends on the workforce; calculating the number of toilets and the changing room area per person is covered by the page on toilets, changing rooms and skips in the Site Layout Plan, Crane and Scaffolding studio. This page deals with the next question: where to put the containers so that workers reach them without crossing the work zone, water, electricity and wastewater arrive without unnecessary lengths, and the welfare block does not get in the way of any phase.
The Swiss Construction Work Ordinance (OTConst) lists sanitary facilities among the measures to be planned for the site, and Ordinance 3 to the Labour Act (OLT 3), with the SECO commentary, sets the hygiene principles for the premises. The detailed requirements are checked in those texts and with SUVA. The 2D Site Layout Plan studio places the containers to scale, with the temporary electrical board and water, on the Cabins and sanitary facilities layer.
Worked example: footprint of a five-container welfare block and its access path
The needs calculation, done separately according to the workforce, results in two changing rooms, a mess room, a site office and a sanitary container. The example containers measure 6.00 m by 2.50 m and stand side by side, with a 1.50 m path along the doors. Example dimensions, to be replaced by the hire company’s.
| Container | Dimensions | Footprint | Connections |
|---|---|---|---|
| Changing room 1 | 6.00 × 2.50 m | 15.00 m² | electricity |
| Changing room 2 | 6.00 × 2.50 m | 15.00 m² | electricity |
| Mess room | 6.00 × 2.50 m | 15.00 m² | electricity, water |
| Site office | 6.00 × 2.50 m | 15.00 m² | electricity, network |
| Sanitary container | 6.00 × 2.50 m | 15.00 m² | electricity, water, wastewater |
| Total containers | 5 × 15.00 m² | 75.00 m² | – |
Five containers set side by side along their long side form a row of 5 × 2.50 = 12.50 m by 6.00 m deep, i.e. 75.00 m². The 1.50 m path in front of the doors adds 12.50 × 1.50 = 18.75 m². The welfare block therefore reserves 75.00 + 18.75 = 93.75 m² on the plan. The sanitary container is placed at the end of the row, on the side of the wastewater connection, with the mess room next to it to share the water supply.
The temporary electrical board and the water point are placed as symbols; the distance from them to the row is measured on the plan and used to order cables and pipes. If space is short, the containers can be stacked on two levels with an external stair: the studio does not calculate their stability, which is for the hire company to determine.
Five containers and their path reserve 93.75 m², including 75.00 m² of containers, to be placed near the access and the connections, away from the work zone and the lorries’ route.
3 costly mistakes in placing the welfare block
A welfare block reached by crossing the site
If workers have to pass under loads or between machines to reach the changing room, the accident risk rises with every break. Place the welfare block near the gate, with access from the public road separate from the work zone, and draw this route as a named zone.
Toilets far from the wastewater connection
A sanitary container placed far from the connection means a holding tank or emptying runs, which cost more and are less hygienic. Place the connection point on the plan first, then the sanitary container as close to it as possible.
Welfare block placed on a future structure
Containers on the site of a future car park, retaining wall or permanent pipe will have to be moved during the works, with disconnections and the rooms out of use. Overlay the external works plan and check the welfare block in every phase.
Three-step guide to placing the welfare block
- Prepare the plan and the needs
Import the site plan and set the scale. Take the number of containers calculated from the workforce and mark the available connection points on the background. - Place the containers and services
Place the site cabins and site toilets, resize them to the hire company’s dimensions, name them, then add the temporary electrical board and temporary water. The legend lists dimensions and areas. - Check every phase and export
Switch from one phase to the next to check that the welfare block hinders neither the excavation, nor the lorry area, nor the external works, then export the plan as a PNG with the legend.
What the free version does not do for the welfare block
The studio does not calculate the number of containers or the area per person, does not check the requirements of the OTConst, OLT 3 or SUVA, and does not size the connections or the stacking of containers. It draws their layout to scale. Nothing is saved when the page closes, and the free export carries a watermark.
Portail chantier keeps the welfare block plan with the other phases of the site, keeps its versions and shares it with the contractors and the client.
Frequently asked questions
How many containers does my team need?
The studio does not calculate it. The page on toilets, changing rooms and skips in the Site Layout Plan, Crane and Scaffolding studio gives an estimate based on the workforce; the requirements are confirmed in the OTConst, OLT 3 and with SUVA.
Can stacked containers be shown?
The plan is a top view: two stacked containers occupy the same footprint. Name them accordingly (“Changing room, levels 1 and 2”); the stair and stability are the hire company’s responsibility.
Where should the mess room go?
Near the toilets and the water point, away from dust and machinery noise, with access that does not cross the work zone. The scale plan lets you compare several positions.
Are the container dimensions fixed?
No. The dimensions offered are indicative starting values: replace them with those of your hire company’s containers in the properties panel.