Site layout plan for a tight urban site: unloading, fences and buffer storage

On a tight plot every square metre counts: place the unloading bay, the buffer storage and the fences to scale before the first lorry arrives.

Open the free studio →

Free, no account: your plans, schedules and figures stay in your browser.

In town, the site often starts right at the edge of the pavement. The plot is barely larger than the building, the lorry cannot turn, pedestrians pass two metres from the excavation and deliveries have to arrive at the right moment because there is no room to store anything. A site layout plan drawn to scale shows straight away what fits, what does not and what has to be organised phase by phase.

The 2D Site Layout Plan studio opens in the browser, without an account. You import the site plan as a PDF or an image, set the scale on a known dimension, then place objects to scale: building footprint, lorry area with its indicative turning circle, storage area, fence drawn point by point, gate, skips, site cabins, temporary water and electrical distribution board. Each phase of the site can have its own plan.

Worked example: dividing a 660 m² urban plot between building, unloading and storage

A small apartment building to be built on a plot of 22.00 m by 30.00 m in an urban setting, with a single access from the street. The building occupies 16.00 m by 20.00 m. The site plan PDF is scaled in the studio on the dimensioned length of the plot. Example dimensions, to be adapted to the project and the actual vehicles.

Division of the plot during the structural phase (areas read from the studio legend)
ZoneDimensionsArea
Plot22.00 × 30.00 m660.00 m²
Building footprint16.00 × 20.00 m320.00 m²
Unloading bay12.00 × 3.50 m42.00 m²
Buffer storage6.00 × 4.00 m24.00 m²
Site cabins and skips30.00 + 15.00 m²45.00 m²
Remaining for traffic and excavation660.00 − 320.00 − 42.00 − 24.00 − 45.00229.00 m²

Once the scale is set, each object shows its dimensions and its area in the legend. The 660.00 m² plot loses 320.00 m² to the building, leaving 340.00 m². The unloading bay of 12.00 m by 3.50 m (42.00 m²), the 24.00 m² buffer storage, two site cabin containers (30.00 m²) and three skips (15.00 m²) take a further 111.00 m². That leaves 229.00 m² for traffic, the excavation slopes and the pedestrian route. The fence drawn around the perimeter measures 2 × (22.00 + 30.00) = 104.00 m, including a 6.00 m gate: 98.00 m of solid fence.

The remaining 229.00 m² looks comfortable, but a large part of it runs along the excavation and cannot be used for storage. The plan then shows that heavy materials must be delivered when they are installed, that the structural phase should be duplicated to draw the fit-out phase (the excavation is backfilled, the storage grows) and that the buffer storage should be kept for the day’s pallets.

Out of 660.00 m², 229.00 m² of circulation space remains once the building, unloading bay, buffer storage, site cabins and skips are placed: deliveries have to be planned to the day.

3 costly mistakes in laying out a tight urban site

Drawing the lorry area without its turning radius

A delivery lorry that cannot drive in forwards blocks the street, and its driver sometimes refuses to unload. In the studio, the lorry area carries an indicative turning circle: replace it with the one for the actual vehicle given by the supplier, then check that it touches neither the fence nor the building footprint.

Forgetting the pedestrian route in each phase

A closed pavement without an alternative route leads to a site stoppage or measures imposed by the municipality. Draw the route as a zone on a dedicated layer and check it in every phase: the position of the gate and the unloading bay often changes between the structural and fit-out phases.

Planning storage as if the plot were empty

On a small plot, storage planned on paper ends up at the edge of the excavation or in the path of machinery. Place the storage area to scale with its real dimensions: if it does not fit, the answer is delivery at the pace of installation, to be agreed with suppliers before submitting the bid.

Three-step guide for a tight site

  1. Import and scale the site plan
    Open the site plan as a PDF or an image, then set the scale on two points of a known dimension, for example the length of the plot. Without a background, you can also work on a blank sheet already to scale, in metres.
  2. Place the zones and objects of the structural phase
    Place the building footprint, lorry area, gate, fence point by point, storage area, skips, site cabins, temporary water and electrical distribution board. Switch on the grid and snapping to align the objects; the legend shows the areas as you go.
  3. Duplicate the phase and export the plans
    Duplicate the phase to draw the next state of the site, move what changes, then export each phase as a PNG image with its legend for the kick-off meeting and for the file submitted to the municipality.

Open the free studio →

What the free version does not do for an urban site

The studio draws and measures, it checks nothing for you: no automatic check of traffic rules, fire brigade access or municipal requirements. The safety pictograms are simplified symbols, not official signs. Cranes, their radius and oversailing the neighbours belong to the Site Layout Plan, Crane and Scaffolding studio, as does the occupation of the pavement in square metres per day (see that studio’s page on the public highway). Nothing is saved: closing the page erases the plan.

Portail chantier saves your site layout plans site by site, with all their phases and versions, and shares them with the team and the client; exports there carry no watermark.

Frequently asked questions

Can you draw a site layout plan without a site plan?

Yes. The studio offers a blank sheet already to scale, in metres: you place the building footprint, fences and areas directly with their dimensions. A background can be added later and scaled on a known dimension.

How do you show the lorries’ direction of travel?

The studio has no traffic arrow tool: draw the entry and exit with the gate, the lorry area and named zones on a dedicated layer, and check the turning circle. The legend lists the name of each zone.

How many phases should a tight site have?

At least one phase for each change of organisation: earthworks, structure, fit-out. The studio lets you add, duplicate and rename phases; each phase is exported separately.

Is the plan sent to a server?

No. The imported background and the objects stay in your browser; the studio contacts no server. In return, nothing is saved: export the plan as a PNG before closing the page.