2D Editor for Your Construction Site Layout Plan

Import a drawing or screenshot, set the scale, then place cranes, skips, site accommodation, and fences at their actual size.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

What a construction site layout plan is used for

The construction site layout plan sets out the spatial organisation of an operation before the first machines arrive on site. This drawing serves as a common benchmark for the site manager, general foreman, site management and the various trades working consecutively on the plot. It brings together traffic flows, crane positions, material storage areas and welfare facilities for site teams.

In Swiss practice, preparing this document during the planning phase clarifies access routes from public roads and allows provisional water and electricity connections to be scheduled. A detailed plan helps anticipate complex interactions between trades, mark out sorting zones for waste removal in accordance with local regulations, and protect neighbouring land. Plotting all these elements on a shared visual drawing prevents confusion when delivery lorries arrive at the site entrance.

This plan also serves as a key resource during site safety coordination meetings. It highlights emergency routes, dedicated pedestrian walkways separated from heavy plant tracks, and perimeter fencing. Well prepared, it offers valuable guidance for the site manager, who can verify the arrival sequence of temporary facilities and adjust the layout over the weeks without disrupting supplier turnarounds.

Importing a background and scaling it

The editor runs directly in your web browser with no account registration required. You can start your project on a blank canvas or import an existing background as a PDF file or an image. If you have an excerpt from a cadastral survey or a capture from swisstopo, you can load this image straight into the tool. The studio never contacts an external server: the file remains on your workstation, and the swisstopo capture loads just like any local image.

The editor's default unit of measurement is the metre. To ensure placed elements accurately represent your real ground footprint, scaling the background document is essential. The application provides three methods for this step:

  • By a known dimension: draw a line between two clear landmarks on your plan, such as an existing building facade or a plot boundary, then enter its actual distance in metres.
  • By the actual background width: enter the overall dimension of your document if you know the total width of the area covered by the image.
  • By a standard scale: directly apply a preset scale for a PDF document printed at one hundred per cent with no page scaling.

Once this step is confirmed, every new object placed on the drawing area automatically reflects your project's metric dimensions. Take a moment to zoom in on a detail to verify benchmark alignment before placing major site installations.

Placing objects: cranes, skips, site cabins, fences, truck areas

The tool provides a library of common objects for organising your construction sites. Every element placed on the plan has editable dimensions so that it can be adjusted to your actual equipment. You can rotate objects, change their length or width, and move them with the keyboard or with touch controls.

The library brings together the equipment that is essential to site life:

  • Site cranes: place tower cranes or self-erecting models. The tool draws the circles that correspond to the jib length and the counter-jib radius, so that you can see the swept areas.
  • Waste sorting skips: position the containers reserved for the different materials to be removed, close to the removal areas or under the lifting radius.
  • Site cabins and sanitary facilities: lay out the site trailers, the office containers for site management, the canteens, the changing rooms and the toilet cabins.
  • Fences and access: draw the perimeter enclosures, the guide barriers and the access gates for vehicles and pedestrians.
  • Truck areas: draw the delivery and unloading zones, including the turning radii that heavy goods vehicles need for their manoeuvres.
  • Utilities and signage: place the temporary water supply points, the electrical distribution boards and the site information signs.

These elements make it possible to set out a site footprint that is legible for everyone involved before earthworks or structural work begin.

Alerts: overlapping cranes and restricted oversailing

The presence of lifting equipment requires particular vigilance on the site layout plan. Two cranes erected on the same plot or on adjacent construction sites may have overlapping working radiuses. Furthermore, a crane jib must not oversail neighbouring inhabited plots, houses, railway lines or sensitive public spaces without prior arrangements.

To help you identify these critical issues while drawing, the editor includes automated visual alerts. As soon as the jib radiuses of two cranes touch on the plan, the system highlights this overlap immediately. This visual prompt lets you reassess crane base locations or adjust planned jib lengths before locking down the layout.

Users can also draw custom polygons to demarcate oversailing exclusion zones, such as an adjacent school, a neighbouring roof or an overhead power line. If a crane's slewing radius enters this protected area, a visual alert appears on your screen. This feature highlights site constraints right from the preliminary sketch stage. It assists in preparing permit applications and determining sectors requiring slewing restriction systems or electronic travel limits.

Phases, layers and legend

A construction site is never static. Ground layouts change significantly between initial earthworks, pouring the structural work, finishing work and exterior landscaping. The editor incorporates a phasing system stored in your browser's active memory. This allows you to organise your site setup according to scheduled works progress and toggle from one stage to another.

Layer management lets you separate base plan structural elements, temporary walkways, utilities and movable objects. You can show or hide specific layers to print one view dedicated to lorry movements, and another focusing on site huts and rebar storage areas. Undo and redo functions make quick adjustments easy without risking the loss of previous arrangements.

As you add equipment to your plan, the tool automatically compiles a summary legend. Every placed object type (crane, skip, office container, fencing, distribution board) is catalogued with its graphic symbol. There is no need to type out a key manually: the legend remains synchronised with the visible content on your drawing. Once your plan is complete, you can generate a PNG image export bearing the Art Construction watermark for your planning files.

The costly mistake on site

On site, teams often order and take delivery of office containers or skips on day one without accurately mapping out articulated lorry swept paths at the site entrance. The driver arrives with the first delivery of mesh or precast components, but the turning angle from the cantonal or municipal road is too tight due to a fence or skip placed too close to the gate.

The lorry ends up stranded across the public highway, blocking local traffic. An all-terrain crane or additional lifting gear must then be called out urgently to relocate site huts already hooked up to provisional water or electrical supplies. This disruption derails the morning schedule, incurs haulier waiting charges and strains relationships with neighbours and local highway authorities.

The simplest way to avoid this setback is to systematically draw the full delivery bay and swept path radius on your plan before setting the positions of permanent fences and cabins. By verifying in the 2D editor that the turning area remains unobstructed by fixed objects, you secure access from day one and ensure a smooth vehicle flow without having to reorganise the site in an emergency.

What the free version does not do

The free tool accessible in your browser is designed for quick, straightforward drafting, but has technical limitations that should be noted before you start:

  • Top-down view only: drawing is strictly in 2D. It does not account for hook heights or ground elevation changes, nor does it calculate safe working loads, wind loading or cable reach. The tool is a visual planning aid and must be approved by the site safety manager.
  • Indicative dimensions: dimensions for library objects are standard baseline values. You must always check and input exact measurements supplied by your equipment hire companies and suppliers.
  • Symbols not to scale: safety signage, standpipes and distribution boards are shown as enlarged pictograms to remain legible on an overview drawing; they do not represent the physical footprint of this equipment.
  • Indicative pictograms: graphic symbols provided are reference icons only and do not replace statutory safety signage required under current regulations.
  • PDF background resolution: a PDF imported as a background is converted into an image once upon opening. Zooming in closely on fine details may appear blurred.
  • No cloud storage: the free tool operates without registration and saves no data online. If you close or refresh your browser tab, your work is reset entirely. You must export your PNG file before leaving the page. In addition, the free version does not include price items or pricing data from the ACIP database.

To prepare your calls for tenders ahead of site setup, you can also view our dedicated module for tenders.

Upgrading to the Portail

For general contractors, site supervision practices and trade contractors managing multiple operations at once, advanced features are available in our paid solution, the Portail. This platform removes the limitations of the standalone editor by providing centralised management tools for your construction sites.

With the Portail, you benefit from:

  • Centralised cloud storage: save your multi-phase site layout plans directly within each construction site file hosted in the cloud, complete with version history. The background drawing is not sent to the server; only its alignment data is saved to keep file transfers light.
  • Resuming projects: reopen an existing plan at any point to update it as work progresses, without risk of data loss if your browser closes.
  • Team collaboration: Team Mode allows site managers, project directors and safety officers to collaborate on the same drawing within your shared workspace.
  • Professional exports: generate watermark-free exports in PNG or HTML format, customised with your company branding and colours.
  • Integrated cost estimation: price your site setup directly by linking quantities to the ACIP price database available to subscribers.

To discover all these management features and equip your project delivery teams, view our packages on the plans/pro/offre page.

Frequently asked questions

Are my data and construction site plans sent to your servers in the free version?

No. In the free version, the studio runs entirely in your web browser. No PDF files, images, site plans or vector data are sent to an external server. All processing takes place locally on your personal computer.

How do I save my site layout plan using the free tool?

The free tool does not include online storage. If you close your browser or refresh the page, your plan will be reset. You must export your drawing as a watermarked PNG image file before ending your work session.

Does the 2D editor calculate crane lifting capacity or height under hook?

No. The tool provides a 2D top-down view only to place bases and jib radius circles. It does not perform calculations for safe working loads, hook reach, mast height or wind resistance. These checks must be verified by the site safety manager.

Can I use a swisstopo map screenshot as a background plan?

Yes. Because the studio does not contact external servers, a swisstopo screenshot can be imported directly like any local image. You then simply use the scale tool to align the drawing's metric scale with your site's actual dimensions.

Are skip and site hut dimensions fixed in the object library?

No. Library objects include default measurements for reference only. Every item placed on the drawing area can be manually adjusted in length and width to match the exact dimensions supplied by your equipment hire companies.

How does the exclusion zone oversailing alert work?

You can draw custom restricted polygons on your plan, such as neighbouring residential properties or public roads. If the circle representing a crane jib enters this boundary, the application displays a visual warning on the plan to alert you to the overlap.

Is the ACIP price database available in the free version to estimate site setup costs?

No. The free version does not include pricing schedules or cost data from the ACIP database. You work solely on the graphical plan with your own figures. Estimating with the ACIP database is reserved for subscribers to our paid platform, the Portail.