Renovating an occupied apartment block, a shop that stays open or a school in use means working next to people who wear neither helmets nor safety shoes. Access routes must stay separate, dust contained, noise limited to certain hours and hazardous zones closed off. A mistake in the organisation costs complaints, interruptions and sometimes a halt to the works.
The 2D Site Layout Plan studio is used to draw this organisation to scale, floor by floor or sector by sector. You import the floor plan or the site plan, set the scale, then draw the work zones, the dust lobbies, the routes for residents and workers, the storage area and the fence. The studio’s phases represent the progress of the works through the building.
Worked example: renovating the bathrooms of an occupied block, riser by riser
A building of 12 flats on 4 levels, 3 flats per floor, remains occupied while the bathrooms and plumbing risers are renovated. The works progress by vertical riser of 4 flats. Each flat under works gets a dust lobby of 2.00 m by 1.50 m in front of its door. Example durations and dimensions, to be adapted to the project.
| Phase | Flats under works | Occupied flats | Dust lobbies | Duration |
|---|---|---|---|---|
| Phase 1: riser A | 4 | 8 | 4 × 3.00 = 12.00 m² | 5 weeks |
| Phase 2: riser B | 4 | 8 | 4 × 3.00 = 12.00 m² | 5 weeks |
| Phase 3: riser C | 4 | 8 | 4 × 3.00 = 12.00 m² | 5 weeks |
| Total | 12 | – | 12 lobbies, 36.00 m² | 15 weeks |
Each lobby measures 2.00 × 1.50 = 3.00 m². One phase affects 4 flats, so 4 lobbies, or 12.00 m² taken from the landings; meanwhile 8 flats remain occupied and must keep a clear route to the staircase. The three phases follow one another: 3 × 5 = 15 weeks, and 12 lobbies are installed in total, one per flat, for 36.00 m².
In the studio, phase 1 is drawn and then duplicated twice: only the work zones and the lobbies are moved from one riser to the next. Storage and the site cabins stay in the courtyard, away from the residents’ route, and the storage area is reduced to the materials for one riser, delivered phase by phase.
Three phases of 5 weeks, 12 lobbies of 3.00 m² and a clear route for 8 occupied flats in each phase: the site layout plan is the basis for informing the tenants.
3 costly mistakes when renovating an occupied building
Workers and residents sharing the same staircase without rules
Carrying rubble and materials through the shared staircase dirties and damages the walls and exposes residents. Draw the two routes on separate layers and, where they cross, plan time slots for transport, to be announced to the residents.
Forgetting the dust lobby and the protection of common areas
Without a lobby, demolition dust reaches the neighbouring flats and cleaning becomes an unplanned item. Draw each lobby as a zone to scale: it takes space on the landing, and that space must remain compatible with the residents’ escape route.
Keeping the same plan for the whole duration of the works
In an occupied building, the organisation changes with each riser, floor or sector. A single plan soon becomes wrong and residents receive contradictory instructions. One phase per stage, exported and displayed in the entrance hall, avoids these misunderstandings.
Three-step guide for a renovation in an occupied building
- Import the plan and create the layers
Import the floor plan or site plan and set the scale. Add free layers, for example “Residents”, “Workers” and “Work zones”, so that each family of objects can be hidden or locked. - Draw the first phase
Place the work zones, lobbies, storage area, skips and courtyard fence; draw the routes as named zones. The simplified pictograms (no unauthorised access, helmet required, first aid) help readability without replacing regulatory signage. - Duplicate for each stage and export
Duplicate the phase, move the work zones to the next riser or floor and rename the phase. Export each phase as a PNG with its legend for display in the building and for the meeting with the client.
What the free version does not do in an occupied building
The studio manages neither working hours, nor noise, nor air quality: these rules are set with the client, the building regulations and the municipal requirements, then written into the site instructions. It does not draw sections or 3D: floors are represented by separate backgrounds and phases. Nothing is saved between two visits, and the free export carries a watermark.
Portail chantier keeps each phase plan site by site, with its versions, and shares it with the client and the property manager: everyone sees the current phase without waiting for an e-mail.
Frequently asked questions
How do you draw a dust lobby in the studio?
As a rectangular zone to scale, named “Dust lobby”, on a dedicated layer. Its area appears in the legend; how the lobby is built (sheeting, closure, extraction) is described in the site instructions.
Can you make one plan per floor?
Yes: import the plan of each floor and use one phase per floor or per stage. The background is changed in the “Background and scale” panel, and each phase is exported separately as an image.
Does the studio suit a school or a shop that stays open?
Yes for drawing the zones, separate access routes and phases. Constraints specific to the operation (hours, evacuation, the shop’s deliveries) remain to be set with the operator and the competent authority.
Can the plan be sent to residents?
The free version exports a PNG image with a watermark, which is enough for a notice. Portail chantier lets you share saved plans without a watermark.