On a small block of 4 to 12 flats, the plot is larger than for a detached house, but there are more contractors and they follow one another for months. The bricklayer needs an area for formwork and reinforcement, the plasterer for boards, the joiner for doors; each wants to be close to the building and none must block lorry access. Without a plan, the areas fill up at random and everything is moved twice.
The 2D Site Layout Plan studio draws this division to scale on the site plan: building footprint, lorry area, storage areas named by trade, site cabins, skips, temporary electrical board and water point, fence and gate. Phases separate the structural works from the fit-out. For a detached house, the Site Layout Plan, Crane and Scaffolding studio has a dedicated page on the house.
Worked example: site layout for an 8-flat building on a 1,400 m² plot
A building of 8 flats with a footprint of 24.00 m by 18.00 m, on a 1,400 m² plot served by a road on one side only. Site plan PDF scaled in the studio. Example dimensions, to be adapted to the actual contractors and deliveries.
| Zone | Dimensions | Area | Phase |
|---|---|---|---|
| Building footprint | 24.00 × 18.00 m | 432.00 m² | all |
| Structural storage (formwork, reinforcement) | 10.00 × 8.00 m | 80.00 m² | structure |
| Fit-out storage (boards, insulation) | 8.00 × 5.00 m | 40.00 m² | fit-out |
| Site cabins (container block) | 12.00 × 5.00 m | 60.00 m² | all |
| Lorry area | 15.00 × 4.00 m | 60.00 m² | all |
| Waste sorting area | 9.00 × 6.00 m | 54.00 m² | all |
| Total site installations | 80 + 40 + 60 + 60 + 54 | 294.00 m² | – |
The 1,400 m² plot minus the 432.00 m² footprint leaves 968.00 m² around the building. The installations total 80.00 + 40.00 + 60.00 + 60.00 + 54.00 = 294.00 m², which leaves 674.00 m² for traffic, excavation slopes and areas to be preserved. In practice, fit-out storage is only needed after the structure: it can take over part of the structural area in the following phase, as the duplicated phase shows.
The temporary electrical board and water point are placed as symbols near the site cabins and the building entrance; their position sets the length of cables and pipes to be provided. The fence drawn around the perimeter gives its total length in the legend, useful for ordering the fence panels.
Of the 968.00 m² free around the building, 294.00 m² are reserved for installations; 674.00 m² remain for traffic without moving stock between two phases.
3 costly mistakes in laying out a small apartment building site
A single storage area for all contractors
When everyone stores in the same place, fit-out materials end up under structural ones and pallets are moved by hand. Name one area per trade and per phase: the studio legend gives its area, which helps to schedule deliveries.
Placing the site cabins where the permanent services will run
Containers set on the route of future pipes or on the future parking spaces have to be moved during the works. Overlay the external works plan as a background and place the cabins clear of future structures.
Underestimating the length of temporary supplies
An electrical board or water point too far from the cabins and the floors means extension leads, hoses on the ground and tripping hazards. Place the water and power symbols on the plan and measure the distances before ordering the site connection.
Three-step guide for a small apartment building
- Prepare the background and the layers
Import the site plan, set the scale on a known dimension, then use the layers provided (waste, cabins and sanitary facilities, fences and access, lorry areas, water and electricity, zones) and add free layers per contractor if needed. - Place the zones of the structural phase
Place the building footprint, lorry area, named storage areas, site cabins, sorting area, electrical board, water point, fence and gate. Resize and rotate the objects; the legend shows dimensions and areas. - Create the fit-out phase and export
Duplicate the phase, replace the structural storage area with the fit-out one, rename the phase and export each phase as a PNG with its legend for the site meeting.
What the free version does not do for a small apartment building
The studio does not calculate the number of containers, toilets or skips according to the workforce: those calculations are on the page about toilets, changing rooms and skips in the Site Layout Plan, Crane and Scaffolding studio. It does not size cranes and does not replace the site layout plan checked by the person responsible for site safety. Nothing is saved when the page closes.
Portail chantier saves the site layout plan of each building with its phases and versions and shares it with the contractors and the client; exports there carry no watermark.
Frequently asked questions
How does it differ from a site layout plan for a house?
The principle is the same, but a small block brings more contractors together at the same time: it needs storage areas per trade, larger site cabins and often several phases. For a house, see the dedicated page in the Site Layout Plan, Crane and Scaffolding studio.
Can each storage area be named?
Yes. Each object has an editable name, shown on the plan when the “Names” option is on and listed in the legend with its dimensions and area.
How do you show how the site evolves?
With phases: add or duplicate a phase for each stage (earthworks, structure, fit-out, external works) and export them one by one.