The Swiss Ordinance on the Avoidance and Disposal of Waste (OLED, SR 814.600) requires construction waste to be sorted: special waste is kept apart and disposed of separately, and the rest is sorted by category for recovery or disposal. For certain projects, the client also states in the building permit application how the waste will be disposed of (Art. 16 OLED). The details of the categories and thresholds are set out in the OLED and in the FOEN enforcement guidance on construction waste, to be confirmed with the competent cantonal office.
On site, these rules take the form of a sorting area: a row of skips, each with its stream, a closed container for special waste and an area where the skip lorry can reverse. The 2D Site Layout Plan studio places these objects to scale: the OLED sorting skip is renamed according to its stream, the legend gives dimensions and areas, and the sorting area is checked in each phase.
Worked example: area of a sorting area with four skips and special waste
An alteration project plans four streams in skips (mineral, wood, metal, combustible waste) and a closed container for special waste. The example skips measure 4.00 m by 2.00 m and stand side by side with 1.00 m gaps; the skip lorry reverses at right angles to the skips. Example dimensions, to be replaced by those of the haulier.
| Element | Dimensions | Footprint |
|---|---|---|
| Mineral skip (concrete, bricks) | 4.00 × 2.00 m | 8.00 m² |
| Wood skip | 4.00 × 2.00 m | 8.00 m² |
| Metal skip | 4.00 × 2.00 m | 8.00 m² |
| Combustible waste skip | 4.00 × 2.00 m | 8.00 m² |
| Row of 4 skips with gaps | (4 × 2.00 + 3 × 1.00) × 4.00 m | 44.00 m² |
| Closed container for special waste | 1.50 × 1.00 m | 1.50 m² |
| Lorry manoeuvring area | 11.00 × 10.00 m | 110.00 m² |
Four skips 2.00 m wide and three gaps of 1.00 m give a length of 4 × 2.00 + 3 × 1.00 = 11.00 m; at 4.00 m deep, the row occupies 44.00 m². The special waste container adds 1.50 m², placed apart and closed. In front of the skips, the manoeuvring area of 11.00 m by 10.00 m (110.00 m²) lets the lorry reverse and lift one skip without moving the others. The complete sorting area therefore reserves 44.00 + 1.50 + 110.00 = 155.50 m².
The number of skips and how often they are emptied depend on the quantities and the workforce: the page on toilets, changing rooms and skips in the Site Layout Plan, Crane and Scaffolding studio deals with that calculation. Here the question is placement: if 155.50 m² does not fit on the plot, the manoeuvring area can overlap the site’s lorry area, or part of the sorting can be done in a fixed facility, where the authority allows it.
In this example, a sorting area with four skips, a special waste container and a manoeuvring area takes 155.50 m²: to be reserved on the plan before work starts.
3 costly mistakes in organising waste sorting
A single skip for the whole site
Mixed waste costs more to dispose of and does not meet the OLED sorting obligation. Provide at least one skip per main stream, renamed on the plan, and mention it in the instructions given to subcontractors.
Special waste in the combustibles skip
Paint tins, solvents, fluorescent tubes or materials suspected of containing asbestos must be kept apart. Draw a closed container, separate from the skips, and on renovations check before the works whether a pollutant survey is required.
Skips placed without access for the skip lorry
A full skip that no lorry can reach blocks sorting for days. Place the studio’s lorry area in front of the sorting area and check the indicative turning circle against the real dimensions of the haulier’s vehicle.
Three-step guide for the sorting area
- Scale the plan and choose the location
Import the site plan, set the scale, then pick a level area, close to the access and away from excavations and building entrances, on the Waste layer. - Place and name the skips
Place one OLED sorting skip per stream, rename it (mineral, wood, metal, combustibles), adjust its dimensions to the haulier’s and add a zone for the special waste container. Switch on the grid to set the gaps. - Check the access and export
Add the lorry area in front of the skips, check its turning circle, read the areas in the legend, then export the plan as a PNG to attach it to the waste disposal plan and the site instructions.
What the free version does not do for waste sorting
The studio does not write the waste disposal plan, does not calculate volumes or the number of collections, and does not check compliance with the OLED: it draws the layout. The sorting categories and reporting obligations are confirmed in the OLED, the FOEN enforcement guidance and the cantonal requirements. Nothing is saved and the free export carries a watermark.
Portail chantier keeps the plan of the sorting area with the other phases of the site and shares it with the contractors and the client, who see the current version instead of an old copy.
Frequently asked questions
Which streams should the sorting area have?
Under the OLED, special waste is kept apart and the rest sorted by category; on an ordinary site this often means mineral, wood, metal and combustible waste. The exact categories are confirmed with the FOEN enforcement guidance and the cantonal office.
Is a waste disposal plan required?
For certain projects, the client must state in the building permit application how the waste will be disposed of (Art. 16 OLED). Which cases are covered and the form of the document are checked with the authority issuing the permit.
Does the studio calculate the number of skips?
No. It draws the skips to scale and gives their footprint. The number of skips according to the workforce and the type of work is calculated on the page on toilets, changing rooms and skips in the Site Layout Plan, Crane and Scaffolding studio.
Can the size of the skips be changed?
Yes. The sorting skip is a resizable object: enter the width and depth of your haulier’s skips. The legend shows the new dimensions.