Layout, Crane and Scaffolding Studio

Place crane, skips, fire route and scaffolding on a scaled Swiss map: checks and quantities, in the browser.

Support address: [email protected]

Studio Guide: Construction site layout plan, crane and scaffolding

This guide shows, step by step, how to set up a scaled construction site layout plan, check the crane, fire services access, logistics and facade scaffolding, and then export the result. The studio is free and runs in your browser.

The screenshots are in French. The letters (A), (B), (C)… refer to the red boxes in each image. The images come from the online studio, with demonstration examples (no real plan, no construction site address).
The studio controls are pre-sizing benchmarks with default values that you can modify. They do not replace the calculation note from the crane supplier or scaffolder, the construction site safety plan, or the decision of the competent authority.

1. Get started

1Identify screen areas

Everything happens on a single page. At the top: (A) the two views, (B) the duration and workforce of the construction site, (C) the export buttons, (D) the background plan. Below: (E) the object palette, (F) the top-down plan, to scale, and (G) the Properties, Alerts and Quantities panels. Below the plan is the checklist.

The two views, Construction site layout plan and Facade scaffolding, work on the same project. Everything is calculated in your browser: nothing is saved, and closing or reloading the page erases the work. Export before leaving.

Studio overview: (A) views, (B) duration and workforce, (C) export, (D) background plan, (E) palette, (F) plan, (G) right panels.
You can open an example directly with the studio address followed by ?preset=villa. The other values are metre_facade, toiture, rayon_grue, domaine_public, ancrage_vent, pompiers, macon_ite, logistique and electrique.

2Set duration and workforce

Enter (A) the construction site duration in weeks and (B) the maximum workforce in people. Check (C) the deconstruction or renovation box to plan for an additional sorting skip. These values are used to calculate the site toilets, site facilities and skips, and the rental in the quantities. Here: 20 weeks and 8 people.

(D) The Undo last action and Redo buttons undo and redo your actions: they activate as soon as the first change is made (200 levels).

Duration and workforce of the construction site: (A) duration, (B) workforce, (C) demolition or renovation, (D) undo and redo.

2. The background plan

3Search for an address

Type an address, a locality or a Swiss plot (A), then click on Search on map (B) or press Enter. The list (C) suggests the found locations: click on the correct one. You can also import your own plan (D).

Address search: (A) input field, (B) search button, (C) locations found, (D) plan import.
The address you are looking for and the displayed map area are requested from swisstopo, in read-only mode: an internet connection is required. If swisstopo does not respond, the plan remains usable on a white background, already scaled in meters.

4Choose the map

The plan is placed on the swisstopo map, at exact scale (approximately 0.20 m per pixel at maximum zoom). (A) The title recalls the location and scale. Choose (B) the aerial photo, (C) the national map or (D) the plot boundaries in addition, then adjust (E) the background opacity. (F) The Remove background button returns to the blank sheet.

swisstopo map background: (A) location and scale, (B) aerial photo, (C) national map, (D) plot boundaries, (E) opacity, (F) remove background.

5Import your PDF or image plan

Click on Import a PDF plan or image (A) and choose a PDF, PNG, JPEG or WebP file. The file remains in your browser. (B) As long as the plan is not calibrated, its scale is only indicative (here 0.083 m per pixel). (C) The Calibrate scale button corrects the scale, (D) the opacity makes the plan more or less pale, (E) Remove background removes it.

A protected PDF requires its password, which remains in the browser. For a multi-page PDF, a field allows choosing the page.

Imported plan: (A) import button, (B) indicative scale, (C) calibration, (D) opacity, (E) background removal.

6Calibrate scale on a known dimension

Click on Calibrate scale, then click the two ends of a known dimension on the plan: here the blue dimension of the example plan. In the window, (A) the studio gives the distance measured in the current background (66.34 units). Enter (B) the actual distance in meters (16 m here), then click on (C) OK.

Calibration window: (A) measured distance, (B) actual distance in metres, (C) validation.

7Check the calibrated scale

The background title (A) changes from "indicative scale" to "calibrated scale" (0.020 m per pixel). Distances, areas and plan checks can then be read at this scale. The view automatically reframes on the calibrated plan.

After calibration: (A) background title with calibrated scale.
The studio does not read the scale of a PDF: always calibrate the plan using a dimension you know. A heavily zoomed PDF becomes blurry because it is only rendered once.

3. Placing and editing objects

8Choosing an object from the palette

The palette groups objects by family. (A) Each family has a title, (B) an eye to hide or show its objects and (C) a padlock to lock them. (D) Click on an object (here a 7 m³ skip): it is armed. (E) The help line tells you what to do: click on the plan to place it, Esc to finish.

There are twenty-six to-scale objects: crane and load to lift, scaffolding perimeter, fire appliance access route and aerial ladder platform area, fire hydrant, power line and electrical cabinet, fences, gates, pedestrian tunnel, concrete mixer truck, skips, silo, site toilet, containers and zones. Hover the mouse over an object to read its description.

Palette: (A) family title, (B) eye, (C) padlock, (D) armed object, (E) help line.

9Drawing a fence, a route or a zone

Fences, the fire appliance access route, the power line, the scaffolding perimeter and zones are drawn. Choose the object (A), click each point (B), then double-click or press Enter to finish. (C) The help line counts the placed points: Backspace removes the last one, Esc cancels.

Drawing in progress: (A) chosen object, (B) placed points and segment being prepared, (C) help line.
Silent video of 21 seconds, captions in English: drawing the scaffolding perimeter around a building.
A drawing that is too short (missing points) is not placed: the studio warns you.

10Select, move and rotate

Click an object to select it (A): its properties open on the right (B). Drag it to move it: it snaps to nearby vertices and to the grid. Shift + click adds an object to the selection. The R key rotates by 15° (Shift + R in the other direction), Ctrl + D copies, Delete deletes, Ctrl + Z undoes and Ctrl + Y redoes. The mouse wheel zooms the plan. (C) The helper line reminds you of these actions.

Selected object: (A) skip outlined, (B) properties on the right, (C) helper line.
Muted video of 14 seconds, captions in English: select, drag, rotate, undo.
The arrow keys move the selected object by one grid step (Shift: five steps, Ctrl: 10 cm). Double-clicking on a side of a path adds a vertex, double-clicking on a vertex removes it.

11Modify an object's properties

The Properties panel provides (A) the name, (B) the x and y position in metres, (C) the rotation in degrees and (D) the dimensions. (E) If a plot boundary is drawn, the distance to this boundary is displayed (here 1.55 m); it turns red when the object leaves the plot. (F) Duplicate and Delete act on the selected object.

A value is applied when you leave the field (Enter or Tab key). Illegible text is flagged and ignored.

Skip properties: (A) name, (B) position, (C) rotation, (D) dimensions, (E) distance to the plot, (F) duplicate and delete.

12Hide or lock a family

(A) The eye hides all objects in a family: here the skips have disappeared from the plan. (B) The padlock locks a family: its objects can no longer be selected or moved, here the fences (C). Click again to revert.

Families: (A) eye on the skips (hidden), (B) padlock on the fences, (C) object from the locked family.

13Adjust grid and names

Below the background plan: (A) the grid is shown or hidden, (B) snapping aligns points to nearby vertices or to the grid, (C) the grid step can be chosen between 0.5, 1, 2, 5 and 10 m (here 5 m), (D) object names are displayed or not.

Grid: (A) display, (B) snap, (C) grid step, (D) names displayed.

4. The crane

14Choose model and jib direction

Place a crane, then click it: (A) the list offers eight generic models, from spider mini-crane to 60 m tower crane, without any brand. (B) Maximum radius and counter-jib, (C) maximum load and jib-end load, (D) jib direction in degrees. (E) On the plan, the green circle is the radius, the orange circle the counter-jib and the line the jib.

Crane properties: (A) model, (B) radius and counter-jib, (C) loads, (D) direction, (E) the crane on the plan.
The starting values of the models are indicative and editable: replace them with the manufacturer's data sheet. Changing model replaces the values you entered. The crane supplier's calculation note is authoritative.

15Read the permissible load at the cursor

Hover over the plan: (A) a tooltip and (B) the status bar below the plan give the distance to the mast and the permissible load at this location. Here, at 20.0 m from the mast: 944 kg. The further away, the less the crane lifts. Beyond the maximum radius, or too close to the mast, the studio writes "out of crane range".

Permissible load at the cursor: (A) tooltip, (B) status bar.
The curve follows a constant lifting moment: this is an indicative curve, not a manufacturer's load chart.

16Read supports and load chart

Further down in the crane properties: (A) the ground under the outriggers (asphalt, soil or entered value) and its permissible pressure, (B) the maximum reaction of an outrigger (103 kN here) and the minimum load-spreading plate (0.75 × 0.75 m), (C) the curve of the permissible load according to the distance to the mast. The points on the curve are the loads to lift placed on the plan: green if they pass, red otherwise.

Supports and curve: (A) ground and permissible pressure, (B) outrigger reaction and plate, (C) permissible load curve.

17Place a load to lift

Choose Load to lift from the palette and click on the plan (A). Enter its mass (B) (here 1500 kg). (C) For each crane, the studio gives the distance to the mast and the permissible load at this distance: crane A allows 1’113 kg at 36.5 m (too little), crane B allows 2’041 kg at 35.0 m (enough). The check is passed if at least one crane can lift the load.

Load to lift: (A) the load on the plan, (B) its mass, (C) allowable load of each crane at its distance.

18Read crane alerts

The Alerts tab (A) lists the alerts, numbered and coloured according to their severity; a badge indicates their number. (B) Crane A's jib extends outside the plot for 74 % of its rotation, up to 27.0 m: neighbour agreement or zone limitation must be arranged. (C) Two crane jibs overlap over 30.9 m: check the heights and the anti-collision device. (D) The circles are read on the plan.

Two-crane alerts: (A) tab, (B) jib outside the plot, (C) overlapping jibs, (D) plan.

19Jump from alert to object

Click an alert: the relevant object is selected and the plan centres on it (B), and its properties open (C). Return to the list using the Alerts tab (A).

After clicking an alert: (A) alerts tab, (B) plan centred on the crane, (C) crane properties.

20Keep distance from a power line

Draw the power line or catenary, then choose (A) its voltage (low or medium, railway catenary, high voltage) and (B) the safety clearance. Default values are 5 m, and 7.5 m for high voltage: to be confirmed with the grid or railway operator. (C) The hatched area marks the clearance zone around the line.

In the example, the jib passes 3.00 m from the line while the entered clearance is 5.00 m: the Power lines and railway line (crane safety clearance) line turns red.

Power line: (A) voltage, (B) safety clearance, (C) clearance zone, (D) plan.
The studio reports distance in top view only: jib heights do not dismiss any alerts.

5. Fire services access

21Draw the access route

Draw the axis of the route (E). The panel gives (A) the clear lane width, (B) the clearance height and gradient, and (C) the bend section, with the outer radius of each. (D) Under each radius, the studio indicates the required width at that radius: here 5.00 m. Default values are 3.50 m on straight sections, 4.50 m clearance height and a maximum of 12 % gradient.

Access route: (A) clear width, (B) height and gradient, (C) bends, (D) required width at bend, (E) the route on the plan.
These values come from the studio manual and are not checked against the AEAI directive or the authority's decision: confirm them with the competent authority (fire prevention).

22Place the ladder platform area and fire hydrant

(A) The route. (B) The aerial ladder platform area (11 × 4.5 m initially) must remain clear. (C) A 3 m diameter zone around the fire hydrant must remain clear. (D) An obstructing object (skip, fence, crane base within the route envelope) is flagged. (E) In the Alerts tab, the alert states that bend 1 has 3.50 m of clear width for 5.00 m required.

Fire services plan: (A) route, (B) ladder platform area, (C) fire hydrant, (D) nearby object, (E) alert.

6. Logistics and public land

23Count toilets, site accommodation and skips

When no object is selected, the Properties panel shows logistics. (A) Duration, workforce and renovation: here 18 people for 20 weeks. (B) The studio compares what you have placed with what is required: toilets 2 out of 2, site accommodation 29.6 m² out of 21.6 m² (2 20-foot containers), sorting skips 4 out of 4, with suggested streams. (C) The objects are visible on the plan.

The Sanitary facilities, site accommodation and waste sorting line in the checklist is green when everything is placed, orange when something is missing: it is never red.

Logistics: (A) duration and workforce, (B) counted toilets, site accommodation and skips, (C) the objects on the plan.

24Modify default values

Open (A) Editable default values at the bottom of the panel. (B) People per toilet (15), (C) room area per person (1.2 m²), minimum area (6 m²), usable area of a 20-foot container; then, for the fire services, (D) clear width of a straight section, clearance height, gradient, turning radii, ladder platform area and hydrant zone. The checks use your values immediately.

Modifiable default values: (A) title, (B) people per toilet, (C) area per person, (D) width of a straight section.
These values come from the studio manual and are not checked against the official source: replace them with those of your commune, canton or contract.

25Count public land

Draw Public land footprint (A) (occupied pavement or roadway). (B) The studio calculates its area (56.0 m²) and (C) the total public land footprint. The quantities list counts it in m²·day: area × 7 days × construction site duration, here 56.0 m² × 7 × 12 weeks = 4’704 m²·day.

Public land: (A) footprint drawn, (B) area, (C) total footprint.

7. Facade scaffolding

26Trace scaffolding perimeter

Select Scaffolding perimeter and trace it along the facades, like a fence. (A) The trace is displayed in blue. (B) The panel gives its length (52.00 m here) and the width of the working platform. (C) The Open in Scaffolding view button opens the Facade scaffolding view: the facade length is then read from the plan.

Scaffolding perimeter: (A) trace, (B) length, (C) open scaffolding view.

27Adjust scaffolding

In the Facade scaffolding view, the left column adjusts the scaffolding. (A) Include scaffolding in quantities and checks. (B) Length source: manual entry or sum of plan traces. (C) Facade length (24 m here), (D) height to eaves (8.5 m), (E) modular bay and (F) load class.

Lower down: storey height, top platform (empty = automatic), payload, platform width, platform-facade distance, cladding, anchor base material, anchor resistance, wind pressure, facade shielding, ground and fall height threshold. Reset to default values resets default values.

Scaffolding parameters: (A) include, (B) length source, (C) length, (D) height to eaves, (E) bay, (F) load class.

28Read elevation and cross-section

(A) The dimensioned elevation shows the facade with its bays, levels, staircase and anchorages (red points. (B) The cross-section labels top guardrail, midrail, toe board, anchorage, platform, base plate and distance to the facade. (C) Results are on the right.

Scaffolding drawing: (A) dimensioned elevation, (B) cross-section, (C) results column.

29Read results

(A) The list gives 10 bays of 2.57 m (length 25.70 m), 5 levels with top platform at 8.00 m (recommended range from 7.50 to 8.50 m), upright height (9.00 m), quantities surface (231.30 m²), access stair towers (1), load class 3, anchor grid (4.00 × 4.00 m: 3.54 kN for 6.00 kN resistance), upright base (7.19 kN for 30.00 kN) and base plate (0.20 × 0.20 m for ground of 200 kN/m²). (B) Scaffolding alerts are displayed below.

Results: (A) list of results, (B) scaffolding alerts.
The billed area does not drop below the standard pricing minimum (50 m²), displayed separately. The top platform defaults to 50 cm below the roof: you can enter it.

30Configure wind anchorages

Choose (A) the cladding (bare, dust protection net, weatherproof tarpaulin), (B) the anchor base material (reinforced concrete, perforated brick, timber), (C) the peak dynamic wind pressure at roof level and (D) the facade shielding (solid or open facade). The wind pressure is ENTERED: the starting value (0.9 kN/m²) is only an illustration to be replaced by the one from standard SIA 261 for your location.

Wind anchorages: (A) cladding, (B) anchor base material, (C) wind pressure, (D) facade shielding.

31Read the anchorage grid

If the standard anchorage pattern does not hold, the studio tightens it automatically: here the grid becomes 2.57 × 2.00 m (A), with 6.31 kN per anchor for 3.60 kN of resistance. (B) The alerts indicate that the pattern is tightened and, if even the tightest pattern does not hold, that an on-site pull-out test and chemical anchoring must be planned.

Anchorage result: (A) tightened anchorage grid, (B) alerts.
The coefficients come from the studio manual: the scaffolder's calculation note is authoritative.

32Plan the roofer's screen

Check (A) the roofer's screen for roofing work: the top guardrail then extends 0.80 m beyond the edge, or 1.00 m if (B) the guardrail is less than 60 cm from the edge. (C) Check the planned access stair tower and (D) the pedestrian walkway under the scaffolding (the studio reminds to protect the walkway). (E) The section shows the screen.

Roofer's screen: (A) roofer's screen, (B) guardrail near the edge, (C) stair tower, (D) pedestrian walkway, (E) section.
The requirement threshold for facade scaffolding (fall height exceeding 3 m) comes from the construction work ordinance (OTConst). It can be modified in the parameters.

8. Checks, quantities and exports

33Read the checklist

Nine lines below the plan update with every action: achieved (green), to check (orange), not achieved (red) or not applicable (grey). Here, (A) Wind anchors is red, (B) OTConst: facade scaffolding and containment wall is orange, (C) Access stair tower is green and (D) Power lines and railway line (crane safety clearance) is not applicable. (E) A reminder states that this check is indicative.

Checklist: (A) red line, (B) orange line, (C) green line, (D) not applicable line, (E) reminder.

34Read the quantities

Open the Quantities tab. (A) Each item is a record with its name, its CFC, its quantity, its unit and its calculation: mobile fence, crane (assembly and rental), site toilet, container, facade scaffolding and its rental, stair tower, public land. Here, 8 items and 485.73 m² of facade scaffolding. The quantities have no prices. (B) Export this bill of quantities (CSV) downloads the quantities.

Quantities: (A) item sheets, (B) CSV export.

35Export image, quantities or PDF

(A) Export image (PNG) downloads a single image: header, plan, checklist, quantities and notices, with the free version watermark. In view Facade scaffolding, it contains the elevation, section and results. (B) Export quantities (CSV) downloads the quantities. (C) Print or save as PDF opens the browser print. (D) A message confirms the export.

Exports: (A) PNG image, (B) CSV quantities, (C) PDF, (D) confirmation message.
If the swisstopo map cannot be read at the time of export, the image is exported without the map background, and the studio indicates this.

36Understand PRO buttons

The five buttons marked PRO (Save to a construction site, Load a project, Cost estimation with the ACIP database, Team Mode and Pro export without watermark) are not active in the free version. Each opens an information window (A): for example, the free version keeps nothing, closing or refreshing the page erases your work. (B) Continue for free closes the window: nothing you have entered is sent or saved.

PRO button information window: (A) window, (B) continue for free.

9. What this software does not do

  • It replaces neither the calculation note from the crane supplier or scaffolder, nor the site safety plan, nor the decision of the competent authority, and it provides no legal advice. The plan is not an engineer's plan and is not reviewed by the authority.
  • It works in top view only: jib heights do not clear any alerts. The load chart follows a constant lifting moment: it is not a manufacturer's load diagram, and the eight crane models are generic, unbranded, with indicative starting values.
  • Wind pressure is entered by you: the studio does not calculate it according to the location. Anchorages and standard bases are to be read using the coefficients in the studio's workbook.
  • Default values (lane width, clearance height, gradient, radii, ladder area, people per toilet, power line safety clearances, etc.) are not checked against the AEAI directive, the network operator or the ordinance: confirm them before relying on them.
  • The background map comes from swisstopo and requires an internet connection. A PDF or image plan must be calibrated against a known dimension: the studio does not read the scale of a PDF, and a heavily zoomed PDF becomes blurry.
  • The studio gives no prices and prices nothing. PRO buttons are not available in this version: there is no saving, no reopening of a project, and no sending to the quote.
  • Tests were carried out on a computer using Chrome. Firefox, Safari, touchscreens and paper printing were not tested.