About this tool
What a construction site Gantt chart is used for
A construction site Gantt chart serves as the common thread for organising the work of the various trades on the ground. Whether you are a site manager for a general contractor, a works supervisor or an architect, you must coordinate contractors and pace key stages, from earthworks through to handover.
On the construction site, a simple table of dates is not enough. The Gantt chart offers a visual representation of operations. Each horizontal bar embodies a task with its start date, execution duration and end date. By linking these bars together, you highlight technical dependencies between trade contractors. The mason knows when the earthmover clears the platform, the carpenter knows when the reinforced concrete slabs are ready, and the plasterer knows when the external joinery is installed.
This online tool allows you to structure your workflow directly in your browser. You visualise the logical sequencing of operations, curing periods and finishing work phases. You communicate a clear schedule to all stakeholders during weekly site meetings. The aim is to anticipate bottlenecks, secure deliveries and keep on track for the final date agreed with the client.
Thanks to direct manipulation using mouse and keyboard, you adjust durations and move bars as the construction site evolves. You thus have a clear overview to steer execution, prevent delays and verify the feasibility of the work rates put forward by each awarded contractor.
Structuring your schedule by CFC codes
To structure a construction schedule in French-speaking Switzerland, using the Construction Cost Code (CFC, Code des frais de construction) provides immediate clarity. Architects, engineers and trade contractors share this classification for tenders, bills of quantities and invoicing. Applying this same logic to the Gantt chart facilitates communication between the office and the construction site.
The interactive tool enables you to group tasks under clearly identified CFC codes. You can create collapsible groups and phases to structure your project hierarchically:
- CFC 1: Preparatory works (demolition, site layout staking, site clearance, site establishment).
- CFC 2: Building (earthworks, underground pipework, reinforced concrete, masonry, carpentry, facades, waterproofing, finishing work).
- CFC 4: External works (asphalt surfacing, kerbs, planting, fencing).
- CFC 5: Ancillary costs (laboratory testing, permits, site sign-offs).
By collapsing phases whose details are not needed during a meeting, you focus the teams' attention on the package currently being executed. For example, during structural work, you keep the details of CFC 211 (masonry and concrete) expanded while collapsing the activities of CFC 27 (painting) or CFC 28 (floor coverings).
Data entry is handled via the keyboard much like a spreadsheet, or directly with the mouse to lengthen or shorten a task. The durations shown in the starter templates are examples to be replaced with your own production times, calculated from your quantity take-offs and your crews' output rates.
Working days and cantonal public holidays
A common mistake in planning is counting in calendar weeks without distinguishing working days from rest days. On the ground, construction sites operate on working days, from Monday to Friday. Calculating the duration of works on an unsuitable calendar inevitably leads to schedule slippages.
This tool integrates a working-day calendar based on the public holidays of the 26 Swiss cantons. Movable holidays, such as Good Friday, Easter Monday or Ascension Day, are calculated from the date of Easter for each year. This avoids having to shift tasks manually when a bank holiday or religious festival falls in the middle of a concrete pour or timber frame erection.
The integrated cantonal public holidays were retrieved from official sources on 17 November 2026. Please note, however, that certain cantons remain marked as "to be verified" in the studio. In addition, half-days, local or communal holidays (such as Saint-Maurice, the Geneva Fast or regional fairs) are not all included by default. You must add them as custom non-working days in your schedule settings.
The same applies to annual leave mandated by collective employment agreements. Summer construction holidays or the winter shutdown of construction sites must be entered as custom non-working periods. Task bars automatically stretch visually to skip these non-working periods, giving an exact end date without altering the actual working duration.
FS and SS dependencies and the critical path
To build a logical schedule, you must link operations together using precedence relationships. The software handles two types of links:
- Finish to Start (FS): the successor task only starts once the predecessor is finished. This is the classic construction site link: floor tiles are not laid before the screed is poured. A positive lag can be added, for instance to respect curing time before laying the covering.
- Start to Start (SS): the successor task can start a certain time after the predecessor begins, allowing operations to overlap with an offset. For example, pulling electrical cables can start a few days after drylining begins, without waiting for all rooms to be enclosed.
By linking tasks, the calculation engine determines the critical path. This is the continuous sequence of operations for which total float is zero. Any day of delay on a critical task directly postpones the final handover date of the project.
The studio also calculates free float (the delay permitted without impacting the start of the next task) and total float (the delay permitted without impacting the project end date). These floats are clearly displayed to help you identify where to concentrate your management efforts. If you accidentally link a task to itself or create an impossible circular dependency, the studio detects the loop and displays a clear message to rectify the sequence.
Essential safety milestones
Occupational health and safety is an integral part of construction site management. Overlooking a collective protective measure or an administrative notice halts an entire team or exposes workers to serious risk. To help you in this process, the schedule templates include indicative safety milestones placed at key stages of structural work and finishing work.
These milestones serve as essential visual checkpoints during site planning:
- Written health and safety plan: scheduled before any work actually begins on site, to set out prevention measures and emergency response.
- SUVA notification for excavations: reminder to file notifications for excavations and trenches exceeding a depth of 1.50 m, requiring appropriate shoring or battering.
- SUVA notification for asbestos: milestone prior to any intervention on materials containing harmful fibres, before demolition or refurbishment.
- Scaffolding handover inspection: essential milestone before facade workers access the site, certifying the inspection of anchorages and guardrails.
- Fall protection: reminder to install safety nets, temporary guardrails and barriers as soon as the potential fall height reaches 2.00 m.
These milestones are provided on a purely indicative basis. Height and depth thresholds can be modified in the tool to adapt to each project's specifics. These points must be confirmed by the site supervisor in accordance with the applicable construction work ordinance and current SUVA directives, as the studio is not intended to replace formal regulatory consultation.
The mistake that costs dearly on site
On site, works supervisors often plan the pouring of a reinforced concrete slab without explicitly showing the curing period before striking support props, or schedule the installation of parquet flooring the very next day after liquid screeds are laid. The finish-to-start link is in place, but no technical drying allowance has been inserted.
The next trade contractor arrives on the construction site on the day stated on the paper schedule, finds that the substrate is not trafficable or that residual moisture prevents laying the floor covering, and leaves the site after filing a notice of work suspension due to adverse conditions or unprepared substrate. Finishing work then suffers an unexpected two-week delay, and subsequent trades can no longer access the site on the planned dates.
The action that avoids this costly mistake is to systematically create a specific task or a positive lag (timed offset) on the FS link to represent technical drying time, with no associated labour. By plotting this waiting time on the diagram, the critical path incorporates the mandatory wait, and no one plans premature work in an inaccessible area. The schedule thereby mirrors the physical reality of the installed building materials.
What the free version does not do
The tool available on this page is free, accessible without registration and without creating an account. It runs 100% within your web browser: no files, plans or entered data are sent to a server. This safeguards the confidentiality of your construction sites.
Conversely, the browser has no memory. Nothing is stored on a remote server: if you close your tab or refresh the page inadvertently, the schedule resets to zero. You must export your work before closing the window. The free version allows a CSV export bearing the Art Construction branding and a paper or PDF printout with a watermark.
Keep in mind the technical limitations of this version:
- The studio schedules tasks and their time dependencies, but manages neither resources (allocation of crews, plant) nor labour costs.
- No rates or pricing data from the ACIP database are included in this free version: you work solely with your own estimates and duration forecasts.
- The durations suggested in the starter templates remain theoretical examples to be tailored to the project specification.
- Public holidays recorded on 17 November 2026 require local verification for municipal holidays and collective company bridge days.
To prepare an advance schedule at the tender stage, you can explore our tools for your construction site tenders.
Upgrading to Portail
For general contractors, site supervision practices and trades managing multiple construction sites in parallel, standalone working has its limits as teams expand. By adopting the paid software Portail, you step up your collaborative management and ensure the long-term durability of your schedules.
Portail enables you to save your projects directly to a secure cloud space, load an existing site and keep successive versions of your calendar. You can lock in a baseline at the start of structural work to compare it continuously against actual site progress. The system then displays the exact variance in days for each phase of works, simplifying the justification of schedule addenda in the event of delays attributable to third parties or extra orders from the client.
With Portail, you benefit from Team Mode for multi-user collaboration on the same schedule, percentage-based tracking of actual progress task by task, and access to the ACIP price database to link lead times to your cost estimates. Finally, your schedule exports and printouts are generated without watermarks, customised with your corporate colours and logo for a professional presentation to your clients and partners. If you wish to learn more about our solutions for construction companies, take a look at our pro package.
Frequently asked questions
Is my construction site data saved on your servers?
No. In the free version, the studio runs 100% in your web browser. No files, plans or scheduling details are transmitted to a server. Closing or refreshing the page clears all your input. Remember to export your data before leaving.
How can I save my schedule to resume work later?
In the free online tool, there is no server-side saving. You must export your schedule in CSV format. To store your construction sites in the cloud, load archived projects and manage successive versions without risk of data loss, you need to use Portail.
Are public holidays for all Swiss cantons included?
The calendar includes public holidays for all 26 Swiss cantons, retrieved from official sources on 17 November 2026. Certain cantons are labelled "to be verified" in the studio. Local holidays, half-days and company shutdowns must be added as custom non-working days.
Do the safety milestones comply with statutory requirements?
The suggested milestones (excavations deeper than 1.50 m, work at height from 2.00 m, asbestos, scaffolding) are purely indicative. They can be modified and must be confirmed by the site supervisor in accordance with the applicable construction work ordinance and current SUVA directives. Art Construction operates independently of CFST and SUVA.
Can workers or costs be assigned to schedule tasks?
No. The free studio only schedules task sequencing and the timeline. It does not account for workforce allocation, machinery or financial costs. In addition, the free version contains no rates or pricing from the ACIP database.
How does the critical path calculation work in the studio?
The engine automatically identifies the sequence of tasks with zero total float—those that directly delay the completion of the construction site if their duration increases. The studio calculates free and total float and alerts you to dependency loops with a clear message.
What is the difference between the free export and the Pro export?
Exporting in the free version produces a CSV bearing the Art Construction label or a paper/PDF printout with a watermark. The Pro version on Portail creates watermark-free documents in your company colours, while enabling percentage-based tracking of actual progress.