Free software · 100% in your browser · no data sent

Building envelope schedule: roof structure, sheet metal work, roofing and façade up to weathertight and airtight

The envelope comes down to two dates, weathertight and airtight: build the schedule that sets them, with the scaffolding and the weather.

Open the free studio →

Free, no account: your plans, schedules and figures stay in your browser.

Until the building is weathertight, then airtight, the fit-out trades cannot move in. Yet carpenter, sheet metal worker, roofer, joiner and façade contractor share the same scaffolding for weeks, and each depends on the weather. An envelope schedule sets the order of works, shows who governs the two key dates and how long the scaffolding stays on hire.

In the construction Gantt schedule editor, jobs that overlap on the scaffolding are linked start-to-start with a lag, the others finish-to-start. The studio calculates the dates in working days, the float and the critical path. You add milestones for weathertight and airtight, as well as the indicative statutory milestones for scaffolding inspection and sign-off and fall protection, and a target end that keeps a visible weather reserve.

Worked example: envelope of a house with a pitched roof

A two-storey house with a traditional timber roof structure, tiled roof, copper sheet metal work, wood-aluminium windows and rendered external insulation. Example durations in working days, 5-day week; façade scaffolding erected and signed off before D1.

Envelope schedule: links and calculated dates (working days)
No. and taskDurationPredecessorsCalculated datesTotal float
1 Roof structure10 dnoneD1 to D100 d
2 Roofing underlay (temporary weathertight)4 d1 FSD11 to D140 d
3 Sheet metal work6 d2 SS+2D13 to D182 d
4 Roof covering8 d2 FSD15 to D2218 d
5 Windows (airtight)6 d2 FSD15 to D200 d
6 Façade insulation and render20 d5 FS; 3 FSD21 to D400 d
7 Scaffolding dismantling3 d6 FS; 4 FSD41 to D430 d

The roofing underlay, laid from D11 to D14, makes the building temporarily weathertight at the end of D14. The sheet metal worker starts 2 days after it begins (D13); roof covering and windows both start on D15, the day after the underlay. Airtight is reached at the end of D20 with the windows installed. The façade waits for the windows and the sheet metal work: it runs from D21 to D40, then the scaffolding is dismantled from D41 to D43.

The sheet metal work, finished on D18, is only needed by the façade at the end of D20: its total float is 2 days. The roof covering, finished on D22, is only needed by the dismantling: 18 days of float. The critical path runs through roof structure, underlay, windows, façade and dismantling: 43 working days. With a target end on D48, the schedule keeps 5 days of weather reserve for the façade.

Temporarily weathertight at the end of D14, airtight at the end of D20, scaffolding released on D43 with 5 days of weather reserve to the target end.

3 costly mistakes in an envelope schedule

Leaving the building open too long

A structure exposed to rain for weeks means wet slabs, delayed screeds and insulation to replace. Place the weathertight milestone straight after the underlay and treat it as a contractual date.

Working on the scaffolding without a sign-off milestone

Scaffolding used before it is signed off, or altered without a new sign-off, exposes workers and the company. Add the studio’s indicative scaffolding inspection and sign-off milestone and link it to the first task that uses it.

Paying for scaffolding for a façade that is waiting

Every extra week of scaffolding is invoiced. If the façade is waiting for windows delivered late, the dismantling moves back by as much: link the façade to the windows and watch this float closely, as it sets the hire period.

Three-step guide to scheduling the envelope

  1. List the jobs and the two milestones
    Create one row per envelope trade and two milestones, weathertight and airtight. Enter your contractors’ example durations and the canton for public holidays.
  2. Link the overlaps
    Link start-to-start what advances together on the scaffolding, for example “2SS+2” for the sheet metal work, and finish-to-start what has to wait. Add the indicative milestones for scaffolding sign-off and fall protection.
  3. Keep a weather reserve and export
    Enter a target end beyond the calculated end: the difference remains visible as float. When the weather stops the site, add the lost days as non-working days and see what is left. Export to CSV or print the sheet.

Open the free studio →

What the free version does not do for the envelope

The studio does not read the weather and sizes neither the scaffolding nor the protection measures: it places indicative milestones to be confirmed against the OTConst and the SUVA rules. It manages neither deliveries nor hire costs, and saves nothing: closing the page erases the schedule. For positioning the scaffolding and the crane, see the Site Layout Plan, Crane and Scaffolding studio.

Portail chantier saves the schedule and its versions on the site file, shares it with the envelope contractors and adds progress tracking: baseline, actual percentage and variance in days.

Frequently asked questions

What do weathertight and airtight mean?

Weathertight: the roof, or at least an underlay, protects the building from rain. Airtight: the windows and external doors are installed or temporarily closed. These are the two dates that open the way for the fit-out.

Must scaffolding be signed off before use?

Yes, the scaffolding is inspected and signed off before use, in line with the OTConst and the SUVA rules. The studio offers this milestone as an indication; the sign-off itself takes place on site.

How do you account for the weather in the schedule?

The studio does not forecast the weather. Keep a reserve with a target end, and enter the days actually lost as non-working days: the dates and the float are recalculated.

Does the studio draw the scaffolding?

No, the schedule editor only handles time. Positioning the scaffolding and the crane is prepared in the Site Layout Plan, Crane and Scaffolding studio.