A full renovation is not scheduled like new build. Before the strip-out, nobody really knows what the ceilings, ducts or old coverings hide: pipes to replace, floors to strengthen, materials containing asbestos. A serious renovation schedule announces a realistic date and keeps a visible reserve for these discoveries, instead of hiding it in every duration.
The construction Gantt schedule editor offers a “Renovation with asbestos survey” template to adapt. You enter durations in working days, link the tasks finish-to-start or start-to-start and set a target end: the studio calculates the dates, float and critical path. If the calculated end overruns the target end, the float becomes negative and you see the delay in days. The indicative milestone “SUVA notification: work involving asbestos” is added in one click and linked to the strip-out.
Worked example: renovating a four-room flat
A four-room flat from the 1970s, fully renovated: pollutant survey, strip-out, plumbing, electrical and heating services, partitions and ceilings, floors, painting. Example durations in working days, 5-day week; the target end is set at D55 to keep 5 days of reserve.
| No. and task | Duration | Predecessors | Calculated dates |
|---|---|---|---|
| 1 Pollutant survey | 5 d | none | D1 to D5 |
| 2 Milestone: survey known, SUVA notification if needed | 0 d | 1 FS | end of D5 |
| 3 Strip-out and demolition | 8 d | 2 FS | D6 to D13 |
| 4 First-fix services | 12 d | 3 FS | D14 to D25 |
| 5 Plasterwork, partitions and ceilings | 10 d | 4 FS | D26 to D35 |
| 6 Floors | 8 d | 5 FS | D36 to D43 |
| 7 Painting and finishes | 7 d | 6 FS | D44 to D50 |
The tasks follow one another finish-to-start: 5 + 8 + 12 + 10 + 8 + 7 = 50 working days, ending on D50, i.e. 10 weeks of 5 days. With a target end on D55, each row on the path shows a total float of 5 days: this is the contingency reserve, visible and shared, instead of being spread silently across every duration.
Suppose the survey reveals asbestos in the adhesive of an old floor covering. A row “Asbestos removal by a recognised contractor” of 6 days is inserted between the milestone and the strip-out. The end moves from D50 to D56: the float becomes 1 day negative against the target end. You know straight away that you must either announce one more day to the client or shorten a later task, for example by overlapping floors and painting with a start-to-start link.
The schedule fits in 50 working days with 5 days of reserve; a 6-day asbestos removal uses up the reserve and overruns the target end by 1 day.
3 costly mistakes in a renovation schedule
Starting the strip-out before the survey
Disturbing a material containing asbestos without a survey stops the site and may expose workers. Put the survey first and link the SUVA notification milestone to the strip-out: until the milestone is reached, the strip-out cannot start in the schedule.
Spreading contingencies across every task
Adding two days “to be safe” to each trade inflates the timescale without making it reliable, and the float disappears without anyone noticing. A target end with an explicit reserve shows how many days are left when a surprise occurs.
Plasterwork waiting on unchecked services
Closing partitions before the pipes and cables are checked means opening them again. Plan the inspection of the first-fix services as a milestone between services and plasterwork; its date is the one the electrician and the plumber must meet.
Three-step guide to scheduling a renovation
- Start from the renovation template
Load the “Renovation with asbestos survey” template, adapt the durations to your property and enter the canton and your non-working days. Delete the rows you do not need and add those for your site. - Add the milestones and the target end
From the statutory milestones panel, add the SUVA notification for work involving asbestos and the safety concept, link them to the strip-out, then enter the target end agreed with the client. - Test the surprise before it happens
Insert a row for asbestos removal or floor repairs and look at the new end and the float. If the test is no use, the Undo button reverts it. Then export the chosen version to CSV.
What the free version does not do for a renovation
The studio does not detect pollutants and does not decide whether a notification to SUVA is needed: it offers indicative milestones to be confirmed against the OTConst and the SUVA rules in force. It manages neither resources nor costs and saves nothing: closing the page erases the schedule, so export it to CSV.
Portail chantier saves the schedule on the site file, keeps its versions, shares it with the client and adds progress tracking with a baseline, actual percentage and variance in days per task.
Frequently asked questions
How long does a full renovation of a flat take?
The example comes to 50 working days, about 10 weeks of works, plus a 5-day reserve. The real duration depends on the floor area, the condition of the services and what the survey reveals.
Is an asbestos survey needed before renovating?
For a building constructed before 1990, a pollutant survey is generally required before works that affect the building fabric. Check the requirements with SUVA and your canton; the studio places the milestone in the schedule, it does not carry out the survey.
How do you show a contingency reserve?
Enter a target end later than the calculated end: the difference appears as total float on the critical path. If a surprise uses it up, the float drops to zero and then becomes negative.
Can two trades overlap?
Yes: a start-to-start link with a lag, for example “6SS+3”, starts painting three working days after the floors begin, room by room.