When a site falls behind, the question is not only by how much, but why and on which path. A delay on a task that had ten days of float does not push back the end; a four-day delay on the critical path pushes it back by four days. Where the contract declares the SIA 118 standard applicable, a contractor suffering a delay for which they are not responsible, such as exceptional bad weather or a late decision by the client, may request an extension of time, provided they notify it in writing in good time and can justify it.
The construction Gantt schedule editor gives you the justification in figures: critical path in red, total float for each row, dates recalculated as soon as a duration or lag changes. You enter the event where it struck, and the studio shows its effect on the end. The free version keeps no baseline: export the initial schedule to CSV before any change, so that you can compare.
Worked example: three events, only one pushes back the end
A small apartment building whose initial schedule, exported to CSV at signature, ends on D180 (working days). During the works, three events occur. The dates and float are those calculated by the studio on the initial schedule; the causes and responsibilities are examples, to be examined under your contract.
| Event | Row affected | Total float before | Lag entered | Effect alone on the end |
|---|---|---|---|---|
| Frost: concrete pour impossible | Slab over ground floor | 0 d | 4 d | +4 d |
| Tile choice submitted late by the client | Tiling | 8 d | 6 d | 0 d |
| Windows delivered late (the contractor’s supplier) | Windows | 5 d | 5 d | 0 d |
| The three events entered together | Whole schedule | none | none | D180 → D184 |
The frost hits the slab over the ground floor, on the critical path: a 4-day lag pushes the end back by 4 days. The late decision on the tiles falls on a row that had 8 days of float: the 6-day lag is absorbed, 2 days of float remain and the end does not move. The window delay uses up exactly their 5 days of float: the end does not move, but the windows join the critical path and a single extra day would push back the end. Entered together, the lags give an end on D184: the frost, upstream of all the fit-out, also shifts the tiling and the windows, without changing their float.
For the discussion with the client, this gives a clear basis: a request for an extension of 4 working days for the bad weather, notified in writing when it occurs; the late decision is documented even though it has no effect on the end; the supplier’s delay, with no effect on the end here, is in principle the contractor’s risk. The exact count of days, entitlements and costs depends on the contract and how it is interpreted.
Of three events, only the frost pushes the end back by 4 working days, from D180 to D184; the windows no longer have any float.
3 costly mistakes in justifying a delay
Notifying the delay too late
An extension claimed at the end of the works, without written notice when the events happened, is hard to obtain. Record the event on the day, enter it in the schedule and send written notice to the client or the site management.
Adding up delays without looking at the float
Four days of frost plus six days waiting for a decision do not make ten days of delay if the decision fell on a task with float. An inflated claim weakens the justified one: present the effect of each event on the end, as in the table.
Losing the reference schedule
Without the signed schedule, it is impossible to prove what was planned. The free version keeps no baseline: export the schedule to CSV and date the file at each approved version.
Three-step guide to documenting a delay
- Freeze the initial schedule
Build the schedule with its links, its canton and its contractual end as the target end, then export it to CSV at signature. This file is the reference. - Enter the event where it strikes
Lengthen the duration of the row affected or add a lag on its link, and add the days the site was stopped as non-working days. The studio recalculates the dates, the float and the critical path. - Compare and write up
Compare the new end with the target end: the negative float gives the delay on the critical path. Export the new version to CSV and attach both files to your written notice.
What the free version does not do for tracking delays
The free version does not freeze a baseline, does not show actual progress percentages or variance per task, and saves nothing: the comparison is made between two CSV exports. It gives no legal advice: whether the SIA 118 standard applies and the right to an extension depend on the signed contract.
Portail chantier freezes the baseline, tracks the actual percentage of each task and calculates the variance in working days from that reference, with the version history of the schedule on the site file.
Frequently asked questions
Does the SIA 118 standard apply to every site?
No. It only applies if the works contract declares it applicable, in whole or in part. Check your contract and its departures before basing a claim on it.
Does bad weather give a right to an extension?
Under SIA 118, a delay that does not depend on the contractor, such as weather conditions preventing work, can give a right to an extension of time, provided it is notified in writing in good time. The details depend on the contract.
What is the critical path?
It is the sequence of tasks without float: any day lost on one of them pushes back the end of the works. The studio colours them red and shows the total float of each row.
How do you compare the initial and current schedules?
In the free version, export each version to CSV and compare the dates in a spreadsheet. Portail chantier freezes a baseline and calculates the variance of each task for you.