Schedule for refitting a bathroom or kitchen on a short timescale: coordinating the trades

Over three weeks of works, a day lost between two tradespeople counts: chain plumber, electrician and tiler with the real drying times.

Open the free studio →

Free, no account: your plans, schedules and figures stay in your browser.

A bathroom or kitchen is often refitted in an occupied home, with a tight promised timescale. Four or five tradespeople follow one another in a few square metres, and the timescale depends less on how fast they work than on the waiting between them: the levelling compound that must dry before the waterproofing, the waterproofing before the tiling, the grouting before the fittings go in.

In the construction Gantt schedule editor, each technical wait is entered as a lag on the link: “4FS+2” means the task starts two working days after task 4 finishes. Work that can overlap is linked start-to-start. The studio calculates the dates, each tradesperson’s float and the critical path; you see who can arrive a day later without shifting anything, and who cannot.

Worked example: full refit of a bathroom

A 6 m² bathroom in an occupied flat: strip-out, new supply and waste pipes, two electrical points, floor levelling, waterproofing under tiles, floor and wall tiling, installation of fittings. Example durations and waiting times, to be confirmed with the product data sheets.

Bathroom schedule: links, lags and calculated dates (working days)
No. and taskDurationPredecessorsCalculated datesTotal float
1 Strip-out and protection2 dnoneD1 to D20 d
2 First-fix plumbing3 d1 FSD3 to D50 d
3 First-fix electrics1 d2 SS+1D41 d
4 Floor levelling1 d2 FS; 3 FSD60 d
5 Waterproofing under tiles1 d4 FS+2D90 d
6 Floor and wall tiling4 d5 FS+1D11 to D140 d
7 Fittings and finishing2 d6 FS+1D16 to D170 d

The electrician starts one day after the plumber (2 SS+1, i.e. D4) and finishes the same day: they keep 1 day of float before the floor levelling, which waits for both sets of services to finish on D6. The levelling compound dries for 2 working days: the waterproofing goes on at D6 + 1 + 2 = D9. It dries for 1 day: tiling starts on D11 and lasts 4 days to D14. The grout takes 1 day: the fittings are installed on D16 and D17.

The refit lasts 17 working days, three and a half weeks, of which 4 days are technical waiting with no tradesperson on site. These waits are example assumptions: the real time is given in the data sheet of the levelling compound, the waterproofing and the tile adhesive, and depends on the temperature and humidity of the room.

End on D17; only the electrician has float (1 day), all the other trades are on the critical path.

3 costly mistakes in a bathroom or kitchen schedule

Tiling over waterproofing that has not dried

Saving a day by tiling too early is paid for in leaks, then in complete removal. Enter the manufacturer’s drying time as an FS+n lag: the schedule will then not let the tiler start earlier.

Bringing two tradespeople into 6 m² on the same day

An overlap planned on paper becomes real waiting when the room is too small for two teams. A one-day start-to-start lag, as for the electrician in the example, better reflects reality.

Forgetting delivery of the fittings and units

A bath or kitchen delivered late blocks the final installation when everything else is ready. Add a “delivery confirmed” milestone linked to the installation: its date is the one to demand from the supplier.

Three-step guide to scheduling a bathroom

  1. Start from a blank schedule
    Load the blank schedule, enter the start date and the canton, then create one row per job. Keep one phase per room if you are refitting the bathroom and the kitchen at the same time.
  2. Enter the links with their waits
    In the Predecessors column, record the technical waits as lags: “4FS+2” for two days of drying of the levelling compound, “2SS+1” for the electrician following the plumber. The studio recalculates all dates with each change.
  3. Check the float and share
    Switch on the critical path to see who has no float, enter the end promised to the customer as the target end, then export to CSV or print the sheet for each tradesperson.

Open the free studio →

What the free version does not do for a bathroom or kitchen

The studio does not know the drying times of the products: you enter them. It does not schedule tradespeople by the hour, does not manage their availability or orders, and saves nothing: closing the page erases the schedule. The CSV export and printout serve as a record.

Portail chantier saves the schedule on the site file, with its versions, shares it with the customer and the tradespeople, and enables progress tracking: baseline, actual percentage and variance in days per task.

Frequently asked questions

How long does a bathroom refit take?

The example on this page comes to 17 working days, including 4 days of technical waiting. A simpler bathroom, without moving the waste pipes, can go faster; a bathroom with a walk-in shower and a new screed, more slowly.

What does FS+2 mean in the predecessors column?

FS means finish-to-start: the task starts after the task cited has finished. +2 adds two working days of waiting, for example for drying. A negative lag, on the other hand, lets a task start a little before the end.

Does the studio take weekends into account?

Yes, durations and lags are in working days: weekends and the public holidays of the canton chosen are skipped. If the team works on Saturdays, tick the 6-day week.

Can a kitchen be scheduled with the same tool?

Yes: the tasks change (connections, worktop, splashback, appliances), but the method is the same, with milestones for measuring the worktop and for delivery.