The structural works schedule of a small building often comes down to a pace: so many days per floor. Behind that figure is a repeating cycle of walls, slab formwork, reinforcement and pouring, then a wait before loading the next floor and, later, removing the props. If a wait is forgotten or shortened, it is not just the timescale that suffers: it is the safety of the structure and of the people.
In the construction Gantt schedule editor, each element of the cycle becomes a row in working days, and each wait set by the engineer becomes a lag on the finish-to-start link. The studio calculates the dates floor by floor, each row’s float and the critical path. The indicative statutory milestones offered by the studio, fall protection from a fall height of 2.00 m and scaffolding inspection and sign-off, are placed before the tasks they govern.
Worked example: structural works for a building with basement, ground floor and one upper floor
A small reinforced concrete building: basement, ground floor and first floor, 25 cm slabs. Example durations in working days, 5-day week. The curing waits (2 days before building walls on a slab) and the propping period (20 working days) are example values to be confirmed by the structural engineer.
| No. and task | Duration | Predecessors | Calculated dates |
|---|---|---|---|
| 1 Raft and basement walls | 15 d | none | D1 to D15 |
| 2 Slab over basement (formwork, reinforcement, pour) | 8 d | 1 FS | D16 to D23 |
| 3 Ground floor walls | 8 d | 2 FS+2 | D26 to D33 |
| 4 Slab over ground floor | 8 d | 3 FS | D34 to D41 |
| 5 First floor walls | 8 d | 4 FS+2 | D44 to D51 |
| 6 Slab over first floor | 8 d | 5 FS | D52 to D59 |
| 7 Removal of props under the ground floor slab | 1 d | 4 FS+20 | D62 |
One floor’s cycle comprises 8 days of walls, 8 days of slab and 2 days of waiting before building the next walls: 18 working days. The slab over the basement finishes on D23; with 2 days of waiting, the ground floor walls start on D26 and finish on D33, and the slab over the ground floor on D41. The same cycle on the first floor: walls from D44 to D51, slab from D52 to D59.
The props under the ground floor slab stay in place for 20 working days after it is poured: 41 + 1 + 20 = D62. The structural works in this example therefore finish on D62, a little over 12 weeks of 5 days, and it is the propping period that sets the end, not the last slab. Bringing the removal forward to save three days is not a scheduling decision: it is the engineer’s decision.
Pace of 18 working days per floor, end of structural works on D62, set by the propping period of the slab over the ground floor.
3 costly mistakes in a structural works schedule
Scheduling prop removal instead of the engineer
Removing props too early can cause cracking, excessive deflection or worse. The period depends on the concrete, the span, the temperature and the construction loads: ask the engineer for the value and enter it as a lag, without shortening it to meet a date.
Forgetting fall protection at slab edges
Work at slab and formwork edges exposes people to falls from a height of about 2 m, the protection threshold recalled by SUVA. Place the indicative fall protection milestone before the ground floor walls: if the guardrails are not installed, the floor does not start.
Ignoring bad weather in the pace
Concrete is not poured in frost or heavy rain. A pace calculated without a single lost day will be overrun by the first winter: keep a target end with a reserve, or add non-working days when the weather stops the site.
Three-step guide to scheduling structural works
- Build one floor’s cycle
Start from the “Small residential building (Ground + 3)” template or a blank schedule, and create one phase per floor with its walls and slab. Enter your team’s durations and the CFC code of each row. - Enter the waits and milestones
Record the waits provided by the engineer as lags, for example “2FS+2” and “4FS+20”. Add the indicative statutory milestones, scaffolding inspection and sign-off and fall protection, and adjust their threshold if your safety concept specifies another one. - Repeat, check, export
Enter the same cycle for each floor, check the critical path and the target end, then export to CSV for the site manager and the foreman.
What the free version does not do for structural works
The studio calculates neither concrete curing, nor the propping period, nor quantities, nor crews: all these values are entered by you and approved by the engineer. The OTConst and SUVA milestones are indicative; they replace neither the written safety concept nor the notifications required by the SUVA rules. Nothing is saved: closing the page erases the schedule.
Portail chantier saves the schedule and its versions on the site file, shares it with the team and enables progress tracking: frozen baseline, actual percentage and variance in days per floor.
Frequently asked questions
How many days per floor in reinforced concrete?
In the example, 18 working days per floor, waiting included. The real figure depends on the slab area, the formwork system, the workforce and the number of prop sets available.
When can a slab’s props be removed?
The structural engineer decides, depending on the concrete, the span, the temperature and the loads. The example uses 20 working days as an illustration; do not reuse it as it is.
From what height is fall protection required?
SUVA points out that the OTConst requires fall protection measures from a fall height of 2 m, in particular at slab and formwork edges. The studio’s milestone uses this threshold by default; check it for your site.
Does the studio know that an excavation needs shoring?
No. It offers an indicative SUVA notification milestone for excavations beyond an adjustable threshold (1.50 m by default); it is up to you to place it and link it to the earthworks.