Free software · 100% in your browser · no data sent

Gantt schedule for building a detached house, from groundworks to handing over the keys

Link the main stages of a house in working days and see which tasks hold the handover date.

Open the free studio →

Free, no account: your plans, schedules and figures stay in your browser.

On a detached house, time is rarely lost on one big task: it is lost in the hand-offs. A carpenter waiting for a slab, a screed laid too late to dry before the parquet, a façade holding up the scaffolding. A Gantt schedule makes these links visible and shows the end date that follows from them, instead of a date picked by hand.

The construction Gantt schedule editor opens in the browser, without an account. It offers a “Detached house” template whose durations are examples to adapt. You enter the duration of each task in working days, its predecessors with a finish-to-start (FS) or start-to-start (SS) link and any lag. The studio calculates the dates, free float and total float and colours the critical path red. The calendar takes into account the public holidays of the canton chosen and your own non-working days (industry holidays, bridge days).

Worked example: Gantt schedule for a house in seven tasks

A two-storey detached house on a raft foundation, with a pitched roof and a rendered façade. The durations are example values to be replaced by those of your contractors. Dates are given in working days from the first day on site (D1), 5-day week, before adding public holidays and industry holidays.

House schedule: durations, links and calculated dates (working days)
No. and taskDurationPredecessorsCalculated datesTotal float
1 Site set-up and earthworks8 dnoneD1 to D80 d
2 Foundations and raft10 d1 FSD9 to D180 d
3 Structure, walls and slabs35 d2 FSD19 to D530 d
4 Roof structure and covering (weathertight)15 d3 FSD54 to D680 d
5 Façades and windows25 d4 FSD69 to D9310 d
6 Building services and screeds25 d4 SS+5D59 to D830 d
7 Interior finishes30 d5 FS; 6 FS+20D104 to D1330 d

Tasks 1 to 4 follow one another finish-to-start: the roof structure starts the day after the structure ends, on D54, and finishes on D68. Building services and screeds are linked to the roof structure start-to-start with a 5-day lag: they start on D54 + 5 = D59 and finish on D83. The finishes wait for the end of the screeds plus 20 working days of drying: 83 + 1 + 20 = D104, then 30 days to D133. The façade, which finishes on D93, only needs to be complete by D103: it has 10 days of total float.

The studio therefore shows an end on D133, i.e. 26.6 weeks of 5 days before public holidays and leave. Once the canton and the industry holidays are entered, the handover date moves accordingly. The 20-day drying time is an assumption: it depends on the screed thickness, the product and the planned floor covering, and is confirmed with the supplier and the flooring contractor.

Six tasks out of seven are on the critical path; only the façade can slip by 10 working days without pushing back the end, set at D133.

3 costly mistakes in a house schedule

Forgetting screed drying time

A screed covered too early with parquet or tiles leads to debonding and remedial work at your expense. Drying is not a labour task: enter it as an FS+n lag between the screed and the finishes, with the value given by the manufacturer.

Linking everything finish-to-start

If each trade waits for the previous one to finish completely, the schedule grows by several weeks. Building services can start a few days after the roof structure begins: a start-to-start link with a lag reflects this real overlap.

Fixing the handover date before having the calendar

Promising a handover without counting the canton’s public holidays and the industry holidays means being late already. Choose the canton in the studio and add your non-working days before giving a date to the client.

Three-step guide to scheduling a house

  1. Load the template and the calendar
    Load the “Detached house” template, enter the start date, choose the canton of the site and add the industry holidays as non-working days. The template durations are examples: replace them with those of your contractors.
  2. Link the tasks and milestones
    In the Predecessors column, enter the links (for example “4SS+5” or “6FS+20”). Add the indicative statutory milestones offered by the studio, such as the written safety concept before work starts, and link them to the tasks they precede.
  3. Read the critical path and export
    Switch on the critical path: red rows have no float. Enter a target end to see whether the schedule meets the promised date. Export to CSV or print the sheet for the kick-off meeting.

Open the free studio →

What the free version does not do for a house schedule

The studio calculates dates from the durations and links you enter: it knows neither your workforce, nor your costs, nor the weather, and does not calculate drying times. It saves nothing: closing the page erases the schedule, hence the CSV export. The OTConst and SUVA milestones are indicative; they replace neither the safety concept nor notifications to SUVA.

With Portail chantier, the schedule is saved on the site file with its versions, shared with the team and the client, and progress tracking becomes possible: frozen baseline, actual percentage and variance per task.

Frequently asked questions

How long does it take to build a detached house in Switzerland?

The example on this page comes to 133 working days, a little over six months of works before public holidays and leave, but everything depends on the construction method, permit timescales and drying. The schedule is built with your own durations.

What is the difference between free float and total float?

Free float is the number of working days a task can slip without delaying the next task; total float, without delaying the end of the project. A total float of 0 puts the task on the critical path.

Does the studio handle public holidays?

Yes: when you choose the canton of the site, its official public holidays are excluded from the calculation. You add the industry holidays, bridge days and other non-working days yourself.

Can the schedule be opened in Excel?

Yes, the CSV export (semicolon separator) opens in Excel with the dates, predecessors, float and critical path flag. It carries the Art Construction mention.