The earthworks contractor digs the excavation, but it is the mason, the waterproofer and the drainage installer who will then work at the toe of the slope: they must be able to erect the outer formwork, lay the waterproofing and the drain, then compact the backfill. The OTConst requires the working space to have a usable width that allows safe work, and a sufficient distance to be kept between the edge of the excavation and stored equipment. The clear working width is therefore a safety parameter as much as a quantity parameter.
In the Excavations, slopes and retaining walls studio, the Clear working width field adds this width on each side of the raft before tracing the slope. If it falls below 0.60 m, a starting value of the studio, a warning asks you to provide at least this width between the structure and the toe of the slope. The true excavated volume, the stripping and the backfill around the basement are recalculated for each width. The result is an indicative preliminary design, not a substitute for a civil engineer's calculation.
Worked example: three working widths for the same 3 m excavation
Raft of 12.00 m by 10.00 m, depth 3.00 m including 0.25 m of topsoil, compact silty-gravelly ground moraine, moderately resistant, slope 2:1 (63.4°), reused as backfill. Starting values of the studio, to be confirmed by the geotechnical report.
| Clear working width | Excavation bottom | Excavation | True excavated volume | Backfill around the basement |
|---|---|---|---|---|
| 0.30 m (studio warning) | 12.60 × 10.60 m | 461.95 | 528.53 | 131.95 |
| 0.60 m (starting value) | 13.20 × 11.20 m | 505.75 | 577.33 | 175.75 |
| 1.00 m | 14.00 × 12.00 m | 567.24 | 645.76 | 237.24 |
| Difference from 0.30 to 1.00 m | +1.40 m per direction | +105.29 | +117.23 | +105.29 |
With 0.60 m, the bottom measures 12.00 + 2 × 0.60 = 13.20 m by 11.20 m. The 2.75 m high slope sets back by 1.375 m: the top measures 15.95 m by 13.95 m, and V = 2.75 ÷ 6 × (13.20 × 11.20 + 15.95 × 13.95 + 4 × 14.575 × 12.575) = 505.75 m³. With 1.00 m, the bottom becomes 14.00 m by 12.00 m, the top 16.75 m by 14.75 m, and V = 2.75 ÷ 6 × (168.00 + 247.06 + 4 × 15.375 × 13.375) = 567.24 m³.
The basement always takes up 12.00 × 10.00 × 2.75 = 330 m³; everything else goes back as backfill: 505.75 − 330 = 175.75 m³ with 0.60 m, 567.24 − 330 = 237.24 m³ with 1.00 m. Each decimetre of working width is therefore paid twice, at the excavation and then at the compacted backfill, but too small a width makes it impossible to form, waterproof and compact properly.
Going from 0.60 to 1.00 m of clear width adds about 61 m³ of earthworks and as much backfill on this excavation; dropping to 0.30 m brings up the studio warning.
3 common mistakes on the working width
Digging flush with the raft
To save a few cubic metres, the excavation is cut at the face of the future wall. The outer formwork, the waterproofing and the drain can then only be fitted by working against the slope, with no room to step back: a risk of burial and a sure waterproofing defect.
Forgetting the thickness of the outer layers
Perimeter insulation, waterproofing protection, the drain and its gravel surround take up space between the wall and the toe of the slope. The clear width is measured beyond these layers, not at the face of the concrete.
Not carrying the width into the quantities
A working width more generous on site than in the quantities produces cubic metres that were never counted, at the excavation as at the backfill. Enter the same width in the quantities and on the construction drawings.
How to use it in 3 steps
- Describe the excavation
In the Excavation and 3D cubature mode, enter the raft, the depth, the topsoil, the ground and the gradient, then the desired clear working width. - Compare several widths
Change the clear working width and note the excavation, the true volume and the backfill: the studio recalculates everything and flags a width below 0.60 m. - Set the width with the trades
Retain the width that leaves room for formwork, waterproofing, drain and compaction, then print the sheet or export the CSV for the quantities and the earthworks plan.
What the free version does not do for the working width
The studio applies a constant width on all four sides, with a plane slope in uniform ground. It does not know the thickness of your insulation or drain, does not draw the formwork and does not set the regulatory width: the 0.60 m value is a starting value, the applicable rule is that of the OTConst and of your safety concept.
Soumissions takes the excavation and backfill volumes into the items of the tender; the ERP tracks hours and plant; the Portail chantier keeps the sheet and the earthworks drawings with the site file.
Frequently asked questions
What working width should be left at the toe of the slope?
The studio starts from 0.60 m between the structure and the toe of the slope and warns below that. The actual width depends on the work to be done at the bottom; the OTConst requires a usable width that allows safe work.
Does the working width count in the quantities?
Yes: it enlarges the bottom and the top of the excavation, so the earthworks, the stripping and the backfill. The studio counts it on all four sides of the raft.
Is the same width needed in a pipe trench?
No, a trench has its own minimum widths depending on the pipe diameter and the depth; the studio calculates them in the Trench and Suva shoring mode.
Why does the backfill increase as much as the excavation?
Because the volume of the basement does not change: everything dug in addition around the structure must be put back as compacted backfill once the walls are finished.