Excavations, Slopes & Retaining Walls Studio: Safety Regulations, Shoring, 3D Volumes & L-Walls (SIA 267)

Calculate the volume of an excavation with slopes and bulking, size a trench shoring system or check an L-shaped retaining wall: OTConst safety, earth pressure, overturning, sliding, bearing capacity, reinforcement and quantity surveying.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

Swiss Excavation and Trench Safety Rules: Construction Work Ordinance and SUVA

On an earthworks or civil engineering construction site, the safety of excavation walls falls under the Construction Work Ordinance and SUVA guidelines. Basic rules require clear measures as soon as surface stripping is completed.

According to the ordinance text, any excavation deeper than 1.50 m that is neither propped nor shored must be sloped or secured by other measures. A vertical wall without shoring beyond this height constitutes an immediate danger situation which the studio flags as blocking. The slope gradient must be adapted to the ground strength encountered on the plot. When rain, water inflows, thawing, top loads, or mechanical vibrations compromise this stability, additional protective measures must be implemented immediately.

Maintaining a safety zone at the surface is equally crucial. The ordinance states that the edge of the excavation must remain clear for at least 1 m if the wall is sloped, and at least 50 cm if it is propped or shored. These clear strips prevent landslides under the weight of stored materials or people.

For deep excavations, the ordinance requires proof of slope stability signed by a specialized engineer or geotechnical engineer, notably beyond 4 m of slope height, as well as in the presence of additional loads or water inflows. The 1.50 m threshold concerns the obligation to slope or shore, not the signature of this proof.

Slope Gradients, Clear Edge Strips, and Box Shoring: What the Studio Calculates

The studio integrates six standard Swiss ground types with editable starting values: sandy gravel from the Plateau, compact moraine, weathered or marly molasse, sound sandstone molasse or compact limestone, clayey silt or soft lacustrine deposit, and heterogeneous old urban fill. These values come from the tool's specifications and are not official; they must be confirmed by the project's geotechnical report.

For maximum starting slopes, the studio uses 1:1 for low-strength soil, 2:1 for medium-strength soil, and 3:1 for very-strength soil (vertical to horizontal ratio). In case of rain, water inflow, or thawing, the studio lowers the slope by one class according to its internal rule. It displays a red alert beyond 4 m in height, an orange alert from 1.50 m in the presence of water or a top surcharge, and proposes a recommended 1 m berm at mid-height beyond 4 m. The studio also retains a clear strip of at least 1 m along a machinery track, a clear working width of at least 0.60 m between the structure and the toe of the slope, and a safety railing at the top of the excavation beyond 2 m of fall.

For pipe trenches, shoring must withstand foreseeable loads and be dimensioned taking into account additional loads from vehicles, machinery, and deposits, in accordance with the ordinance text. The studio calculates the apparent earth pressure of Terzaghi-Peck and axle surcharge using Boussinesq's formula for a rigid wall. It proposes indicative box classes (light aluminum, standard steel, double slide rails), calculates the force in the struts, and indicates the shoring extension of 0.15 m above ground and an access ladder exceeding by 1 m.

Why Calculating Earthworks Without Slopes and Swelling Ruins Site Margins

A frequent error is estimating excavation volumes from a simple right rectangular prism based on the raft foundation footprint. This approach ignores the peripheral workspace, the slope batter on all four sides, and the possible presence of a berm. The studio applies the exact prismoidal formula by integrating the bottom surface, the mid-height surface, and the excavation crest surface.

Earthworks generate three distinct volumes that the surveyor must rigorously separate:

  • The theoretical in-place volume (right prism of the structure without slopes).
  • The true excavated in-place volume, integrating topsoil stripping, a workspace of at least 0.60 m, and slope gradients.
  • The bulking volume after extraction, which directly determines the number of skips to evacuate.

On site, excavated earth increases in volume as soon as it is destructure by the excavator bucket. Failing to integrate the bulking coefficient distorts the estimate of necessary trucks. The studio compares the in-place volume, reusable peripheral backfill, imported gravel if the extracted material is unsuitable, and the actual evacuable volume. With an 18-tonne payload for a four-axle truck (editable value), the calculated number of rotations prevents unexpected budget overruns during landfill transport.

Dimensioning a Reinforced Concrete L-Shaped Retaining Wall According to SIA Standards 260, 262, and 267: Pressure, Overturning, Sliding, Bearing Capacity, and Reinforcement

For an L-shaped retaining wall, geotechnical and structural design relies on the principles of SIA standards 260, 262, and 267. The studio calculates active earth pressure using Rankine's method applied to a fictitious vertical plane behind the heel, taking into account the inclination of the upstream slope and a uniform live surcharge. Coulomb's coefficient is also displayed for comparison.

Four external equilibrium checks are conducted:

  • Overturning safety relative to the front edge of the footing.
  • Sliding resistance at the base, with the option to add a shear key underneath.
  • Eccentricity of the overall load, verified to keep the resultant within the middle third at the serviceability limit state.
  • Bearing capacity stress of the foundation soil according to Meyerhof's diagram with a reduced compressed width.

For structural calculation, the studio determines the bending moment at the base of the C30/37 concrete vertical stem and proposes B500B reinforcement bars (diameter and spacing) at least equal to the minimum section. Indicative moments are also provided for the toe and heel. The automatic sizing function adjusts the footing geometry targeting the most concrete-efficient option while keeping stress ratios below the 95% threshold.

Rear Drainage: The Water Pressure the Wall Cannot Support

Water accumulation behind a retaining wall is a classic cause of defects in reinforced concrete structures. When the upstream backfill becomes waterlogged following storms or poor runoff management, a triangular hydrostatic pressure is exerted over the entire height of the wall.

The studio highlights this phenomenon through a direct comparative calculation with and without drainage: without drainage devices, water pressure adds entirely to active earth pressure. The overturning moment at the base of the wall then doubles or triples, which can push stress ratios beyond 100%.

To avoid this saturation, the drainage complex must combine a cellular protective membrane against the concrete, a granular filtering backfill behind the wall stem, and a perforated collector pipe laid at the footing base with a functional outlet. In boundary line situations where the toe is zero and the footing is oriented exclusively upstream, drainage control remains paramount to prevent the structure from tipping over.

Evacuating Excavation Materials: Topsoil, Waste Ordinance Channels, and Contractor Responsibility

The management of excavation spoils in Switzerland is governed by the Waste Ordinance (OLED). The text stipulates that earthy and excavation materials must be sorted on the construction site and recycled as much as possible if they are unpolluted. Topsoil resulting from initial stripping is counted and stored separately for restoration or external works.

According to the ordinance, the client indicates in their permit application the type, quality, quantity, and disposal channels for waste when the quantity is likely to exceed 200 m³ or in the presence of hazardous pollutants. The contractor must organize evacuations accordingly.

The studio classifies channels according to standard markers in the specifications:

  • Stripped topsoil to be reused on site or recycled.
  • Unpolluted excavation materials directed to a Type A landfill.
  • Slightly polluted or mineral deconstruction materials admitted to a Type B landfill.
  • Polluted soils requiring treatment or disposal in a Type E landfill.

In case of doubt regarding the environmental quality of soils, laboratory chemical analysis is mandatory, and the competent cantonal service must be consulted to validate the admission channel.

Contractor Responsibility in Switzerland: Duty to Notify, Service Contract, SIA 118 Standard, and Signed Engineer's Note

Opening an excavation or building a retaining wall commits the contractor under the service contract governed by the Code of Obligations (CO) and, where applicable, the SIA 118 standard. The company is subject to a strict duty to notify: if it notes discrepancies between the actual ground and the descriptive assumptions, slope instability, unforeseen water inflows, or a risk to neighboring plots, it must immediately notify site management in writing.

The Swiss Criminal Code also recalls fundamental duties regarding accident prevention during construction work. Using the studio provides decision-making support for site pre-dimensioning but does not replace a formal geotechnical study.

Soil investigation and a calculation note signed by a civil engineer or geotechnical engineer according to SIA standard 267 remain required for the final execution of the structure, as well as in the following situations: height exceeding 4 m, presence of a groundwater table, unstable slope, or neighboring building within the zone of influence.

From Calculation to Bill of Quantities: Quantities to Quote and Transitioning to Tenders, ERP, or Portal

Once dimensions are validated, the studio generates a complete bill of quantities without prices, displaying volume formulas and service lines necessary for drawing up a quote: topsoil stripping, bulk earthworks, shored trench, bulked evacuation, shoring surface, blinding concrete, formwork, C30/37 structural concrete, B500B steel, bedding layer, and drainage network.

This free version runs entirely in your internet browser: nothing is sent to an external server, nothing is saved, and no local memory is retained. If you close or reload the tab, all entered data is erased. The CSV export indicates the mention of the free version, and printing the sheet includes an Art Construction watermark.

To save your variants in the cloud and keep a history per construction site, you can switch to our ERP solution or access the Portal. Linking with our Tenders module allows you to instantly retrieve these quantities to apply unit prices from the cantonal ACIP database and produce professional quotes without watermarks.

Frequently asked questions

From what depth must an excavation be sloped or shored according to the Construction Work Ordinance?

According to the Construction Work Ordinance, any excavation wall deeper than 1.50 m that is neither propped nor shored must obligatorily be sloped or secured by other appropriate measures. The studio flags any unpropped vertical excavation exceeding this height as blocking.

When is it necessary to have stability calculation notes signed by a specialized engineer?

The Construction Work Ordinance requires proof signed by a specialized engineer or geotechnical engineer as soon as the slope height exceeds 4 m, as well as in the presence of additional loads at the top of the slope or water inflows. The 1.50 m threshold does not concern the signature of this proof.

What clearance width must be left free at the edge of a trench or excavation?

The text of the Construction Work Ordinance sets a clear strip of at least 1 m along a sloped wall and at least 50 cm if the wall is propped or shored. The studio additionally retains a minimum setback of 1 m along machinery tracks.

How does the studio take rain or thawing into account for slope gradients?

The studio's maximum starting slopes are 1:1 for low-strength soil, 2:1 for medium soil, and 3:1 for very-strength soil. In case of bad weather, thawing, or water, the studio applies its own rule by automatically lowering the allowable slope by one class.

Why is water pressure dangerous for an L-shaped retaining wall?

Water accumulated without drainage exerts hydrostatic pressure that adds to earth pressure. This additional load doubles or triples the overturning moment at the base of the wall, which can cause the concrete and soil stress ratio to exceed 100%.

What are the sorting obligations for construction site spoils according to the Waste Ordinance?

The Waste Ordinance requires sorting earthy and excavation materials on site to recycle them if they are unpolluted. If the volume is likely to exceed 200 m³ or if pollutants are suspected, the client must declare channels and quantities in the permit application.

Does my calculation data remain saved if I close my browser?

No. In this free version, everything runs locally in the browser: nothing is transmitted to a server or kept in memory. Reloading or closing the tab deletes the study. Online backup and multi-user access require our Pro version.