An excavation for the deep basement of a small block of flats or a car park quickly exceeds 4 m. A continuous slope over the full height is then long, hard to monitor and exposed: a stone that comes loose at the top reaches the bottom with speed, and a slip carries the whole height with it. The berm, a horizontal bench cut at mid-height, splits the slope into two shorter slopes, catches small falls and provides a landing for inspection and maintenance. Beyond 4 m of slope height, the OTConst also requires a proof of slope safety drawn up by a specialist engineer or a geotechnical engineer.
In the Excavations, slopes and retaining walls studio, the Berm (bench) field of the Excavation and 3D cubature mode adds the width of the bench to the setback of the slope. Beyond 4.00 m of depth, if no bench of at least 1.00 m is entered, the studio shows a warning and proposes a 1.00 m berm at mid-height, a starting value of the studio. The true excavated volume, the stripping and the truck trips are recalculated with the bench.
Worked example: 5 m deep excavation, without then with a 1 m berm
Raft of 12.00 m by 10.00 m, total depth 5.00 m including 0.25 m of topsoil, clear working width of 0.60 m. Well-graded sandy gravel, moderately resistant, starting gradient 2:1 (63.4°), dry ground, reused as backfill. Starting values of the studio, to be confirmed by the geotechnical engineer.
| Quantity | Without berm | With a 1.00 m berm | Difference |
|---|---|---|---|
| Setback of the slope at the top | 2.38 m | 3.38 m | +1.00 m |
| Dimensions at the top | 17.95 × 15.95 m | 19.95 × 17.95 m | +2.00 m per side |
| Excavation below the topsoil | 1013.23 | 1165.54 | +152.31 |
| Topsoil stripping | 89.53 | 109.48 | +19.95 |
| True excavated volume | 1102.75 | 1275.02 | +172.27 |
| Backfill around the basement | 443.23 | 595.54 | +152.31 |
Below the topsoil, the slope is 5.00 − 0.25 = 4.75 m high. With a 2:1 gradient, it sets back by 4.75 ÷ 2 = 2.375 m; the berm adds 1.00 m, giving 3.375 m. The bottom measures 13.20 m by 11.20 m; the top 13.20 + 2 × 3.375 = 19.95 m by 17.95 m. The studio treats the bench as an extra setback and applies the prismoid formula: V = 4.75 ÷ 6 × (13.20 × 11.20 + 19.95 × 17.95 + 4 × 16.575 × 14.575) = 1165.54 m³, against 1013.23 m³ without a bench.
The volume of the basement itself stays 12.00 × 10.00 × 4.75 = 570 m³: what is removed does not change when the gravel is reused. On the other hand, the 152 m³ extra must be dug, stored on site and then put back as compacted backfill around the structure, and the footprint at the top of the excavation gains 2.00 m in each direction.
A 1.00 m berm on a 5 m excavation adds about 152 m³ of earthworks and 2.00 m of footprint per direction, without changing the volume removed if the gravel is reused.
3 common mistakes with a berm
A bench too narrow or sloping towards the excavation
A 30 cm berm catches nothing and cannot be walked on. Provide enough width to catch falls and allow inspection, and give it a slight fall towards the slope so that water does not run down the lower slope.
Forgetting the footprint at the top
The bench pushes the edge back: on a narrow plot, the top of the excavation may then reach the boundary, a footpath or a pipe. Check the actual footprint before choosing between a berm, a steeper verified slope or shoring.
Believing the berm removes the need for a proof
The bench improves safety, but beyond 4 m of slope height the signed proof is still required by the OTConst. The geotechnical engineer sets the final geometry, berm included.
How to use it in 3 steps
- Enter the deep excavation
In the Excavation and 3D cubature mode, enter the raft, the total depth, the topsoil, the clear working width and the ground. Beyond 4.00 m, the studio signals that a berm should be planned. - Add the berm
Enter the width of the bench in Berm (bench): the drawn section shows it at mid-height and the volumes are recalculated with the extra setback. - Compare and pass on
Compare the volumes with and without the bench, check the footprint at the top against the plot, then print the sheet for the geotechnical engineer who will draw up the proof.
What the free version does not do for a deep excavation
This is an indicative preliminary design: the studio checks the stability neither of the two slopes nor of the bench. It adds the berm width to the setback and applies the same starting gradient below and above. It models neither groundwater, nor different ground layers, nor nailed or anchored walls; an excavation deeper than 4 m requires a signed proof in any case and, generally, a geotechnical study and a civil engineer's calculation.
Soumissions takes the excavation and backfill volumes into the items of the tender; the ERP tracks plant, hours and invoicing; the Portail chantier keeps the sheet, the geotechnical study and the proof in the site file.
Frequently asked questions
What is a berm?
It is a horizontal bench cut into a slope, usually at mid-height. It splits the slope into two shorter slopes, catches small falls of material and serves as a landing for inspection.
From what depth should a berm be planned?
The studio proposes it beyond 4.00 m of depth, with a starting width of 1.00 m. The final geometry is set by the engineer who draws up the proof of slope safety.
Does the berm increase the volume to remove?
It increases the volume to dig. If the material is reused as backfill, the volume removed stays that of the basement; otherwise, the whole excavated volume goes to landfill.
Can the berm be replaced by shoring?
Yes, a shored wall or an enclosure designed by an engineer replaces the slope and the berm when space is short. The studio does not design this kind of enclosure: it only calculates the shoring of a pipe trench.