Before the geotechnical report, the site manager and the quantity surveyor often have to estimate an excavation from a rough borehole or from experience of the area. The ground decides almost everything: the gradient the slope can hold in the short term, the pressure on a wall, the bulking of the material once loaded, whether it can be reused as backfill and therefore the number of trucks. Getting the ground wrong means getting the volume, the duration and the disposal route wrong.
The Excavations, slopes and retaining walls studio offers six typical Swiss grounds: well-graded sandy gravel, compact ground moraine, weathered or marly molasse, sound sandstone molasse or compact rock, silty clay or soft lake deposit, and old urban fill. Each loads starting values (unit weight γ, friction angle φ′, cohesion c′, bulking, reuse, disposal route) and a strength class that sets the starting gradient of the slope. All these values can be edited and must be replaced by those of the geotechnical report; the result remains an indicative preliminary design, not a civil engineer's calculation.
Worked example: the same 12 × 10 × 3 m excavation in six grounds
Raft of 12.00 m by 10.00 m, depth 3.00 m including 0.25 m of topsoil, clear working width of 0.60 m, dry ground, truck with an 18 t payload. Reuse follows the studio's starting value: gravel and moraine are reused as backfill, the other grounds go to landfill. Values not official.
| Ground type | γ ; φ′ ; c′ | Starting gradient | Bulked volume removed | Truck trips |
|---|---|---|---|---|
| Well-graded sandy gravel | 21 kN/m³ ; 35° ; 0 | 2:1 (63.4°) | 330 × 1.20 = 396 m³ | 39 |
| Compact ground moraine | 22 kN/m³ ; 33° ; 5 kPa | 2:1 (63.4°) | 330 × 1.26 = 415.8 m³ | 41 |
| Weathered or marly molasse | 22.5 kN/m³ ; 30° ; 15 kPa | 2:1 (63.4°) | 505.75 × 1.35 = 682.8 m³ | 64 |
| Sound sandstone molasse, rock | 24.5 kN/m³ ; 40° ; 50 kPa | 3:1 (71.6°) | 471.15 × 1.48 = 697.3 m³ | 65 |
| Silty clay, soft lake deposit | 19 kN/m³ ; 24° ; 2 kPa | 1:1 (45.0°) | 618.81 × 1.30 = 804.5 m³ | 66 |
| Old urban fill | 18.5 kN/m³ ; 27° ; 0 | 1:1 (45.0°) | 618.81 × 1.28 = 792.1 m³ | 64 |
Below the topsoil, the slope measures 2.75 m and the bottom 13.20 m by 11.20 m. At a 2:1 gradient, the top measures 15.95 m by 13.95 m and the prismoid gives 505.75 m³; at 3:1, the setback is only 0.917 m and the volume 471.15 m³; at 1:1, the top reaches 18.70 m by 16.70 m and the volume 618.81 m³. When the material is reused, only the basement volume leaves, 12.00 × 10.00 × 2.75 = 330 m³; otherwise, the whole excavated volume is removed.
The bulked volume multiplies the volume removed by the coefficient of the ground. The number of trucks is counted by mass: in-place volume removed × γ ÷ 10 gives tonnes, for example 618.81 × 19 ÷ 10 = 1175.8 t for the silt, i.e. 1175.8 ÷ 18 = 65.3, rounded up to 66 trips. For reused gravel: 330 × 21 ÷ 10 = 693 t, i.e. 39 trips.
Between reused gravel and soft silt sent to landfill, the same excavation goes from 39 to 66 truck trips and from 396 to 804 m³ bulked.
3 common mistakes in choosing the ground
Choosing the ground from the surface
A clean gravel at the top of the excavation may rest on a lake silt or a finer moraine 2 m down. The ground to retain is that of the full slope height and of the excavation bottom, according to the boreholes, not the first bucketful.
Counting on reuse without checking it
A gravel can only be reused as backfill if it is clean, compactable and unpolluted. Old urban fill or wet silt does not compact properly and goes to landfill, often by another disposal route; the volume removed and the trucks change completely.
Keeping the cohesion value for the slope
The cohesion of a silt or a weathered molasse partly disappears with water, frost or disturbance. The studio does not use it to steepen the slope: the starting gradient depends on the ground class, and it drops by a further class in case of rain or thaw.
How to use it in 3 steps
- Choose the closest ground type
In the Ground panel, choose among the six typical Swiss grounds the one that best matches your borehole; its starting values are displayed. - Replace with the report values
As soon as the geotechnical report is available, replace γ, φ′, c′, bulking and reuse with its values: the studio recalculates the starting gradient, the volumes and the trucks. - Compare the assumptions
Try the least favourable plausible ground to bracket the volume and the number of trips, then print the sheet or export the CSV for the quantities and the removal schedule.
What the free version does not do with the grounds
The six grounds are unofficial starting values: they replace neither boreholes, nor tests, nor the geotechnical report. The studio assumes uniform ground over the full height, without groundwater, and does not assign a final disposal route: the classification of excavated material is confirmed with the authority and, if necessary, by analysis.
Soumissions takes the earthworks, removal and backfill volumes into the items of the tender; the ERP tracks plant, trucks and invoicing; the Portail chantier keeps the sheet and the geotechnical report in the site file.
Frequently asked questions
What values does the studio give for a sandy gravel?
Unit weight 21 kN/m³, friction angle 35°, no cohesion, bulking 1.20, reuse possible and a starting gradient of 2:1. These are starting values, to be replaced by those of the geotechnical report.
Why can rock be sloped more steeply?
A sound sandstone molasse or a compact, unfissured limestone is classed as very resistant: the studio starts from a 3:1 gradient. Fissured or weathered rock is treated as a less resistant ground.
What does bulking mean?
Excavated ground takes up more volume than in place. A coefficient of 1.30 means that 1 m³ in place becomes 1.30 m³ in the skip; that is the volume that counts for skips and stockpiles.
How does the studio count the trucks?
By mass: in-place volume removed multiplied by the unit weight, divided by 10 to get tonnes, then divided by the truck payload, 18 t by default, rounded up to the next truck.