Why the straight cube underestimates a sloped excavation
Multiplying the length of the foundation slab by its width and excavation depth yields a straight cube. On site, this theoretical calculation systematically underestimates the reality of the earthworks. As soon as the excavation goes below natural ground level, the walls cannot remain vertical without continuous shoring. According to the construction work ordinance, beyond a depth of 1.50 m, a wall that is neither braced nor sheeted must be sloped or secured by other measures. A vertical wall without shoring beyond this height is flagged as blocking by the studio.
From the moment the walls slope to form banks, the excavated volume grows outwards. The earthworks surface at the crest greatly exceeds the footprint of the basement. Ignoring this trapezoid of earth leads to ordering too few truck rotations, underestimating disposal and distorting the bill of quantities given to the client in the tender. On a typical 12 m by 10 m villa dug to a depth of 3.00 m with a 2:1 slope, the actual bulk excavated volume deviates heavily from a simple right rectangular prism.
The prismoidal formula: bottom, mid-height and crest
To obtain the exact volume of a bulk sloped excavation, the studio applies the rigorous geometric formula of the prismoid. This mathematical method does not settle for a rough average between the bottom and the crest. It incorporates three distinct horizontal sections: the area at the bottom of the excavation, the area at the earthworks crest and the area taken exactly at mid-depth of excavation.
The calculation takes into account the exact footprint of the structure, earthwork extra widths and the batter applied to the four walls. The slope gradient must be adapted to the ground's resistance. The studio's starting values use indicative maximum slopes: 1:1 for low-resistance ground, 2:1 for medium-resistance ground and 3:1 for high-resistance ground (vertical to horizontal). In case of rain, water inflow or thaw, the studio lowers the slope by one class. The formulas remain visible in the generated bill of quantities. The 3D view compares the straight cube to the true excavated volume, allowing the site manager to visualise the total mass before the excavator arrives.
Topsoil, working space and berm in the volume
A professional volume calculation never starts from the outer skin of the cellar wall. Three physical parameters modify the geometric earthwork volume:
- Topsoil stripping: the surface layer is stripped, accounted for and stored separately. According to the waste ordinance, earthy and excavation materials are sorted on the construction site and recycled as much as possible if unpolluted.
- Working space: masons must formwork, install waterproofing and set up drainage. The studio uses a free working width of at least 0.60 m between the structure and the toe of the slope. The excavation edge must keep a clear strip of at least 1 m if the wall is sloped (at least 50 cm if shored, according to the ordinance) and at least 1 m along a plant track according to the studio. A guardrail is placed beyond a 2.00 m fall hazard according to manual values.
- The berm: the ordinance requires proof of slope safety signed by a specialised engineer or geotechnical expert, particularly beyond a slope height of 4 m, in the event of additional loads or water inflows. The studio displays a red alert beyond 4 m and suggests an intermediate horizontal bench (berm) of 1 m recommended at mid-height.
From in-situ volume to bulked volume: trucks and backfill
Earth in place in the ground has been compacted for centuries. As soon as bucket teeth break it down, its volume increases under the effect of air: this is bulking. One cubic metre measured in place at the bottom of the excavation yields a significantly higher volume once loaded onto the skip. The studio allows you to select six typical Swiss soils with starting bulking coefficients and unit masses: compacted moraine, sandy gravel from the Plateau, weathered or sandstone molasse, clayey silt or old urban backfill.
The studio calculates the bulked volume for transport and deducts the volume required for peripheral backfilling. If the natural soil is unsuitable for backfilling, imported gravel is planned. The total evacuated mass is then divided by the truck's changeable payload (18 t for a four-axle truck) to obtain the number of rotations. Sorting relies on manual channels: surface recovery, type A landfill for unpolluted excavation materials, type B for lightly polluted materials or type E for polluted soils requiring analysis.
Frequent measurement errors by small earthmoving companies
The costly mistake on site consists in costing soil disposal by confusing the in-situ volume in the bill of quantities with the actual volume on the truck. Companies are often seen ordering skips based on the theoretical cube of the tender. From the first days of excavation, the platform becomes congested, the number of rotations explodes and the landfill charges a tonnage much higher than forecast. The earthmover then finds themselves forced to negotiate a delicate addendum or cut into their gross margin.
Another frequent trap concerns forgetting the working extra width and the clear strip at the top of the slope. Excavating flush with the future concrete prevents proper installation of drainage and forces the excavator to re-excavate underpinnings once the formwork is in place. The action that avoids these disorders consists in modelling the excavation with its peripheral space of 0.60 m and its clear strip of 1 m, then immediately applying the soil bulking coefficient before ordering transport.
Contractor responsibility on site and quantities
The free studio runs 100% in your web browser, without registration and without an account. Nothing is sent to a server, nothing is saved and closing the tab erases the data. The printout carries an Art Construction watermark and the CSV export mentions the free version. The bill of quantities gives workshop quantities without prices. To save your files per construction site, price with the ACIP cantonal database and collaborate, the link to the ERP, the Portail or the Tenders module opens professional management functions.
These calculations constitute decision-support pre-dimensioning based on modifiable manual values. They do not replace soil investigation or contractor responsibility. Beyond a height of 4 m, in the presence of water tables, unstable ground or a neighbouring building, a calculation note signed by a civil engineer according to SIA 267 standard is required. The client also indicates waste channels in their permit application when the quantity will likely exceed 200 m³ (waste ordinance).
Frequently asked questions
What is the difference between the straight cube and the sloped volume?
The straight cube simply multiplies the surface area at the bottom of the excavation by the depth. The volume with slope applies the prismoidal formula by incorporating the flare of the inclined walls. The angle depends on the ground and the construction work ordinance, which significantly increases the mass of excavated earth.
How to calculate the number of trucks to evacuate spoil?
The studio applies the soil bulking coefficient to the in-situ volume to find the volume on the truck. The evacuated tonnage is calculated using the in-situ volume and the soil unit mass; it is divided by the truck payload, set for example at 18 t for a four-axle truck.
Why must topsoil be stripped and counted separately?
According to the waste ordinance, unpolluted earthy materials must be sorted and recycled as much as possible. Fertile topsoil is surface-stripped to a dedicated thickness, stored separately on the construction site for reuse in landscaping, without being mixed with deep mineral spoil.
What slope gradient should be chosen depending on the nature of the ground?
The construction work ordinance requires adapting the slope to soil resistance. The studio uses indicative starting values: 1:1 for low-resistance soil, 2:1 for medium ground and 3:1 for very resistant soil. In case of water or rain, the studio lowers the slope by one class. Geotechnical data takes precedence.
When does an engineer's calculation note become mandatory for a slope?
The construction work ordinance requires proof signed by a specialised engineer or geotechnical expert, particularly beyond a slope height of 4 m, or in the event of additional loads at the top or water inflows. The studio displays a red alert from 4 m.
What is the free working space at the toe of the slope?
This is a horizontal extra width reserved between the outer skin of the finished structure and the toe of the earthworks slope. The studio uses a free working width of at least 0.60 m to allow for formwork, waterproofing of buried walls and laying of drainage pipes.
Is my volume calculation data kept online?
No. In this free version, the calculation is carried out entirely within your web browser. No file or figure is sent to a server. As soon as you close or reload your tab, the data is erased. Saving to a server requires the professional construction site management module.