Insulation is not chosen on its thermal conductivity λ alone. On a façade, reaction to fire limits combustible products according to the height of the building; on a roof, summer comfort and mass count; against the ground, resistance to moisture and compression rules out most fibrous materials. In Switzerland, the reaction to fire of building materials is classified under the fire protection regulations of the AEAI (VKF) into categories RF1 (no contribution to fire), RF2, RF3 and RF4, with the mention “cr” for critical behaviour that restricts use.
The Insulation studio calculates the U-value of a wall with the insulation of your choice and gives the reaction-to-fire class of each insulating layer. For a façade, it applies a table by height category and shows whether RF1 fire barriers are needed. It also gives the mass of the layers for the KBOB life-cycle assessment when the material is matched in it. It gives no price: material cost is priced in Soumissions.
Worked example: six insulation materials to reach U ≤ 0.17 on the same wall
200 mm reinforced concrete wall, 15 mm internal plaster and 15 mm render (resistance excluding insulation: 0.3036 m²·K/W with Rsi = 0.13 and Rse = 0.04). Insulation to be added for U ≤ 0.17 W/(m²·K). The λ values and fire classes are the studio’s generic values, to be replaced by those of the product.
| Insulation | λ (W/(m·K)) | Calculated then chosen thickness | U obtained (W/(m²·K)) | Reaction to fire (studio) |
|---|---|---|---|---|
| Glass wool | 0.035 | 195.3 → 200 mm | 0.1662 | RF1 |
| Stone wool | 0.036 | 200.8 → 210 mm | 0.1629 | RF1 |
| Wood fibre | 0.038 | 212.0 → 220 mm | 0.1641 | RF3 |
| Blown cellulose | 0.039 | 217.6 → 220 mm | 0.1682 | RF3 |
| Expanded polystyrene (EPS) | 0.036 | 200.8 → 210 mm | 0.1629 | RF3 (cr) |
| PIR / PUR rigid foam | 0.025 | 139.5 → 140 mm | 0.1694 | RF3 (cr) |
For U ≤ 0.17, RT ≥ 5.882 m²·K/W is needed, so insulation with R ≥ 5.882 − 0.3036 = 5.579. The minimum thickness is R × λ: 5.579 × 0.035 = 0.1953 m for glass wool, 5.579 × 0.025 = 0.1395 m for PIR. Rounded up to 10 mm boards, glass wool at 200 mm gives R = 5.714, RT = 6.018 and U = 0.1662; PIR at 140 mm gives R = 5.600 and U = 0.1694.
The installed masses differ a great deal: about 6.0 kg/m² for 200 mm of glass wool (30 kg/m³), 12.6 kg/m² for 210 mm of stone wool (60 kg/m³), 3.8 kg/m² for 210 mm of EPS (18 kg/m³). Mass affects summer time lag and fixing. On a medium-height façade, the studio table only accepts RF1 materials without further measures and asks for fire barriers with an RF3 (cr) material.
PIR reaches 0.17 with 140 mm and cellulose with 220 mm; the final choice also depends on the fire class required by the height and on the mass, not on λ alone.
3 common mistakes when choosing insulation
Comparing λ values of different kinds
A generic λ, a declared λ and a design λ are not equivalent. Compare the design values from the data sheets and enter them in the layer values.
Ignoring the height of the building
A combustible material accepted on a house may require fire barriers or be excluded on a taller building. Confirm the rule with the cantonal building insurer before tendering.
Laying fibrous insulation against the ground
Against the ground and under a base slab, materials that resist water and compression are used, such as XPS or cellular glass. Mineral wool has no place there.
How to use it in 3 steps
- Build the typical wall
Load the closest preset, for example “Façade insulated on the outside”, and set the limit value to be reached. - Swap the insulation and adjust the thickness
Replace the insulating layer with each product considered, enter its λ and fire class, then increase the thickness until the verdict reads “Lower or equal”. - Read the Fire and ecology tab
Choose the height category to see whether the façade rule is met or fire barriers are needed, note the mass, then print the comparison.
What the free version does not do
The studio gives no price or material cost, and its reaction-to-fire table by height is a parameter not checked against the cantonal insurers’ source: confirm the applicable rule, which also depends on the façade system (rendered or ventilated). It does not assess compressive strength, water absorption or the fire performance of a complete system.
With Soumissions, each insulation variant becomes a tender item priced with the price database; the ERP then tracks the purchases, the hours and the invoicing of the site.
Frequently asked questions
What do RF1, RF2, RF3 and RF4 mean?
They are the Swiss AEAI reaction-to-fire categories: RF1 no contribution to fire, RF2 low contribution, RF3 acceptable contribution, RF4 unacceptable contribution. The mention “cr” flags critical behaviour.
Is the thinnest insulation the best?
It saves space, but not necessarily on reaction to fire, summer comfort or the life-cycle assessment. Compare these criteria together with the U-value.
Does the studio give the cost of insulation?
No. It gives the thickness, the U-value, the fire class and the mass. The price is worked out in Soumissions with the price database.
Can I enter a specific product?
Yes. Open the design values of the layer and enter the λ, ρ, c, μ and reaction-to-fire class stated by the manufacturer.