A small apartment block heated with gas or oil often needs more output than the largest common air/water heat pump template. The usual answer is to install two or more units working together: this is called a cascade. The demand is covered, but the noise of the installation increases, and it is often the noise that decides the location.
The heat pump, noise and solar studio shows 'cascade required' when no single template covers the required output: it then takes the largest template of the chosen type and counts the number of identical units needed. You can also set the number of units in the noise tab. On the acoustic side, it adds 10 × log10(n) to the unit's sound power level (+3 dB for two, +4.8 dB for three). The demand calculation method is described on the sizing page; the details of the noise radar, on the noise calculator page.
Worked example: six flats heated with gas
Small apartment block with six flats, condensing gas boiler, 120,000 kWh of gas a year (gross calorific value on the bill), hot water included, radiators at 55 °C, design temperature of −8 °C. Units placed in front of the facade, most exposed neighbouring window at 20 m, noise sensitivity level II. Studio starting values and generic templates, to be replaced by the manufacturer's data sheet.
| Quantity | 1 unit (for comparison) | 2 units in cascade | Remark |
|---|---|---|---|
| Output at 55 °C | 35 kW | 2 × 35 = 70 kW | required: 43.0 kW |
| Night sound power level | 62 dB(A) | 62 + 3.0 = 65.0 dB(A) | +10 × log10(2) |
| Night Lr, normal mode | 43.0 dB(A) | 46.0 dB(A) | PV SL II: 45 dB(A) |
| Night Lr, silent mode | 39.0 dB(A) | 42.0 dB(A) | margin of 3.0 dB |
| Electricity per year (SCOP 3.25) | insufficient alone | 31,569 kWh | useful heat 102,600 kWh |
Useful heat: 120,000 kWh gross × 0.9 (conversion to net calorific value) × 0.95 = 102,600 kWh. Average output: 102,600 ÷ 2,300 h = 44.6 kW; at −7 °C: 44.6 × 27 ÷ 28 = 43.0 kW. The studio's largest outdoor air/water template delivers 35 kW at 55 °C: two are needed. Electricity: 102,600 ÷ 3.25 = 31,569 kWh a year.
Noise, studio formula: Leq = LWA + 10 × log10(n) − 11 + Dc − 20 × log10(distance). In front of a facade, Dc = 6. For two units at night: 62 + 3.01 − 11 + 6 − 26.02 = 34.0 dB(A), then Lr = Leq + 10 (night correction) + 2 = 46.0 dB(A), i.e. 1 dB above the planning value. In silent mode (58 dB(A) per unit), Lr falls to 42.0 dB(A).
Two units cover the 43 kW required, but their combined noise exceeds the night planning value by 1 dB at 20 m: silent mode, another location or other measures must be studied before submitting the file.
3 common mistakes with heat pumps in cascade
Doing the noise assessment with a single unit
The sound power level on the data sheet applies to one unit. With two identical units side by side, the level rises by 3 dB, with three by 4.8 dB. An assessment made for one unit underestimates the noise and may be rejected.
Adding up outputs without looking at the controls
Two 35 kW units cover 43 kW, but the installation must switch on the second one only when needed. The cascade controls and the sharing of operating hours are set with the manufacturer and the installer; the studio does not calculate them.
Putting all the units in a corner
In an inside corner, the directivity becomes Dc = 9 instead of 6 in front of a facade: 3 dB more at the neighbour's. With an already loud cascade, the location often matters more than the choice of enclosure.
Study a cascade in the studio in 3 steps
- Let the studio count the units
Enter the demand (consumption or floor area) and choose the unit type and the emitters. If the 'cascade required' alert appears, the studio shows the number of identical units and their output. - Place the units and the neighbouring windows
In the noise radar, place the unit and the neighbours' windows on the plan, set the number of units in cascade and the sensitivity level. The studio adds 10 × log10(n) to the sound power level. - Try the measures and print
Switch on silent mode, a timer or an enclosure, or move the units, until you stay below the planning value with a margin. Print the sheet for the assessment and the installer.
What the studio does not do for a cascade
The studio does not size the controls, buffer tanks or pipework, and assumes identical units. The templates, SCOP values and sound power levels are generic: the manufacturer's data sheet is authoritative. The acoustic result is an estimate following the Cercle Bruit implementation guide; the official assessment is signed by the applicant or their installer.
Soumissions takes over the quantities to cost the installation; the ERP tracks the site, purchases and invoicing; the Portail chantier keeps the noise assessment and data sheets with the building's file.
Frequently asked questions
How many dB does a second identical heat pump add?
About 3 dB to the sound power level: the studio adds 10 × log10(2) = 3.0 dB. Three identical units add 4.8 dB.
Can the studio mix two different units?
No, it counts identical units. For two different models, the sound power levels must be added separately, using the manufacturers' data sheets.
What if the cascade exceeds the planning value?
Try silent mode, the timer, an enclosure, another location further away or out of a corner, or a ground-source heat pump, which has no outdoor noise.
Does the studio always choose the largest template for a cascade?
In automatic mode yes, then it counts the units. You can set another number of units or enter a manufacturer's data sheet in free entry.