In a rental building or a condominium, a photovoltaic system on the roof produces for the whole building, while each flat has its own meter. The self-consumption group (ZEV, called RCP in French-speaking Switzerland) makes it possible to consume this power on site between several consumers: it is provided for by the federal Energy Act (EnA) and its ordinance (EnO), with rules on connection, metering and relations with tenants. More recent forms exist or have been announced, such as the virtual ZEV and the local electricity community: their conditions should be checked with the grid operator and in the texts in force.
The heat pump, noise and solar studio does not set up a ZEV, but it gives the two figures needed to discuss one: the annual solar output of the roof and the electricity demand of the building, households and heat pump included, with a self-consumption rate capped at 85% of the demand. Coupling a heat pump with solar (SG-Ready control, battery) is detailed on the coupling page; the one-off remuneration, on the Pronovo page.
Worked example: six flats, a shared heat pump and 150 m² of roof
Small apartment block with six flats in the lowlands, roof facing south and pitched at 30°, 150 m² usable, global irradiation of 1,150 kWh/m² a year. Current heating with gas (60,000 kWh gross a year, condensing), replaced by a shared air/water heat pump at 35 °C. Households estimated at 2,500 kWh per flat a year, an example value. Studio starting values, to be checked.
| Quantity | Calculation | Result |
|---|---|---|
| Modules on the roof | 150 m² × 0.82 ÷ 1.99 m² | 61 modules |
| Array output | 61 × 0.45 kWp | 27.45 kWp |
| Annual production | 27.45 × 1,150 × 1.12 × 0.84 | 29,699 kWh |
| Heat pump electricity | 51,300 kWh ÷ SCOP 4.40 | 11,659 kWh |
| Households (6 flats) | 6 × 2,500 kWh | 15,000 kWh |
| Total building demand | 11,659 + 15,000 | 26,659 kWh |
Solar array: the studio counts 82% of the usable area covered by modules of 1.99 m² and 0.45 kWp, i.e. 61 modules and 27.45 kWp. Production: output × irradiation × orientation factor (1.12 for a south roof at 30°) × system efficiency (0.84) = 29,699 kWh a year. Heat pump: 60,000 kWh gross × 0.9 × 0.95 = 51,300 kWh of heat, 21.5 kW required at −7 °C, 29 kW template at 35 °C, SCOP 4.40, hence 11,659 kWh of electricity.
Over the year, the roof produces 29,699 kWh for a demand of 26,659 kWh, about 1.1 times the demand. But production is high in summer and the heat pump consumes mainly in winter: a large share of the summer power is fed into the grid, and winter is partly covered from the grid. The studio shows the estimated self-consumption rate; it is this rate, not the annual balance, that counts for a ZEV.
The roof covers the building's annual demand in volume, but not at the same time: the ZEV mainly adds value to the share consumed on site, which the studio estimates without splitting it between the flats.
3 common mistakes when preparing a ZEV with a heat pump
Reasoning on the annual balance instead of self-consumption
Producing as much as the building consumes over the year does not mean consuming everything on site. The heat pump draws mainly in winter, when the roof produces little: look at the self-consumption rate, not only the annual kWh.
Forgetting metering and contracts
A ZEV requires suitable metering, internal rules and, for tenants, legal rules on billing electricity. These points are settled with the grid operator and specialist advice, before the works.
Sizing the heat pump without the electricity demand
The shared heat pump often becomes the building's largest consumer. Calculate its annual electricity first, then the solar array: otherwise the sharing of power rests on an underestimated demand.
Prepare the figures for a ZEV in the studio in 3 steps
- Size the heat pump
Enter the current consumption or the floor area, hot water, the location and the emitters. The studio gives the unit and its electricity per year. - Describe the roof and the household demand
In the solar tab, enter the usable area (or the output), the orientation and the pitch, then the household demand. The studio calculates the production and the total demand of the building. - Read the self-consumption and print
Note the production, the demand, the self-consumption rate and the share fed into the grid, try SG-Ready control or a battery, then print the sheet for the grid operator and the ZEV adviser.
What the studio does not calculate for a ZEV
The studio does not split the power between flats, does not calculate meters, internal tariffs or contracts with tenants or owners, and does not say whether a virtual ZEV or a local electricity community is possible on your grid. It has no hourly profile: self-consumption is an annual estimate. The applicable rules should be checked in the Energy Act, its ordinance and with the grid operator.
Soumissions costs the solar installation and the heat pump from the quantities; the ERP tracks the site, purchases and invoicing; the Portail chantier keeps the sheet, the plans and the ZEV documents with the building's file.
Frequently asked questions
What is a ZEV?
A group of several consumers in the same building or on the same site who jointly consume the power produced on site, under the federal Energy Act. The exact conditions should be checked with the grid operator.
Does the studio calculate the share of each flat?
No. It calculates the production, the building's demand and an overall self-consumption rate. The split between flats depends on the meters and the ZEV rules.
Can the shared heat pump be part of the ZEV?
It is a consumer of the building: its electricity is counted in the studio's demand. Its connection within the ZEV is settled with the installer and the grid operator.
Does the studio take the one-off remuneration into account?
Yes, in the solar tab, with an editable scale: the details are on the Pronovo page. Subsidies and their conditions change: check them before submitting an application.