Mobile Negative Pressure Air Scrubbers: Dust Containment in Occupied Renovations

Technical guide to negative pressure mobile air scrubbers in occupied Swiss sites: HEPA filtration, containment integrity, and OTConst compliance.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: The escape of fine dust outside the work area leads to deep cleaning and remediation work, with unexpected costs frequently ranging between 3 500 CHF and 12 000 CHF for an occupied flat. If the contractor has not implemented appropriate technical measures, these expenses remain entirely at their expense under art. 364 CO.
  2. Legal / Joint Body / SUVA: Under art. 33 OTConst, air quality must be maintained and hazardous substances must be exhausted, filtered, or diluted using mechanical ventilation. Pursuant to art. 82 LAA, the employer takes the necessary steps to prevent occupational illnesses. Knowingly endangering health by failing to observe the recognized rules of the trade exposes violators to criminal prosecution under art. 229 CP.
  3. Administrative / Acceptance: Damaging finishes in an occupied home or contaminating communal areas triggers client complaints, which can jeopardize the joint inspection report under standard SIA 118 and delay final payment for the work under art. 372 CO.

During rehabilitation and alteration work in occupied premises, managing airborne particulates poses an ongoing technical challenge for site management and trade contractors. Sawing, chiselling, and sanding release respirable mineral dust that easily penetrates conventional physical barriers unless negative pressure is maintained. Setting up a mobile negative pressure air scrubber creates a targeted airflow into the work zone, ensuring contaminated air is extracted and filtered before discharge, thereby safeguarding the residents' immediate environment.

This equipment guide details the key criteria for selecting and sizing a mobile negative pressure and air purification system on a Swiss construction site. In accordance with art. 3 OTConst, operations must be planned to reduce the risk of harm to health, while art. 4 OTConst requires a written plan detailing the necessary safety and protective measures. Combining an airtight casing, high-capacity prefilters, and absolute filtration stages allows the contractor to meet clean air requirements while protecting the overall profitability of their project.

Technical sizing criteria and regulatory requirements

Selecting a mobile negative pressure air scrubber for occupied premises depends on the unit's total airflow capacity and the efficiency of its filtration sequence. In accordance with art. 33 OTConst, airborne hazardous substances must be discharged into the open air, filtered, or diluted by mechanical ventilation so that air quality at workstations remains within permissible exposure limits. During interior renovation work, depressurizing a room requires sufficient volumetric flow to offset the air infiltration inherent to airlocks and temporary partition walls.

To calculate the actual flow rate needed on the construction site, site management and installers evaluate the geometric volume of the room alongside the required air change rate per hour. The overarching framework for prevention stems from art. 82 LAA, which requires employers to take all measures shown by experience to be necessary, feasible according to state-of-the-art technology, and tailored to the given circumstances. This general principle is supplemented by art. 3 OPA regarding protective installations built according to technical rules, as well as art. 4 OTConst concerning the preparation of a written health and safety plan prior to opening the construction site.

Filtration stages and airflow management

An efficient air purification setup relies on multiple successive barrier stages to safeguard the terminal high-efficiency filter:

  • Coarse prefiltration: traps heavy plaster, masonry, or cutting dust to prevent premature clogging of the secondary filter media.
  • Intermediate filtration: captures medium-sized particulates to extend the service life of the terminal filter without sudden pressure drops.
  • Absolute terminal filtration: captures respirable mineral dust fractions and microparticles before cleaned air is discharged outdoors or recirculated in a controlled manner.

When the construction site involves risks related to especially hazardous substances such as asbestos or PCBs, art. 32 OTConst stipulates that if the presence of such materials is suspected, the employer must identify and assess the hazards, plan the required measures, and inform workers of diagnostic findings. Furthermore, should such a substance be uncovered unexpectedly, work must stop immediately and the client or their representative must be informed, pursuant to art. 32 OTConst. If work releasing significant amounts of asbestos fibres must be performed, art. 82 OTConst mandates that it may only be carried out by CNA-recognized asbestos removal contractors.

Clog indicators and maintaining negative pressure

Monitoring filter pressure drop through visual or audible indicators ensures the containment zone maintains continuous airflow integrity. An undetected drop in airflow leads to pressure equalization and pushes dust into communal corridors or occupied living spaces. Art. 5 OTConst requires the employer to appoint a competent person on every construction site responsible for occupational safety and health protection, who is authorized to issue instructions to workers. This active site supervision prevents containment failure.

To protect workers' respiratory tracts whenever technical capture or filtration measures prove insufficient on their own, art. 33 OTConst mandates the use of respiratory protective equipment. In keeping with general health protection principles, art. 18 OLT 3 addresses air pollution, while art. 27 OLT 3 covers personal protective equipment. All machinery deployed on site must satisfy the technical requirements of the Machinery Safety Ordinance (OMach, RS 819.14).

Comparative table of mobile air scrubber setups

Selecting mobile equipment depends on the spatial layout, the types of pollutants generated, and the level of containment specified in the contract for work under art. 363 CO. The following table outlines standard operational configurations encountered on Swiss rehabilitation sites.

Air scrubber setupTechnical and regulatory frameworkTypical use on the construction siteOn-site inspection checkpoints
Compact single-room scrubber (polythene dust airlock)art. 33 OTConst (air quality and filtration), art. 82 LAABathroom or kitchen renovation in an occupied flatSealing around duct penetrations, prefilter clogging, sheeting condition
Medium-capacity mobile air scrubber with outdoor exhaustart. 33 OTConst (exhaust into open air), OMach, RS 819.14Demolition of brick partitions or interior screed grindingExhaust duct attachment, avoiding backdraft toward adjacent windows
Heavy extraction unit with sealed housingart. 3 OTConst (planning), art. 32 OTConst (hazardous substances)Full-floor strip-out with suspected airborne contaminantsDifferential pressure gauge calibration, competent person's inspection log
Mobile filtration unit with variable speed controlart. 18 OLT 3, art. 33 OTConst (mechanical ventilation)Dust-generating finishing work in occupied commercial spacesNoise levels matching local limits, intake grille condition
Scrubber for modular rigid airlock containmentart. 3 OPA, art. 4 OTConst (written safety plan)Major remediation in residential stairwells or entrance hallsStructural stability of the airlock, airtight exhaust duct connections

Purchasing and installation errors and financial consequences

Miscalculating airflow rates or paying insufficient attention to duct sealing leads to severe technical setbacks on Swiss sites. Art. 364 CO reminds contractors that they are liable for any negligence and must procure at their own expense the tools and resources needed to execute the work.

  • Inadequate airflow sizing: purchasing a unit with insufficient flow rate fails to establish the necessary negative pressure. Dust escapes into adjacent occupied areas, triggering specialized cleaning costs typically running between 2 800 CHF and 6 500 CHF for a single home.
  • Exhausting air into an enclosed lightwell: discharging contaminated air through a transom window into a lightwell allows dust to be drawn back into residents' ventilation openings. Emergency rehousing or facade cleaning expenses can easily reach 4 000 CHF to 9 000 CHF.
  • Failure to monitor filters during works: running without a differential pressure alarm leads to quiet filtration failure. Pursuant to art. 366 CO, the client can set a deadline to correct the defective work and have the project completed at the contractor's expense.
  • Disregard for building rules and safety: intentionally disregarding the recognized rules of the trade during execution and knowingly endangering life or bodily integrity triggers penalties under art. 229 CP.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and scenarios outlined below serve as illustrative examples designed to clarify how the rules of the trade apply in practice.

Scenario 1: Renovation of a PPE apartment in an occupied building (Canton of Vaud)

On a renovation site in the canton of Vaud, a general contractor with three workers is demolishing two clay brick partition walls and grinding 65 m² of cement screed in a co-owned residential building with neighbouring flats fully occupied. Demolition and wall-chasing activities release substantial volumes of crystalline silica dust.

To comply with art. 33 OTConst, the contractor erects an airtight polythene containment airlock at the flat's entrance door. They install a mobile air scrubber equipped with prefiltration and a terminal high-efficiency filter. The air is vented outside through a flexible duct routed through an insulated window panel on the balcony. The unit runs at a steady flow rate that maintains continuous negative pressure, preventing fine dust from escaping into the communal stairwell. Investing around 2 400 CHF in equipment and consumables prevented a dispute with the co-owners and avoided compensatory cleaning costs of over 5 000 CHF.

Scenario 2: Washroom renovation in an administrative office building (Canton of Geneva)

In a commercial building in the canton of Geneva, tile chiselling and complete pipework replacements are scheduled on a floor shared with two operating professional service firms. The on-site crew consists of two plumbing installers.

In accordance with art. 3 OTConst, prior project planning accounted for dust risks and the uninterrupted operations of neighboring tenants. The contractor commissions a mobile negative pressure air scrubber fitted with a differential pressure monitor. Mineral dust is captured at the source, while exhaust air is directed into a sealed service shaft. Appointing a competent person under art. 5 OTConst ensures daily checks of filter condition and actual negative pressure levels. This setup prevents operational disruptions for the adjacent offices and ensures compliant delivery of the works under art. 367 CO.

Free construction site calculators

Thirty-five trade calculators: site installations, waste, concrete, screeds, insulation, scaffolding. No sign-up required.

View trade calculators

Frequently asked questions

What legal basis mandates air filtration in contained zones?

Under art. 33 OTConst, hazardous substances must be filtered, exhausted outdoors, or diluted to preserve air quality. Art. 82 LAA requires employers to implement these appropriate protective measures, avoiding disputes over cleaning costs typically around 1 200 CHF.

How should containment be documented before demolition begins?

Art. 4 OTConst requires drawing up a written health and safety plan setting out the site measures in detail. The contractor records the ventilation and extraction layout in it, preventing performance delays under art. 366 CO whose additional costs often reach 800 CHF per day.

Who is responsible for monitoring the air scrubber on the construction site?

Pursuant to art. 5 OTConst, the employer appoints a competent person on each construction site who is responsible for occupational safety and authorised to issue directives. This person checks the condition of exhaust ducts and saturation gauges, preventing technical shutdowns estimated at nearly 950 CHF.

Can the client reject the work if dust escapes?

Yes. Under art. 367 CO, the client gives notice of defects after verification. Silica residues in occupied areas justify remedial work at no extra charge under art. 368 CO. The contractor must then bear the cost of full decontamination, with restoration expenses that can exceed 3 500 CHF.

How should unexpected airborne pollutants be managed during renovation work?

Under art. 32 OTConst, if an especially hazardous substance is discovered unexpectedly, work must be stopped immediately and the client informed. The contractor also applies art. 365 CO by reporting this circumstance that jeopardises performance, avoiding additional remediation costs of 4 000 CHF.

Is the contractor responsible for the cost of air extraction equipment?

Under art. 364 CO, unless agreed or customary otherwise, the contractor provides at their own expense the resources, plant and tools needed to complete the work. Investing in a mobile air scrubber, roughly 2 200 CHF, forms an integral part of their material obligations to deliver compliant work.

Controlling negative pressure and air extraction in occupied premises protects workers' health while securing acceptance of the work without financial deductions. To find out more about selecting equipment and extraction protocols on your Swiss construction sites, consult our dedicated technical guides: