On a load-bearing reinforced concrete wall, the ventilated façade is very common: fibrous insulation fixed against the concrete, a vapour-open breather membrane, a ventilated air gap, then timber, fibre-cement or metal cladding. When it comes to pricing the insulation, the same question comes back: what insulation thickness is needed to get below the limit value, and what is the air gap worth in the calculation? The answer is simple, but it is often applied wrongly.
The Wall section studio calculates the U-value of a wall made of homogeneous layers, from inside to outside, using the method of EN ISO 6946. It does not calculate a ventilated air gap: the wall stops at the breather membrane and the external surface resistance Rse is set as for still air. The studio then shows the U-value, the total resistance, the temperature profile, the Glaser diagram and the comparison with the limit value you choose, for example the MoPEC 2025 one. This calculation covers the plain wall only: the thermal bridges of the cladding brackets need a separate calculation.
Worked example: insulation thickness for a ventilated façade on 200 mm concrete
New apartment building, 200 mm reinforced concrete load-bearing wall with 10 mm internal gypsum plaster. Stone wool insulation, vapour-open breather membrane, ventilated air gap and cladding. Target limit value: 0.17 W/(m²·K), the MoPEC 2025 preset for a new element against the outside. Material values: generic studio values, to be replaced with the manufacturer's.
| Layer or surface | d (mm) | λ (W/(m·K)) | R (m²·K/W) |
|---|---|---|---|
| Rsi, internal surface | – | – | 0.130 |
| Gypsum plaster | 10 | 0.51 | 0.020 |
| Reinforced concrete | 200 | 2.3 | 0.087 |
| Stone wool | 200 | 0.036 | 5.556 |
| Vapour-open breather membrane | 0.5 | 0.3 | 0.002 |
| Rse taken as still air (ventilated gap) | – | – | 0.130 |
| Total resistance Rtot | – | – | 5.924 |
Each resistance is R = d / λ: 0.200 m ÷ 0.036 = 5.556 m²·K/W for the stone wool, 0.200 ÷ 2.3 = 0.087 for the concrete. Because the air gap is strongly ventilated, the cladding and the gap do not count, and the external resistance is taken equal to the internal one, 0.13 instead of 0.04. The exact sum is 5.924 m²·K/W (the table values are rounded), hence U = 1 / 5.924 = 0.169 W/(m²·K), below the 0.17 limit. With only 180 mm, Rtot drops to 5.368 and U rises to 0.186: the limit is not met.
The concrete stays on the warm side: the calculated temperature at the inner face of the insulation is about 19 °C for 20 °C inside and −5 °C outside, and the Glaser diagram shows no condensation, because the layers become more and more vapour-open towards the outside (sd of 20 m for the concrete, 0.2 m for the stone wool, 0.1 m for the membrane). In the tender, 200 mm is kept, bearing in mind that the cladding brackets add losses not included in this U-value.
With 200 mm of stone wool at λ = 0.036, the plain wall reaches U = 0.169 W/(m²·K), below 0.17, with no condensation in the concrete.
3 frequent mistakes on the U-value of a ventilated façade
Counting the cladding and the air gap
Adding the resistance of the cladding and of a ventilated air gap gives a U-value that is too flattering. With a strongly ventilated gap, everything outside the gap leaves the calculation; only an unventilated gap has a tabulated resistance.
Keeping Rse = 0.04
The 0.04 resistance applies to a surface exposed to the wind. Behind a ventilated gap, the membrane is sheltered: a still-air resistance equal to Rsi is used. The difference is small, but it matters when you are right at the limit.
Forgetting the cladding fixings
The metal brackets and angles pass through the insulation. The U-value of the plain wall does not include them: allow a margin in thickness or have these point thermal bridges calculated for the fixing system chosen.
Three-step guide in the Wall section studio
- Enter the wall up to the membrane
Choose the wall type, horizontal heat flow, then add the layers from inside to outside: plaster, reinforced concrete, insulation, open membrane. Add neither the ventilated gap nor the cladding. - Set Rse and the limit value
Replace the external surface resistance with 0.13, as for still air. Choose the limit value preset that matches your project, then enter the manufacturer's λ values. - Adjust the thickness and check Glaser
Vary the insulation thickness until you are below the limit. Check the Glaser tab, then print the sheet or export the CSV for your file.
What the free version does not do for a ventilated façade
The studio calculates a homogeneous one-dimensional wall: it counts neither the cladding brackets, nor the anchors, nor the corners and window junctions. It does not calculate the airflow in the ventilated gap and does not check the fire protection of the façade. Material values are generic; the limit value is a parameter you choose and check in the text that applies to your project. For the rendered façade and its thermal bridges, see the Insulation studio page on the externally insulated façade.
With Soumissions, the calculated wall becomes tender items (insulation, membrane, substructure, cladding) with the cost database and a file per site. The ERP then tracks the job, the hours, the material purchases and the invoicing, with documents free of watermarks.
Frequently asked questions
Why does the ventilated air gap not count in the U-value?
Because outside air circulates in it: it does not insulate. The calculation method stops the wall at this gap and replaces the external resistance with that of still air.
What stone wool thickness gives U ≤ 0.17 on 200 mm of concrete?
With λ = 0.036 and an internal plaster, about 200 mm is needed, giving U = 0.169. With a better-performing insulant, the thickness drops: enter the manufacturer's λ value in the studio.
Is a vapour barrier needed on the inside of a concrete wall?
Generally not for this build-up: the concrete is already very vapour-tight and the open fibrous insulation is on the cold side. The studio's Glaser diagram lets you check it with your indoor and outdoor conditions.
Is the result enough for the energy certificate?
It gives the U-value of the plain wall. The cantonal energy proof also requires the thermal bridges and sometimes an overall balance: have it prepared by a professional.