Flat roof: warm roof with vapour barrier or inverted roof in XPS, U-value and condensation

Same slab, same target U-value, two opposite logics: where the waterproofing sits relative to the insulation changes everything on the vapour side.

Open the free studio →

Free, no account: your walls and your calculations stay in your browser.

On a concrete slab, a flat roof is built in two main variants. The warm roof places a vapour barrier on the slab, then the insulation (PIR, EPS, mineral wool), then the waterproofing and its protection. The inverted roof places the waterproofing directly on the slab, then an insulant that tolerates water, usually extruded polystyrene (XPS), ballasted with gravel or a green roof.

The Wall section studio calculates both with upward heat flow (Rsi = 0.10, Rse = 0.04): U-value, temperature profile, Glaser diagram and comparison with the limit value. It does not automatically calculate the U-value correction due to rainwater flowing under the insulation of an inverted roof: this correction is taken according to the calculation method and the product approval, and translates into a thickness margin. For the edge junction, see the 2D thermal bridge studio page on the parapet insulated on three faces.

Worked example: 220 mm slab, U ≤ 0.17 W/(m²·K) as a warm roof and as an inverted roof

Roof of a new apartment building, 220 mm reinforced concrete slab. Warm roof: vapour barrier, 140 mm PIR (λ 0.025), 10 mm two-layer bituminous waterproofing, 50 mm gravel. Inverted roof: waterproofing on the slab, XPS (λ 0.035), gravel not counted. Studio winter conditions: 20 °C and 50 % inside, −5 °C and 80 % outside. Generic values and example sd values, to be replaced with the products'.

U-value and Glaser check of the flat roof variants
VariantInsulationU (W/(m²·K))Condensation according to Glaser
Warm roof, vapour barrier sd 250 mPIR 140 mm0.168yes, under the waterproofing
Warm roof, vapour barrier sd 5,000 mPIR 140 mm0.168no
Inverted roof, before correctionXPS 200 mm0.167no
Inverted roof, before correctionXPS 220 mm0.152no

Warm roof: Rtot = 0.10 + 0.096 (slab) + 0.022 (vapour barrier) + 5.600 (0.140 ÷ 0.025) + 0.043 (waterproofing) + 0.063 (gravel) + 0.04 = 5.963 m²·K/W, so U = 0.168. On the vapour side, the upper waterproofing has an sd of about 500 m: with a vapour barrier of only 250 m, vapour gets in more easily than it gets out and Glaser places condensation under the waterproofing, at about −4 °C. With a vapour barrier much tighter than the waterproofing (sd 5,000 m in the example), the condensation disappears.

Inverted roof: Rtot = 0.10 + 0.096 + 0.043 + 5.714 (0.200 ÷ 0.035) + 0.04 = 5.993, so U = 0.167 before correction. The waterproofing is on the slab, on the warm side: no condensation. But the water passing under the XPS boards carries heat away: the required correction can push the result over the limit. With 220 mm, U = 0.152 leaves a margin for this correction.

140 mm PIR as a warm roof or 220 mm XPS as an inverted roof: about 0.17 W/(m²·K), provided that in the first case the vapour barrier is far tighter than the waterproofing.

3 frequent mistakes on a flat roof

A vapour barrier that is too open

On a warm roof, the waterproofing is very vapour-tight. If the vapour barrier is less so, moisture gets into the insulation and stays there. Compare the sd values of the two layers in the studio.

Forgetting the inverted roof correction

The U-value calculated without correction is too optimistic: rainwater flowing under the XPS cools the waterproofing. Apply the correction set by the method and the product approval, and allow extra thickness.

Neglecting the fall and construction moisture

A roof without sufficient fall holds water, and insulation laid wet on a warm roof stays wet. The minimum fall is checked in SIA 271 and with the manufacturer; protect the insulation until the waterproofing is laid.

Three-step guide for a flat roof

  1. Choose roof and upward heat flow
    Roof type: the studio proposes Rsi = 0.10 and Rse = 0.04. You can start from the ready-made example of a warm flat roof with vapour barrier.
  2. Enter the layers and their sd
    From inside to outside: slab, vapour barrier, insulation, waterproofing, ballast. For the inverted roof: slab, waterproofing, XPS. Enter the actual sd of the vapour barrier and the waterproofing.
  3. Compare and keep a margin
    Read U and the Glaser tab for each variant. For the inverted roof, add the thickness that covers the product's correction, then export the CSV.

Open the free studio →

What the free version does not do for a flat roof

The studio does not calculate the inverted roof correction, nor falls, nor water run-off, nor tapered insulation (boards of variable thickness), nor the thermal bridges of parapets, outlets and mechanical fixings. The Glaser condensate amount is indicative and does not account for drying in summer. Product values are entered from their technical data sheets.

With Soumissions, the chosen build-up becomes waterproofing and insulation tender items, with the cost database and a file per site. The ERP tracks the job, material purchases and invoicing.

Frequently asked questions

Warm roof or inverted roof: which to choose?

The inverted roof protects the waterproofing from impacts and temperature swings, but needs an insulant that tolerates water and a U-value correction. The warm roof is thinner for the same U-value with a high-performance insulant, but depends on a perfectly laid vapour barrier.

Is a vapour barrier needed on an inverted roof?

Generally not: the waterproofing laid on the slab does this job, on the warm side. The studio's Glaser diagram lets you check it for your build-up.

Does the gravel count in the U-value?

Its resistance is low. On an inverted roof, layers placed above the insulation are generally not counted. If in doubt, leave it out of the calculation.

Why does water under the XPS increase the U-value?

Cold rain flowing between the insulation and the waterproofing carries heat away from the slab. Calculation methods account for it with a correction, to be taken from the product approval.