When the façade of an old or listed building cannot be insulated from outside, internal insulation remains. Two families compete: mineral wool with a carefully sealed vapour control layer, and so-called capillary-active insulants (calcium silicate, mineral boards, some wood fibre boards) laid without a vapour control layer, bonded onto a levelling plaster. The latter accept a little condensation behind them, then redistribute the water by capillary action towards the room, where it dries.
The Wall section studio calculates the U-value and the Glaser diagram in steady state: it compares the vapour pressure with the saturation pressure, layer by layer, without capillary transport. It therefore shows very well where the dew point falls, but it cannot say whether the water will be taken up by the material. This page shows how to read the result without jumping to conclusions, with insulant λ and μ values entered by hand (calcium silicate is not in the generic library). For conventional internal insulation with a vapour control layer, see the Insulation studio page on the dew point.
Worked example: 380 mm solid brick wall insulated from inside
Old 380 mm solid brick wall, 20 mm mineral render outside, 10 mm gypsum plaster inside. Variants: 60 or 80 mm capillary-active board (example values from a manufacturer: λ = 0.06 W/(m·K), μ = 6), or 60 mm mineral wool under plasterboard without a vapour control layer. Studio winter conditions: 20 °C and 50 % inside, −5 °C and 80 % outside.
| Variant | Insulation added (mm) | U (W/(m²·K)) | θ behind the insulation (°C) | Condensation according to Glaser |
|---|---|---|---|---|
| Existing wall | 0 | 1.454 | 14.6 | no |
| Capillary-active board | 60 | 0.593 | 3.0 | yes |
| Capillary-active board | 80 | 0.495 | 1.7 | yes |
| Mineral wool without vapour control layer | 60 | 0.411 | 0.5 | yes |
Existing wall: Rtot = 0.13 + 0.020 + 0.475 (380 mm ÷ 0.8) + 0.023 + 0.04 = 0.688 m²·K/W, so U = 1.454 W/(m²·K). With 60 mm of board at λ = 0.06, R = 1.000 is added: Rtot = 1.688 and U = 0.593. With 80 mm, R = 1.333, Rtot = 2.021 and U = 0.495. The inner face of the brick, which was at 14.6 °C, drops to 3.0 °C then 1.7 °C: the wall becomes cold and that is where Glaser places the condensation.
With 60 mm at μ = 6, the insulant weighs only 0.36 m of sd against 3.8 m for the brick: the vapour pressure at the interface (about 1,085 Pa) exceeds saturation (about 756 Pa). Mineral wool without a vapour control layer does worse: the dew point falls at 0.5 °C. The real difference between these solutions lies in capillary transport and water uptake, which Glaser does not calculate: the manufacturer's test data or a hygrothermal simulation decide.
Real gain: U goes from 1.454 to 0.593 W/(m²·K) with 60 mm; the condensation predicted by Glaser is then judged by the capillary behaviour, outside the studio.
3 frequent mistakes with a capillary-active insulant
Deciding on Glaser alone
Glaser ignores capillarity: it also condemns systems that work. Nor does it prove that a system is safe. Use it to find the cold point, then base the decision on the manufacturer's tests or a dynamic simulation.
Fitting it too thick
The thicker the insulation, the colder the brick and the more water has to be redistributed. Manufacturers often limit the thickness of these systems: follow their instructions rather than aiming for a new-build U-value.
Ignoring driving rain
An exposed wall that gets wet from outside dries less well once insulated inside. Check the state of the render, the joints and rising damp before fitting anything.
Three-step guide to compare the variants
- Enter the existing wall
Wall type, horizontal heat flow: internal plaster, brick or stone, render. Note the U-value and the temperature of the inner face of the wall in the temperature profile. - Add the insulation with its values
Insert a layer on the inside and enter the product's λ and μ, or choose a mineral wool with or without a vapour control layer to compare. - Read Glaser as an indicator
Find the interface where condensation appears and its indicative amount over the chosen period. Print the sheet and pass it to the manufacturer or the building physicist.
What the free version does not do for internal insulation
The studio calculates neither capillarity, nor absorption and drying, nor driving rain, nor the thermal bridges at floor slabs and partition walls, which are critical with internal insulation. For these junctions, see the 2D thermal bridge studio page on the slab, the partition wall and the return strip. For a listed building, cantonal requirements may allow relaxations: check with the authority.
With Soumissions, the variants become comparable tender items with the cost database. The ERP then tracks the hours, purchases and invoicing of the renovation job.
Frequently asked questions
Why does Glaser predict condensation behind a capillary-active insulant?
Because this material is deliberately vapour-open: the vapour reaches the cold wall. Glaser counts this water, but it does not see that it is taken up by capillary action.
What internal insulation thickness is reasonable on an old wall?
Often a few centimetres, depending on the system's instructions and the state of the wall. The biggest gain comes from the first centimetres: in the example, 60 mm already more than halves the U-value.
Can I enter an insulant that is not in the library?
Yes. Take a similar layer and replace λ, ρ, c and μ with the manufacturer's design values.
Is a vapour control layer needed with internal mineral wool?
Generally yes, sealed continuously. The example shows that without it the dew point falls in the insulation, against the brick.