Excavation Slope Gradients and Shoring Rules According to OTConst

Excavation slope angles and shoring according to OTConst. Calculate your earthwork slopes with our free online tool, no installation needed.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

Beyond 1.50 m: Sloping, Shoring or Other Measures

On an earthworks construction site in Switzerland, excavation wall safety must comply with specific requirements. Under the Swiss Construction Works Ordinance (OTConst), as soon as the depth exceeds 1.50 m, an excavation wall that is neither propped nor shored must be sloped or secured with other measures. Leaving a vertical wall without support beyond this height exposes workers at the bottom of the excavation to sudden cave-ins. In our online studio, such a situation is flagged as blocking.

To support the ground, contractors choose between bulk excavation with an appropriate batter or installing a shoring system. Trench shoring must resist foreseeable loads and be dimensioned taking into account additional surcharges, such as vehicle traffic, plant movement, and stockpiled materials. Earthworks contractors or bricklayers prepare the operation by measuring the total excavation depth, including formation for the pipe bedding or blinding concrete.

In the free version of the studio, users test configurations directly in their browser without creating an account. Calculations run with no data transfer to a server and no internal storage. The tool compares the utilisation rate against 100% of the design value and indicates whether the setup is below the limit, displays a warning, or is blocked.

Slopes Suited to Ground Strength: Initial Baseline Classes

The OTConst specifies that the slope gradient must be adapted to the strength of the ground. Soils encountered on Romand construction sites exhibit highly variable mechanical behaviour depending on their compactness and geological nature. The studio provides six typical Swiss ground types with editable initial values: Plateau sandy gravel, dense moraine, weathered or marly molasse, sound sandstone molasse or compact limestone, clayey silt or soft lacustrine deposits, and heterogeneous historic urban fill. These figures derive from technical guidelines and must be replaced with data from a site-specific geotechnical report.

To start verification checks, the studio applies maximum initial slope gradients based on three indicative categories expressed as a vertical to horizontal ratio:

  • Low-strength ground: 1:1 slope;
  • Medium-strength ground: 2:1 slope;
  • High-strength ground: 3:1 slope.

These inclinations serve as indicative working values and do not originate from the wording of the ordinance itself. During excavation, site managers verify consistency between the actual soil layers observed in the excavator bucket and the initial design assumptions. Global slope stability is not modelled by the studio, which solely applies the guideline baseline slopes to calculate earthwork footprints and volumes.

Rain, Thaw, Water Ingress and Crest Surcharges

Weather conditions alter ground equilibrium. Water is a conventional cause of failure on temporary cut slopes. As soon as rain infiltrates, thaw sets in, or water ingress appears along a permeable layer, soil cohesion drops and ground unit weight rises. The wording of the ordinance requires adapting the slope and implementing measures whenever vibrations, surcharge loads, or adverse weather compromise ground stability.

To address these hazards, the studio applies an internal rule: it reduces the initial slope by one class to secure the site footprint. For instance, a medium-strength ground originally set at 2:1 switches to 1:1 as soon as moisture or water ingress is selected. This principle reduces the risk of slumping but considerably widens the surface footprint at the excavation crest.

Similarly, the presence of a surface axle load, such as an on-site lorry or an excavator in motion, exerts lateral thrust on the ground. In trench mode, the studio calculates this surcharge pressure using Boussinesq’s formula for a rigid wall; in excavation mode, it triggers an amber warning above a depth of 1.50 m if a load acts at the crest without suitable shoring.

When an Engineer's or Geotechnical Report Is Required

The OTConst mandates formal slope stability certification signed by a specialist engineer or geotechnical engineer in specific circumstances. This requirement applies in particular when the slope height exceeds 4 m, in the event of water ingress into the excavation, or when surcharge loads act at the crest. The regulatory 1.50 m threshold applies strictly to the obligation to slope or shore, not to the requirement for a certified engineer's report.

On site, as soon as an excavation reaches a significant depth, the studio displays a red alert beyond 4 m. It then recommends constructing a berm—a horizontal bench at least 1 m wide—typically positioned at mid-height to break the slope's continuity. This berm also facilitates slope maintenance and surface water drainage.

For permanent retaining structures or complex excavations located within the zone of influence of an adjacent building, the involvement of a civil or geotechnical engineer under standard SIA 267 remains mandatory. The studio provides geometric pre-dimensioning and volume estimations, but does not replace an engineer's design calculation report.

Clear Strip, Working Width and Edge Protection at the Crest

The perimeter around the crest of the excavation is governed by minimum clearance distances defined by the ordinance. The upper edge of the excavation must remain completely clear over a width of at least 1 m if the face is sloped, and at least 50 cm if it is propped or shored. No excavated spoil, equipment, or tools may encroach upon this protective margin.

Along access routes or plant tracks, the studio applies a clear setback of at least 1 m to prevent direct loads on the crest edge. At the base of the excavation, to allow formwork installation or pipe laying in adequate working conditions, a clear working width of at least 0.60 m is maintained between the toe of the slope and the external face of the structure.

To prevent falls from height, the studio also includes the provision of edge protection along the crest for drop heights exceeding 2 m. When trench shoring boxes are used, the shoring panel must extend at least 0.15 m above ground level to stop falling stones, and access ladders must project at least 1 m above ground surface.

Criminal Liability and the Contractor's Duty to Notify

In contract and statutory law, contractors shoulder stringent liabilities. Pursuant to the Code of Obligations (CO) and standard SIA 118, the contractor is bound by a duty to notify (devoir d'avis) and warn the client and site management if design drawings present safety risks or if actual ground conditions differ from expectations. Should a construction site accident occur, provisions of the Swiss Criminal Code may be enforced against site managers and technical executives.

The handling of excavated material is governed by the Waste Ordinance (OLED). Earth and excavation spoil must be segregated directly on the construction site and reused or recycled whenever uncontaminated. In their building permit application, the client must specify the type, quality, volume, and designated disposal routes as soon as the total quantity is likely to exceed 200 m³ or whenever hazardous pollutants are identified. If ground quality is uncertain, laboratory testing and coordination with the cantonal environmental agency are required.

The most expensive mistake on site typically involves opening a cut with an overly steep slope to minimise earthmoving, without verifying water ingress. Faces degrade rapidly under moisture, forcing the contractor to perform emergency clearing in the rain, widen the cut, and order unplanned skips. The technical best practice that prevents disputes is to sample the ground prior to digging, monitor water ingress, and establish the clear protective margin at the crest right from the start.

To refine your cost estimates and structure your earthworks quotes, explore our Soumissions solutions, use our ERP platform, or visit the Portail to centralise execution documents.

Frequently asked questions

At what depth is securing an excavation mandatory?

Under the Construction Works Ordinance (OTConst), any excavation wall deeper than 1.50 m that is neither propped nor shored must be sloped at a suitable angle or protected with other safety measures.

What width of clear strip must be maintained along the excavation edge?

The ordinance requires leaving a clear border of at least 1 m if the face is sloped, and at least 50 cm if it is shored or propped. No spoil or equipment may be placed within this strip.

When is an engineer's or geotechnical specialist's approval required?

The OTConst requires slope safety verification signed by a specialist engineer or geotechnical expert notably when the slope height exceeds 4 m, if water ingress occurs, or when surcharges act on the crest.

What initial slope gradients are applied in the studio?

The studio applies indicative baseline ratios of 1:1 for low-strength ground, 2:1 for medium-strength ground, and 3:1 for high-strength ground. These slopes are lowered by one class in the event of rain or water ingress.

What obligations does the OLED impose on excavated material?

According to the Waste Ordinance (OLED), excavated soils and spoil must be sorted on the construction site and recycled if uncontaminated. The permit application must specify disposal routes if the volume is likely to exceed 200 m³.

What features are included in the free version of the studio?

The tool runs 100% in your browser without registration or server-side saving. It allows you to test cut slopes, excavation quantities, and preliminary retaining wall sizing with transparent calculation formulas.

What does the Pro version offer compared to the free online studio?

The Pro version allows you to save your projects to a construction site, load existing files, price bill items using the ACIP price database, collaborate with team members, and export unwatermarked calculation sheets.