What is swelling and why it changes the number of trucks
On an earthmoving construction site, compacted soil never keeps its initial volume once extracted by the excavator. As soon as the bucket breaks up the natural ground, air gaps intersperse between solid particles or rock blocks. This mechanical phenomenon corresponds to swelling. The volume measured in the evacuation skip is therefore systematically greater than the initial volume measured in place in the excavation.
For the site manager and the surveyor, ignoring this behavior leads directly to underestimating evacuation logistics. If you plan your transports based on hole dimensions without applying the appropriate coefficient, the number of vehicles booked will be insufficient. The construction site then suffers from pacing delays or machine standstill costs on a time-and-materials basis.
The studio addresses this physical reality right from the initial measurement. By distinguishing theoretical geometric volume, actual excavated volume and loaded bulked volume, the tool makes it possible to anticipate the actual evacuation capacities required. This technical distinction serves as the basis for clear exchanges between the trade master, the engineer and the carrier, avoiding disputes when settling disposal slips.
Gravel, moraine, molasse, silt, rock: six terrains, six starting coefficients
The geological nature determines the amplitude of volumetric expansion. The studio integrates six typical Swiss terrains with modifiable, non-official starting values from the specifications:
- Plateau sandy gravel: permeable granular material showing moderate reorganization during extraction.
- Compact moraine: dense mixture of clay, silts and glacial blocks, very hard in place but releasing volume under the bucket tooth.
- Weathered or marly molasse: sedimentary terrain sensitive to water inflows, losing its initial cohesion as soon as earthmoving starts.
- Sound sandstone molasse or compact limestone: massive rock requiring ripping, whose fractionation into blocks generates significant interstitial voids.
- Clayey silt or soft lacustre deposit: fine and loose soil, often waterlogged, whose handling strongly modifies consistency.
- Heterogeneous old urban fill: reworked terrain comprising various components and mineral debris.
These starting data are indicative. Each terrain presents local singularities. Only a site-specific geotechnical report can confirm the actual values of friction angle, unit weight, cohesion and swelling to introduce into your stability and evacuation calculations.
From volume in place to transported volume: the studio formula
To obtain a realistic estimate, the excavation calculation cannot be reduced to a simplistic parallelepiped. The Fouilles studio uses the rigorous geometric formula of the prismatoid integrating three horizontal sections: the bottom of the excavation, the mid-height section and the crest surface. This calculation takes into account the footprint of the construction, the working width reserved at the foot of the slope, the inclination of the walls on all four sides and the possible presence of a berm.
Initial topsoil stripping is also isolated from general earthmoving, as these earths must be stored separately on the site for subsequent valorization. Once the cubic volume in place is calculated with its actual slopes, the studio applies the swell factor specific to the selected soil.
The bulked volume obtained faithfully represents the space occupied by the excavation spoils in transport skips. This transparency in visible formulas makes it possible to compare gross geometric volume, extracted volume and transported volume, without masking the calculation assumptions applied to the measurement.
Truck payload and rotations: reading the comparison
The number of rotations required depends on both the bulked volume and the total weight of the evacuated spoils. A road truck is limited by its legal payload. The studio defaults to an eighteen-tonne payload for a four-axle truck, this value remaining entirely modifiable according to the equipment used by your carrier.
In the case of heavy soil like dense moraine or limestone rock, the payload limit in tonnes can be reached before the skip is completely filled by volume. Conversely, for lighter materials, the bulked volume dictates rotation. The studio calculates the total mass evacuated from the volume in place and the unit weight of the selected terrain, which determines the number of trips required.
The comparison tab presents the same simulated excavation simultaneously in the six Swiss geological contexts. You directly visualize the impact of geology on the starting slope gradient, the earthmoving volume generated, the number of truck rotations and the foreseeable disposal pathway.
On-site reuse, backfill and imported gravel
Systematic disposal in dumps represents a major financial and environmental burden. The studio evaluates the volume of peripheral backfill required around completed masonry. Depending on the geotechnical nature of the site, you can choose to reuse extracted materials if they present suitable mechanical characteristics, or to provide imported gravel if the original soil is unsuitable for compaction, such as soft silt or weathered marly molasse.
This approach is part of the principles of the Waste Ordinance (OLED). Earthy and excavation materials must be sorted on the construction site and valorized as much as possible when unpolluted. In addition, the client indicates in their permit application the type, quality, quantity and waste disposal pathways when the quantity will likely exceed two hundred cubic meters or in the presence of hazardous pollutants.
The studio classifies pathways indicatively: topsoil valorization, type A unpolluted materials, type B slightly polluted materials or type E polluted soils. In the presence of suspicious spoils or materials from former industrial sites, laboratory analysis and validation with the competent cantonal service remain essential.
Contractor's responsibility for transported quantities
The results provided by the studio constitute an aid to technical preparation and decision-making. They in no way replace a complete geotechnical reconnaissance, a calculation note signed by a specialized engineer or direct control of site conditions during excavations. The company's responsibility remains complete regarding the execution of works and orders placed with subcontractors.
On a contractual level, according to the project description and rules of art, rigorous monitoring of transport slips and actual weighings at the disposal site makes it possible to adjust initial forecasts. In the event of a geological hazard or modification of reception pathways, the site manager immediately reports discrepancies to establish the necessary addenda with the site management.
To go further in administrative management and detailed costing of your earthmoving operations, you can link your quantities to dedicated tools via Tenders, coordinate your construction sites with our ERP or manage your teams' access on the Portal.
Frequently asked questions
How does the free version of the studio work for calculating swelling?
The free version works entirely in your browser, without registration and without account creation. Nothing is sent or saved on a remote server, and no memory is kept: closing or reloading the tab clears all your entries. You can print a watermarked results sheet or export a CSV file bearing the mention of the free version.
How does the studio check the stability of excavation slopes?
The studio applies the safety rules of the Construction Work Ordinance (OTConst). Beyond 1.50 m in depth, an unbraced wall must be sloped or secured. The studio flags vertical walls without shoring beyond this threshold as blocking and displays an alert when the height exceeds 4 m, a threshold requiring justification signed by an engineer.
Why does the truck payload change the number of rotations?
Even if the skip offers sufficient volume to accommodate bulked earth, the vehicle cannot exceed its legal payload limit. For very dense materials such as rock blocks or wet moraines, capacity in tonnes is reached before the skip fills, which requires increasing the number of truck rotations.
Are the studio's slopes and coefficients official values?
No, the proposed swell factors, unit weights and slope gradients are indicative starting values from the studio's specifications. Art Construction is independent of normative bodies. These parameters must be adjusted according to laboratory tests and data from a geotechnical report carried out for your construction site.
What does the Waste Ordinance provide for the evacuation of excavation earth?
According to the Waste Ordinance (OLED), earthy and excavation materials must be sorted on the construction site and valorized if unpolluted. The client must declare the type, quality, quantity and disposal pathway in their permit application as soon as the volume likely exceeds two hundred cubic meters or in the case of hazardous pollutants.
What is the difference between the free measurement and the Pro version?
The free version provides a detailed measurement with visible formulas, without unit prices or ACIP codes. The Pro version allows you to automatically price your items thanks to the server-processed ACIP price list, save your studies by construction site in the cloud, work in teams and export reports without a watermark.
When is it necessary to involve an engineer for an excavation or a wall?
Justification of slope safety signed by a specialized engineer or geotechnical engineer is required beyond 4 m of slope height, in case of water inflows or additional loads at the top of the excavation. For a definitive retaining structure, a calculation note according to SIA 267 standard is required.