Earth Pressure with Upstream Slope and Road Surcharge: Rankine and Coulomb

Earth pressure calculation using Rankine and Coulomb with upstream slopes and road surcharges. Free pre-sizing studio without registration.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

From Characteristic Friction Angle to Design Value

On a construction site in Western Switzerland, estimating the forces exerted by the ground starts with the mechanical properties of the soil. To evaluate active earth pressure, two parameters play a central role: the unit weight and the internal friction angle. The SIA 260 and SIA 267 standards introduce a clear distinction between characteristic values, derived from tests or geotechnical data, and design values introduced into equilibrium equations.

Within the studio, six typical Swiss soil types are offered with editable starting values: sandy gravel from the Plateau, compacted moraine, weathered or marly molasse, sound sandstone molasse or compact limestone, clayey silt or soft lacustrine deposit, and heterogeneous old urban fill. These quantities remain indicative and come from the tool's specifications. They do not constitute official values under any circumstances. Only a site-specific geotechnical report allows establishing the actual ground quantities.

The transition to design values occurs by applying partial safety factors to the soil properties, in accordance with the principles of the SIA 267 standard. The effective friction angle is thus reduced to determine the mobilisable resistance. For calculating the active pressure exerted on an L-shaped retaining wall, the studio sets a forced cohesion of zero on the upstream side. This conservative assumption avoids underestimating the pressure over time, as cohesion may degrade under the action of water infiltration or seasonal cycles.

Inclined Rankine and Fictitious Vertical Plane: Horizontal and Vertical Pressure

For a reinforced concrete L-shaped wall, Rankine's method is commonly applied by considering a fictitious vertical plane that rises from the rear end of the footing heel to the ground surface. This approach makes it possible to treat the soil mass located directly above the heel as an integral part of the structure for global stability checks.

When the upstream terrain features an inclined slope, for example an upstream slope inclined at 18 degrees, the direction of the earth pressure changes. According to Rankine's theory, the stresses acting on the fictitious vertical plane remain parallel to the slope of the natural upstream terrain. The active pressure coefficient Ka increases with the slope inclination.

This overall inclined pressure is then broken down into two action components:

  • A horizontal component, which stresses the structure towards overturning downstream and generates a sliding force at the base of the footing.
  • A downward vertical component, which loads the wall heel and contributes favourably to the stabilising weight of the assembly against overturning.

The studio compares the forces on this fictitious vertical plane. In the studio's equilibrium calculations, the passive resistance of the downstream terrain is ignored, with the exception of half of that developed on any anchor key. Similarly, the weight of the soil located on the front toe is not taken into account for stabilisation.

Coulomb in Comparison: Soil-Concrete Friction

Coulomb's theory approaches active pressure by considering the limit equilibrium of a triangular failure wedge sliding along a slip plane in the soil. Unlike Rankine's approach, Coulomb's formulation makes it possible to consider the effective friction angle between the rear facing of the structure and the backfill soil.

On the studio dashboard, the active pressure coefficient obtained by Coulomb's method is displayed alongside the one calculated by Rankine. This comparative presentation highlights the influence of wall roughness. When soil-concrete friction is mobilised along an inclined or rough facing, the resultant pressure tilts relative to the normal to the wall, which tends to reduce the value of the horizontal pressure compared to a perfectly smooth wall assumption.

However, on an L-shaped retaining wall, analysis on the fictitious vertical plane according to Rankine remains the preferred usage, because friction is exerted between soil masses and not directly against a concrete facing. The studio presents the comparison of these coefficients to allow the site manager or quantity surveyor to visualise the differences in intensity according to the assumptions retained for the active pressure model.

Garden, Parking, or Road Surcharge: The Effect on the Wall

Live loads located upstream of the wall increase lateral pressures on the screen. A uniformly distributed surface surcharge, whether it is a garden landscaping project, a parking area, or a heavy traffic roadway, results in an additional constant horizontal stress over the entire height of the wall.

In the studio, the entered surcharge yields an additional constant active lateral pressure over the height of the fictitious vertical plane. This pressure adds directly to that resulting from the dead weight of the soil. The impact is immediate on the structural stability criteria:

  • Increase in the overturning moment at the base of the stem and under the footing.
  • Increase in the shear force tending to make the structure slide on its foundation soil.
  • Displacement of the resultant forces towards the downstream edge of the foundation footing.

The studio checks load eccentricity according to Meyerhof's distribution and ensures that the resultant lies within the middle third of the footing at the serviceability limit state (SLS). For the dimensioning of the reinforced concrete structure (C30/37 concrete and B500B steel), the fixed-end moment at the base of the stem determines the calculated steel section against the minimum required section. For each check, the studio compares the stress ratio to 100% of the design value and indicates whether the obtained value is lower than or equal to, or higher than the limit.

What Changes When the Slope Approaches the Friction Angle

When the inclination of the upstream slope approaches the internal friction angle of the soil, the equilibrium conditions change profoundly. In the trigonometric equations of Rankine and Coulomb, the term under the radical tends towards zero, which causes a steep rise in the Ka coefficient.

Mechanically, the pressure prism widens considerably at the crest. The volume of soil mobilised upstream becomes much larger, strongly increasing the horizontal forces applied to the structure. If the slope gradient exceeds the internal friction angle, the natural mass no longer exhibits intrinsic stability without specific retention or geotechnical reinforcement.

In this configuration, sliding and overturning checks become predominant. The tool incorporates an automatic optimisation algorithm that searches for the footing geometry that uses the least concrete while keeping all stress ratios under 95%. But on site, an overly steep upstream slope often requires a significant widening of the heel or the addition of an anchor key underneath the footing to take up the horizontal force at the base without excessive sliding.

Contractor Responsibility and Engineer's Note

Using digital tools to estimate earth pressure never relieves the company of its control and monitoring obligations on the construction site. The Art Construction studio operates as a technical pre-sizing tool within the web browser. It helps prepare earthworks, reinforcement takeoffs, and assess the sensitivity of a retaining structure to surcharges.

The Construction Work Ordinance sets precise requirements for excavations: beyond 1.50 m in depth, a wall that is neither shored nor sheeted must be sloped or secured by other measures. The slope must be adapted to the strength of the soil, with supplementary measures if rain, thawing, loads, or tremors compromise it. In addition, the ordinance requires proof of slope safety signed by a specialised engineer or geotechnical expert, particularly beyond 4 m of slope height, in the event of additional loads or water inflows. The SIA 118 standard also governs contractual relations and the contractor's duties of care.

The studio's calculations remain limited to simplified assumptions: homogeneous soil, groundwater table managed by perfect drainage, and checks restricted to simple bending without checking for shear force, cracking, or anchorage lengths. A site geotechnical investigation and a calculation note signed by a civil engineer in accordance with the SIA 267 standard are mandatory before any final execution. To link these quantities to your company quotes, you can explore the Tenders modules, global management via the ERP, or team tracking on the Portal.

Frequently asked questions

How does the studio handle the presence of water behind the wall?

The studio's comparison shows the wall with or without a drainage system. Without a functional drain, the total hydrostatic water pressure adds to the earth pressure forces. This doubles or triples the overturning moment. The studio does not model uplift pressure or soil buoyancy without drainage.

Are my retaining wall calculation data stored online?

In this free version, the tool runs entirely within your web browser. No files or parameters are transmitted to a server or saved in local memory. Closing or refreshing your browser tab clears your entire ongoing study.

What is the safety rule for excavation slopes according to the Construction Work Ordinance?

According to the text of the Construction Work Ordinance, any excavation wall deeper than 1.50 m that is neither shored nor sheeted must be sloped or secured by other measures. A certificate signed by a specialised engineer or geotechnical expert is required in particular beyond 4 m in height, in the event of water inflows or additional loads.

What technical difference does the studio make between Rankine and Coulomb?

The main calculation of the L-shaped wall relies on Rankine's theory applied to a fictitious vertical plane passing behind the heel. The studio also calculates Coulomb's coefficient for comparison, to show the impact of accounting for direct friction between the soil and the concrete facing.

How are road traffic surcharges managed?

A uniform surcharge at the top of the wall, caused by a roadway or a parking lot, is converted into a constant lateral stress applied over the entire height of the fictitious facing. This pressure increases bending moments as well as sliding and overturning stresses on the footing.

What are the limitations of the proposed reinforcement calculation?

The reinforcement sizing provided by the tool considers solely the simple bending of the reinforced concrete stem and footing. Shear force, crack width control, distribution reinforcement, and bar anchorage lengths are not handled by the studio.

What features does the Pro version offer compared to the free studio?

The Pro version allows you to save and classify your construction sites on the cloud, export complete calculation reports without watermarks, directly cost quantities with the cantonal price database on a server, and collaborate with multiple users on technical files.