The fire brigade must be able to set up an aerial ladder at the foot of the façades and connect its hoses to the hydrants in the street, including while work is under way. On a building site these areas fill up quickly: deliveries, skips, storage, scaffold feet. The page on the fire brigade access road covers the width, the clear height and the bends of the road; this one focuses on the ladder area and the fire hydrants, and on keeping them clear phase after phase.
In the Crane and scaffolding studio, the aerial ladder area is a starting rectangle of 11 × 4.5 m and each fire hydrant a 3 m diameter disc to keep clear. The objects are placed on the map or the imported plan, moved and copied from one phase to the next. These dimensions are starting values of the studio: the applicable requirements come from the local fire brigade and the fire protection authority, which often rely on the guideline of the Swiss Fire Brigade Coordination (CSSP) on access roads and support areas.
Worked example: a three-phase site with one ladder area and two hydrants
Four-storey building along a street, site in three phases (excavation, structural work, façades). An aerial ladder area is required in front of the main façade, and two fire hydrants stand at the edge of the plot. Starting dimensions of the studio: area 11 × 4.5 m, clear zone of 3 m diameter around each hydrant, 10 m³ skip of 4 × 2 m.
| Element | Dimensions | Area | Phase at risk |
|---|---|---|---|
| Aerial ladder area | 11.0 × 4.5 m | 49.50 m² | façades: scaffold feet |
| Fire hydrant 1 | 3.0 m disc | 7.07 m² | structural work: reinforcement storage |
| Fire hydrant 2 | 3.0 m disc | 7.07 m² | excavation: fence |
| Total to keep clear | area + 2 hydrants | 63.64 m² | all phases |
| Planned 10 m³ skip | 4.0 × 2.0 m | 8.00 m² | to be moved out of the area |
The ladder area covers 11 × 4.5 = 49.50 m². Each hydrant zone is π × 1.5² = 7.07 m², or 14.14 m² for both. So 49.50 + 14.14 = 63.64 m² must stay clear at every phase. The 10 m³ skip planned in front of the entrance cuts into the ladder area: its 8 m² must go somewhere else, for example along the fence on the courtyard side.
The façade phase is the trickiest: the scaffolding must leave the ladder area accessible or be designed together with the fire brigade (a zone without scaffolding, access from another side). By copying the phase in the studio and moving the objects, you check visually at each stage that neither the skip, nor storage, nor scaffold feet encroach on the 63.64 m².
On this site, 63.64 m² must stay clear at every phase: the skip planned on the ladder area is moved, and the façade phase is settled with the fire brigade.
3 common mistakes around the ladder area and the hydrants
Checking only one phase
A plan approved for the excavation says nothing about the façade phase. Scaffolding, material stores and skips change from one phase to the next: check each phase.
Hiding the hydrant behind the fence
A site fence set on the plot boundary can shut a fire hydrant in. The hydrant must stay visible and accessible from the public road.
Using the starting dimensions without confirming them
The 11 × 4.5 m and the 3 m diameter are starting values of the studio. The local fire brigade or the fire protection authority sets the dimensions and the bearing capacity required.
How to use it in 3 steps
- Place the area and the hydrants
On the map or the imported plan, place the aerial ladder area in front of the façade concerned and a fire hydrant on each existing hydrant. - Copy the phases
For each phase of the site, move skips, storage, fences and scaffolding and check that no object encroaches on the areas to keep clear. - Export for the meeting
Export each phase as PNG or PDF and add it to the site file for the discussion with the fire brigade.
What the free version does not do
The studio checks neither the bearing capacity of the ground under the ladder area, nor the position required by the fire brigade, nor the flow of the hydrants. It draws starting areas and helps to spot conflicts on the plan. The applicable requirements come from the fire brigade and the fire protection authority; this plan replaces neither their opinion nor the site safety concept.
With Soumissions, the quantities of the site layout plan (fences, skips, scaffolding) go into the items of your tender, with the price database and one file per site.
Frequently asked questions
How large should an aerial ladder area be?
The studio offers a starting rectangle of 11 × 4.5 m. The dimensions, gradient and bearing capacity required are confirmed with the local fire brigade or the fire protection authority.
Must a zone around fire hydrants be kept clear?
Yes, the studio reserves a 3 m diameter disc around each hydrant, to keep free and accessible. The exact value is confirmed locally.
Does the studio check the fire brigade access road?
Yes, with the fire access road object: width, clear height, gradient and bends. The page on the access road explains these checks.
What if the scaffolding occupies the ladder area?
You need a solution agreed with the fire brigade: area moved, access from another façade or compensating measures. The exported plan supports this discussion.