Crane supports: outrigger reaction, ground bearing pressure and spreader plate

A crane stands on four supports: if the ground gives way under a single outrigger, the whole machine tips over. Here is how to read the reaction of an outrigger and choose the plate that spreads it.

Open the free studio →

Free, no account: an indicative preliminary design, which does not replace the calculation note signed by an engineer.

On a tight site, the self-erecting crane is often set on an asphalt yard, recent fill or a strip of soil at the edge of the excavation. The site manager then has a simple question to answer: can the ground take the load from each outrigger, and which spreader plate goes underneath? The manufacturer's data sheet gives the exact reactions; before it is available, an order of magnitude is needed to book the plates, plan a compacted sub-base or move the crane. The page on crane radius covers the load chart and oversailing; this one details the supports.

The Crane and scaffolding studio places the crane on the plan and calculates, for the chosen model, the maximum reaction of an outrigger and the minimum square plate. It starts from the crane mass, the outrigger spacing, the overturning moment (estimated from the load at the jib tip and the radius, or entered) and the allowable ground pressure: asphalt or compacted gravel, filled topsoil, or an entered value. This calculation is an indicative preliminary design: it replaces neither the manufacturer's data sheet, nor the calculation note of the crane supplier, nor the opinion of a geotechnical engineer.

Worked example: a 30 m self-erecting crane on asphalt or on filled soil

Small apartment building under construction, self-erecting crane with a 30 m jib chosen from the studio's list. Default values of the studio (indicative, to be replaced by the manufacturer's data sheet): mass 25 t, outrigger spacing 3.90 m, load at the jib tip 800 kg, hook block mass 140 kg. Two possible locations: an asphalt yard (200 kN/m²) or a strip of filled soil (80 kN/m²).

Outrigger reaction and minimum plate by ground type (studio values, indicative)
QuantityFormulaAsphaltFilled soil
Overturning moment ΔM(800 + 140) kg × 30 m × 9.81 / 1000276.64 kN·m276.64 kN·m
Share of self-weight per outrigger25 t × 9.81 / 461.31 kN61.31 kN
Share of moment per outriggerΔM / (3.90 × √2)50.16 kN50.16 kN
Outrigger reaction R1.15 × (61.31 + 50.16)128.19 kN128.19 kN
Minimum plate areaR / σadm0.641 m²1.602 m²
Square plate chosenside rounded up to the next 5 cm0.85 × 0.85 m1.30 × 1.30 m

The overturning moment comes from the load at the jib tip plus the hook block: 940 kg × 30 m × 9.81 / 1000 = 276.64 kN·m. The self-weight is shared over four outriggers: 25 × 9.81 / 4 = 61.31 kN. The moment is carried along the diagonal of the outriggers, of length 3.90 × √2 = 5.515 m: 276.64 / 5.515 = 50.16 kN. The studio then applies a factor of 1.15: 1.15 × 111.47 = 128.19 kN on the most loaded outrigger.

The plate follows from the allowable pressure: on asphalt, 128.19 / 200 = 0.641 m², a square of 0.801 m rounded up to 0.85 m; on filled soil, 128.19 / 80 = 1.602 m², that is 1.266 m rounded up to 1.30 m. The same crane therefore needs plates almost 2.5 times larger on soil: they must be planned when ordering, or a compacted sub-base must be laid.

For this 30 m crane, an outrigger transmits about 128 kN: a 0.85 × 0.85 m plate on asphalt, but 1.30 × 1.30 m on filled soil (indicative values, the manufacturer's data sheet prevails).

3 frequent mistakes with crane supports

Picking the ground pressure at random

A new asphalt yard and soil filled last year do not carry the same load. Entering 200 kN/m² out of habit on uncompacted fill undersizes the plate by a factor of 2.5. When in doubt, a study or a plate load test on site settles it.

Forgetting the edge of the excavation

An outrigger placed near the edge of an excavation adds a load at the crest that reduces the stability of the slope. The crane studio does not calculate this setback: it is checked with the Excavations and slopes studio and the engineer. See the page on excavation slopes and the OTConst rules.

Calculating with the default values

The masses, spacings and loads of the studio's models are default values. A real crane has its own data sheet, sometimes with different counterweights: replace the values before ordering the plates.

Three-step guide

  1. Place the crane on the plan
    Search for the address or import the drawing, place the crane object, choose the model and the jib direction, then replace the default values with the manufacturer's.
  2. Choose the ground under the outriggers
    Select asphalt or compacted gravel, filled topsoil, or enter the allowable pressure given by the study. Enter the overturning moment from the data sheet if you have it.
  3. Read the reaction and the plate
    The properties panel shows the maximum reaction of an outrigger and the minimum square plate. Export the plan as PNG or PDF for the site meeting.

Open the free studio →

What the free version does not do

The studio checks neither the deep bearing capacity of the ground, nor settlement, nor the stability of a nearby slope, nor wind forces on the crane. The 1.15 factor and the proposed ground pressures are default values. This preliminary design replaces neither the crane supplier's calculation note, nor the geotechnical study, nor the note signed by a civil engineer (SIA standards 260 to 267) when a crane foundation has to be built.

The plan and the quantities stay in your browser and disappear when the page is closed. With Soumissions, the crane quantities (erection, hire) go into the items of your tender, with the cost database and a file per site.

Frequently asked questions

How does the studio calculate the reaction of an outrigger?

It adds to a quarter of the crane weight the share of the overturning moment carried along the diagonal of the outriggers, then applies a factor of 1.15. The moment is estimated from the load at the jib tip and the radius, or taken from your entry.

Which allowable ground pressure should be chosen?

The studio offers 200 kN/m² for asphalt or compacted gravel and 80 kN/m² for filled soil. These are default values: the geotechnical study or a plate load test give the value to use.

Can a crane be placed near an excavation?

Only after the slope or the shoring has been checked with the outrigger load. The crane studio does not do this check: use the Excavations and slopes studio and ask the engineer.

Is the calculated plate enough for execution?

No. It is an order of magnitude to prepare the site. The manufacturer's data sheet, the crane supplier's note and, if needed, the engineer set the final supports.