A slab poured with a skip or a pump, a mortar silo for masonry: these installations need precise areas close to the crane and the truck access. Badly placed, they block the street, force the mixer to reverse across the footpath or put the skip out of the crane's reach. The pages on the detached house and on the crane radius show the general layout; this one focuses on the logistics of concrete and mortar.
The Crane and scaffolding studio offers a starting truck mixer bay of 10 × 3.5 m, a dry mortar silo of 2.5 m diameter and a load to lift object whose mass is compared with the load the crane allows at the distance where it stands. You can thus see whether the full concrete skip stays within the load curve between the mixer and the slab. The starting values (dimensions, crane model) are replaced by those of the supplier.
Worked example: a 120 m² slab poured with a skip
Slab of 120 m² and 22 cm thick, poured by crane with a 500 litre skip. Example truck mixer of 8 m³ per trip. Example mass of the full skip: concrete 0.5 m³ × 2,400 kg/m³ plus 150 kg of skip. Starting mixer bay of the studio: 10 × 3.5 m; silo of 2.5 m diameter.
| Quantity | Calculation | Result |
|---|---|---|
| Concrete volume | 120 × 0.22 | 26.4 m³ |
| Trips of an 8 m³ truck mixer | 26.4 / 8 = 3.3 | 4 trips |
| 500 litre skips | 26.4 / 0.5 | 53 lifts |
| Mass of a full skip | 0.5 × 2,400 + 150 | 1,350 kg |
| Truck mixer bay | 10 × 3.5 | 35.0 m² |
| Mortar silo | π × 1.25² | 4.91 m² |
The slab needs 120 × 0.22 = 26.4 m³ of concrete, that is 26.4 / 8 = 3.3 trips rounded up to 4 truck mixers, and 26.4 / 0.5 = 52.8 rounded up to 53 skip lifts. A full skip weighs 0.5 × 2,400 + 150 = 1,350 kg: placed on the plan as a load to lift, it is compared by the studio with the load the crane allows at that radius, on the mixer side as on the slab side.
The mixer bay covers 10 × 3.5 = 35.0 m², the silo π × 1.25² = 4.91 m², not counting the space for manoeuvring and discharging. If the skip leaves the load curve at the far end of the slab, you move the mixer bay closer, use a smaller skip or switch to the pump: the plan shows it before pouring day.
For this slab, 4 truck mixer trips and 53 lifts of a 1,350 kg skip: the 35 m² bay and the skip must stay within the load the crane allows along the whole route.
3 common mistakes for concrete deliveries
Checking the crane only in the middle of the slab
The allowed load decreases with the radius: the full skip may pass in the centre and exceed the load at the furthest corner. Place the load to lift at both ends of the route.
Parking the mixer on the footpath
A mixer that stops outside the planned bay blocks pedestrians and may require an occupation permit. Reserve the bay on the plan and check the truck access.
Leaving the silo out of the plan
A mortar silo delivered at the last minute often ends up on the aerial ladder area or against a fire hydrant. Place it in the site layout plan from the start, with access for the refilling truck.
How to use it in 3 steps
- Place the mixer and the silo
Place the truck mixer bay close to the access and the silo close to the masonry area; adjust their dimensions to those of the supplier. - Enter the skip as a load to lift
Add a load to lift with the mass of the full skip and move it between the mixer and the furthest point of the slab: the studio shows the allowed load at each radius. - Export the pouring plan
Export the pouring phase as PNG or PDF and hand it to the driver, the crane operator and the concrete plant.
What the free version does not do
The studio calculates neither the trip schedule, nor the pouring rate, nor the forces on the fresh slab, nor the stability of the silo in the wind. The crane models and dimensions are starting values to replace with the manufacturer's and supplier's data sheets. This plan replaces neither the crane calculation nor the site safety concept.
With Soumissions, the quantities of the site layout plan go into the items of your tender, with the price database and one file per site.
Frequently asked questions
How much space should be planned for a truck mixer?
The studio offers a starting bay of 10 × 3.5 m, or 35 m², to adapt to the actual truck and to the manoeuvring space.
How can I tell whether the crane lifts the full concrete skip?
Enter the skip as a load to lift with its full mass: the studio compares it with the load the crane allows at the radius where it stands.
How many truck mixers for a slab?
Divide the concrete volume by the capacity of one mixer and round up to the next whole number: 26.4 m³ in 8 m³ mixers gives 4 trips.
Does the studio plan the pour?
No, it places the installations and checks the crane load. The schedule and the pouring rate are agreed with the concrete plant.