The painter, the facade plasterer and the external insulation contractor work with light loads: buckets, bags of render, insulation boards. The load class of the scaffold is chosen according to what will be placed on the platforms, and class 3 generally covers this work. Ordering a heavier class costs equipment and erection time; ordering too light exposes the scaffold to overloading as soon as a pallet of boards is stored on the platform. The page on the bricklayer's scaffold details class 4 and structural work; this one focuses on facade finishing trades.
The Crane and scaffolding studio draws the scaffold perimeter along the facades, offers class 3 (2.0 kN/m²), 4 (3.0 kN/m²) or 5 (4.5 kN/m²) with a default platform width, and calculates the quantities: scaffold area, inside brackets when the gap to the facade exceeds 30 cm, debris netting or sheeting, stair tower. It replaces neither the manufacturer's erection instructions, nor the inspection of the scaffold before use, nor the site safety concept.
Worked example: an 18 m facade repainted then insulated
Facade 18 m long and 7.50 m high, rendered then insulated externally with 200 mm of insulation. Default platform widths of the studio: 0.65 m in class 3, 0.95 m in class 4. Example bay length: 2.50 m (depending on the manufacturer). The platform is set 30 cm from the future insulated surface.
| Quantity | Class 3 | Class 4 | Remark |
|---|---|---|---|
| Distributed load | 2.0 kN/m² | 3.0 kN/m² | common load classes |
| Platform width (default) | 0.65 m | 0.95 m | to be checked with the manufacturer |
| Load per metre of platform | 1.30 kN/m | 2.85 kN/m | load × width |
| Load per 2.50 m bay | 3.25 kN | 7.13 kN | about 330 kg and 725 kg |
| Number of bays over 18 m | 8 | 8 | 18 / 2.50 = 7.2, rounded up |
| Gross facade area | 135 m² | 135 m² | 18 × 7.50, before additions |
In class 3, one metre of a 0.65 m platform carries 2.0 × 0.65 = 1.30 kN, that is 3.25 kN per 2.50 m bay, about 330 kg spread out: buckets, bags and two workers are fine, a full pallet of insulation boards must not be set down on it. Class 4 carries 2.85 kN/m, that is 7.13 kN per bay. The facade has 18 / 2.50 = 7.2 bays, rounded up to 8, and 18 × 7.50 = 135 m² of gross area before the additions covered on the page on scaffold quantities.
Once 200 mm of insulation is fitted, the facade moves closer to the scaffold: the platform cannot be moved in afterwards. If the platform is erected 30 cm from the future insulated surface, the gap between the platform and the masonry is 0.30 + 0.20 = 0.50 m while the boards are being bonded. As soon as the gap exceeds 30 cm, inside brackets are needed to prevent a fall between the platform and the wall: the studio adds them to the quantities.
For this facade, class 3 with a 0.65 m platform is enough for the painter and the insulation (3.25 kN per bay), provided inside brackets are added and no pallets are stored on it.
3 frequent mistakes with class 3 scaffolding
Storing pallets on the platform
A pallet of insulation boards or render bags quickly exceeds the load of a class 3 bay. Deliver in small quantities or plan a storage area on the ground and a higher class if storage on the platform is essential.
Forgetting the thickness of the insulation
Erecting the platform against the bare facade prevents fitting the insulation; erecting it far away without brackets leaves a dangerous gap. The gap must be planned at erection, with the inside brackets needed.
Keeping class 3 for masonry
If the same scaffold is later used to lay bricks or dressed stone, it must move to class 4 or 5. See the page on the bricklayer's scaffold.
Three-step guide
- Draw the scaffold perimeter
On the plan, draw the scaffold along the facades concerned: the studio measures the length. - Set the class and the platform
Open the Scaffolding view, choose class 3, the platform width and the gap to the facade; the studio flags inside brackets beyond 30 cm. - Export the quantities
The quantities tab lists the scaffold area, the brackets, the netting or sheeting and the stair tower. Export it as CSV for your tender or for the hire company.
What the free version does not do
The studio calculates neither the strength of the scaffold components, nor the tie pattern, nor the effect of wind on sheeting (see the page on wind ties). The platform widths are default values to be confirmed in the manufacturer's instructions. The scaffold must be erected according to these instructions and inspected before use; this preliminary design replaces neither the safety concept nor an engineer's note for a special scaffold.
With Soumissions, the scaffold quantities go into the items of your tender, with the cost database and a file per site.
Frequently asked questions
Which scaffold class for repainting a facade?
Class 3 (2.0 kN/m²) generally covers painting, light render and external insulation, without storing pallets on the platform. The manufacturer's instructions and the safety concept confirm the choice.
When are inside brackets needed?
The studio adds them as soon as the gap between the platform and the facade exceeds 30 cm, which often happens with thick external insulation.
Does the studio check the ties?
No. The force per tie and the tie pattern are set by the manufacturer's instructions; the page on wind ties explains this calculation.
Can the scaffold be reused for masonry?
Only if it is class 4 or 5 and erected for that purpose. A class 3 scaffold must not be used to store bricks.