From the Ψ coefficient to kWh lost per year: costing a thermal bridge before and after

A Ψ in W/(m·K) means little to a client; multiplied by the detail length and the degree-days, it becomes an annual loss you can compare from one variant to the next.

Open the free studio →

Free, no account: your walls and your calculations stay in your browser.

To make the case for correcting a thermal bridge to a client, the Ψ value is not enough: it has to be turned into energy lost every year, then compared before and after the works. The calculation is simple, as long as you do not mix up the detail length, the degree-days of the location and the price of an energy that is not the one the building actually buys.

The 2D Thermal Bridges studio shows for each detail the annual loss over the length entered, using the formula Ψe × length × degree-days × 24 / 1000, and an indicative cost at the energy price you enter. The “Before / after” tab compares two variants of the same detail. For the full results sheet of a detail and for the balcony with and without a thermal break, see the linked pages: here, the method is used to add up several details of a façade.

Worked example: three details of a façade before and after renovation

A small block of flats whose façade is being refurbished. Example degree-days: 3 600 K·d, to be replaced by those of your location. Example heat price: 0.15 CHF per kWh. The Ψe values before and after are example values, to be replaced by those the studio calculates for your details. Common factor: 3 600 × 24 / 1000 = 86.4.

Annual loss = Ψe × length × 86.4 (example degree-days 3 600 K·d)
DetailLengthΨe before → after (example)Loss before → after
Blind boxes32.0 m0.30 → 0.10 W/(m·K)829.44 → 276.48 kWh/yr
Reveals and sills41.6 m0.10 → 0.03 W/(m·K)359.42 → 107.83 kWh/yr
Wall base over basement30.0 m0.25 → 0.12 W/(m·K)648.00 → 311.04 kWh/yr
Total of the three details103.6 m–1 836.86 → 695.35 kWh/yr
Annual saving––1 141.51 kWh/yr, i.e. 171.23 CHF/yr

Blind boxes: 0.30 × 32.0 × 86.4 = 829.44 kWh before, 0.10 × 32.0 × 86.4 = 276.48 kWh after. Reveals: 0.10 × 41.6 × 86.4 = 359.42 kWh before, 0.03 × 41.6 × 86.4 = 107.83 kWh after. Wall base: 0.25 × 30.0 × 86.4 = 648.00 kWh before, 0.12 × 30.0 × 86.4 = 311.04 kWh after. Total: 1 836.86 kWh before, 695.35 kWh after, i.e. a saving of 1 141.51 kWh per year.

At the example price of 0.15 CHF per kWh, the loss goes from 275.53 to 104.30 CHF per year, a saving of 171.23 CHF. These are kWh of heat lost: the energy bought depends on the efficiency of the boiler or the coefficient of performance of the heat pump. Divide the heat by this efficiency, or enter in the studio a price for useful heat that takes it into account.

In this example, correcting three details saves about 1 140 kWh of heat per year; the blind box alone accounts for nearly half of the saving.

3 common mistakes when costing a thermal bridge in kWh

Taking the fuel price for the heat price

The studio multiplies the kWh of heat lost by the price entered. If you enter the price of heating oil, gas or electricity without allowing for the efficiency or the coefficient of performance, the cost shown is wrong by that much.

Entering the length of a single window

Ψ applies to the whole length of the detail on the building: the perimeter of all the windows concerned, the façade length of a wall base. One window instead of twenty divides the loss by twenty and distorts the comparison.

Adding Ψe and Ψi from two details

Values on external and internal dimensions do not mix. Choose one convention, the same as for the plain elements in your energy balance, and keep it for every detail, including negative Ψe values, which are subtracted.

How to cost a thermal bridge in kWh in 3 steps

  1. Calculate the current detail
    Choose the template for the detail, set the existing geometry and materials, then enter the length of the detail on the building, the degree-days for your location and the heat price. The studio shows Ψe and the annual loss.
  2. Compare the corrective solution
    In “Before / after”, keep the current state as the reference and apply the correction: box lining, insulation return, insulating block or thermal break. The studio shows the difference in Ψe, kWh and cost.
  3. Add up the details and export
    Repeat the process for each detail of the façade, export each result to CSV and add up the losses in your spreadsheet, as in the table above. The take-off of the corrective solution gives the quantities without prices.

Open the free studio →

What the free version does not do for energy costing

The studio calculates one detail at a time: adding several details is done by hand. The degree-days and temperatures offered are starting values to be checked; the cost is indicative and ignores the heating efficiency unless you build it into the price. It replaces neither an energy balance under SIA 380/1 nor a CECB building energy certificate. Nothing is saved.

With Soumissions, the quantities of the corrective take-off go into the tender items with the price database. The ERP tracks the site and the invoicing, and the Portail chantier keeps the before and after sheets to present them to the client.

Frequently asked questions

How do you get from Ψ to kWh per year?

Multiply Ψ in W/(m·K) by the detail length in metres, by the heating degree-days in K·d and by 24 hours, then divide by 1000 to convert Wh into kWh. This is the formula shown by the studio.

Where can I find the degree-days for my location?

From the energy authorities, the climate data of the standard or your heat supplier. The studio’s starting value is indicative: replace it with the one for your locality.

What does a negative annual loss mean?

A negative Ψe on external dimensions gives a negative loss: it is a correction to losses already counted in the plain elements, to be kept in the balance, not a real energy gain.

Is the saving in kWh enough to justify a correction?

Not on its own. A correction can be justified by the risk of mould, checked with the fRsi factor, even when the energy saving is modest. The studio shows both.