The landscaper, the paving contractor or the civil engineering firm pricing external works relies on the site plan: asphalt driveway, paved parking spaces, terrace, lawn, kerbs, fences. This plan is often at 1:200 and the shapes are rarely rectangular. A reading error of one millimetre represents twenty centimetres on the ground.
The Take-Off & Métré studio opens the PDF site plan in the browser, without sending anything. After calibrating on a known dimension, you draw each surfacing as a polygon area, subtract planting beds and manhole covers, and follow kerbs and fences as cumulative lengths. The adjustable height turns an area into a volume, useful for a sub-base. The table by layer exports to CSV.
Worked example: take-off of the external works of a house from the site plan
A rectangular plot of 31.00 m by 20.00 m, i.e. 620.00 m². The house has a footprint of 112.00 m². The site plan, a PDF at 1:200, is calibrated on the dimensioned length of the plot.
| Work | Measurement | Quantity | Unit |
|---|---|---|---|
| Asphalt driveway | 18.00 m × 3.50 m | 63.00 | m² |
| Paved parking spaces | 5.00 m × 5.00 m | 25.00 | m² |
| Slabbed terrace | 6.00 m × 4.00 m | 24.00 | m² |
| Lawn | 620.00 − 112.00 − 112.00 − 36.00 | 360.00 | m² |
| Kerbs | 36.00 m + 15.00 m | 51.00 | m |
| Fence | 102.00 m − 4.00 m | 98.00 | m |
The three hard surfacings total 63.00 + 25.00 + 24.00, i.e. 112.00 m². The lawn is derived from the plot: 620.00 m² less 112.00 m² of house, 112.00 m² of surfacing and 36.00 m² of planting leaves 360.00 m². The kerbs run along both sides of the driveway (36.00 m) and three sides of the parking spaces (15.00 m): 51.00 m. The perimeter is 2 × (31.00 + 20.00), i.e. 102.00 m; less 4.00 m for the gate, the fence measures 98.00 m.
The adjustable height gives the volume of the sub-base: 63.00 m² of driveway over a thickness of 0.40 m represents 25.20 m³ in place. An allowance of 5% for cutting the pavers is taken here as an assumption, to be confirmed according to the laying pattern and the specification: 25.00 m² × 1.05 gives 26.25 m² to order.
Key figures: 112.00 m² of hard surfacing, 360.00 m² of lawn, 51.00 m of kerbs, 98.00 m of fence and 25.20 m³ of sub-base under the driveway.
3 common mistakes in an external works and paving take-off
Trusting the stated scale of a reduced plan
A site plan at 1:200 that has been scanned or reduced to fit on a page is no longer to scale, and the slightest deviation is multiplied by two hundred. Calibrating on the longest dimensioned length of the plot limits the error.
Measuring sloping ground as if it were flat
The plan gives areas projected onto the horizontal. On a steep driveway or an embankment, the real area is larger. The studio measures in plan: the slope factor is then applied in the spreadsheet.
Confusing surfacing area with earthworks volume
The asphalt area is not enough: the sub-base, the foundation layer and the removal of spoil are counted in cubic metres, with a bulking factor to be stated. Separate layers for areas, volumes and kerbs help you not to forget an item.
How to take off quantities from a PDF site plan in 3 steps
- Open the site plan and calibrate
Drop the PDF into the studio and calibrate on the longest known dimension, for example one side of the plot. For a scanned plan, use the separate X and Y calibration. Create one layer per type of work: asphalt, paving, lawn, kerbs, fence. - Draw the areas and follow the lengths
Draw each surfacing as a polygon area, following curves in short segments, and subtract planting beds and manhole covers. Follow the kerbs and the fence as polylines, then enter a height on the areas whose volume you want. - Check consistency and export
Check that the sum of the house, the surfacings, the planting and the lawn matches the area of the plot. Export the table to CSV to add your cutting and bulking allowances.
What the free version of the external works take-off does not do
Outlines are drawn by hand, with no recognition of plot boundaries or surfacings. The studio measures in plan: it does not read levels and calculates neither slopes nor volumes between two profiles. Export is limited to CSV with the Art Construction notice, and everything is erased when the tab is closed.
Soumissions takes the quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) keeps layers and measurements, allows teamwork and exports without a watermark.
Frequently asked questions
How do you measure an asphalt or paved area with curved edges?
Draw the polygon area by placing points close together along the curve: the closer they are, the nearer the area comes to the real shape.
Does the studio calculate the volume of earthworks or sub-base?
It calculates a simple volume: area multiplied by the height you enter, for example the thickness of the sub-base. It does not handle cross-sections. Bulking is added in your spreadsheet, as a stated assumption.
What allowance should be planned for cutting pavers or slabs?
It depends on the format, the laying pattern and the shape: diagonal laying or curved edges call for more cuts. The example takes 5% as an assumption; rely on your comparable jobs and on the specification.
Can an extract from the cadastral plan be used?
Yes, if it is a PDF and a known length allows it to be calibrated. It is used to check the area of the plot; the planned surfacings are measured on the landscaping plan.