In an interior renovation, the demolition item is poorly priced when it rests on an impression from a site visit. The contractor needs quantities: partitions to knock down, screeds and tiling to break out, suspended ceilings to take down, doors and appliances to remove. On alteration drawings, the elements to be demolished are customarily shown in yellow.
The Take-Off & Métré studio opens these PDF plans in the browser, without uploading the file. After calibrating the scale, you follow the yellow partitions as cumulative lengths, draw the floors and ceilings as polygon areas and count doors or appliances with markers. The adjustable height gives wall areas and volumes, grouped on a CFC 112 layer and exportable to CSV.
Worked example: demolition and strip-out take-off for a flat to be renovated
A four-room flat in a 1970s building, to be fully renovated. Alteration drawing as a PDF at 1:50, ceiling height 2.50 m. The thicknesses come from trial openings made during the visit.
| Element to remove | Measurement | Area (m²) | In-place volume (m³) |
|---|---|---|---|
| Brick partitions, 10 cm | 14.20 m × 2.50 m − 3.20 m² | 32.30 | 3.23 |
| Screed and tiling, 7 cm | Floor areas drawn | 42.00 | 2.94 |
| Plaster suspended ceiling, 2 cm | Ceiling areas drawn | 28.00 | 0.56 |
| Wall tiles and adhesive, 1.5 cm | 8.00 m × 2.50 m | 20.00 | 0.30 |
| Total in place | 7.03 |
The yellow partitions measure 14.20 m; over a height of 2.50 m, that makes 35.50 m², from which two doors of 0.80 m by 2.00 m are taken off, i.e. 3.20 m²: 32.30 m² remain, and 3.23 m³ for a thickness of 10 cm. The screed and its tiling represent 42.00 m² × 0.07 m, i.e. 2.94 m³; the suspended ceiling 28.00 m² × 0.02 m, i.e. 0.56 m³; the wall tiles 20.00 m² × 0.015 m, i.e. 0.30 m³. The in-place volume comes to 7.03 m³.
With a bulking factor of 1.5, taken here as an assumption to be adapted to the materials, 7.03 m³ becomes about 10.55 m³. With 7 m³ skips, two loads should be planned. The permitted weight per skip and the sorting of materials may change that number.
Key figures: 7.03 m³ in place, about 10.55 m³ bulked with a factor of 1.5 taken as an assumption, i.e. two 7 m³ skips.
3 common mistakes in a demolition and strip-out take-off
Pricing the in-place volume without bulking
A partition of 3 m³ does not fit into 3 m³ of skip. Forgetting bulking leads to underestimating the skip loads and the handling. The factor is stated in the quote as an assumption, together with the in-place volume.
Taking thicknesses from the plan rather than on site
The plan rarely shows the real build-up of an old floor. Two extra centimetres over 42 m² add nearly one cubic metre. Thicknesses are checked by trial openings, or noted as a reservation.
Lumping all materials into a single item
Bricks, plaster, timber and metal do not follow the same disposal route. One layer or one category per material gives separate quantities for estimating the sorting, and reminds you to deal separately with materials that may contain pollutants.
How to measure a demolition job on a PDF plan in 3 steps
- Open the alteration drawing and calibrate
Drop the PDF into the studio and calibrate the scale on a known dimension, for example the length of a room. Create a CFC 112 layer and, for sorting, one layer per material. Set the height to the ceiling height. - Follow the elements in yellow and draw the areas
Follow the partitions to be demolished as cumulative lengths: with the height, the studio calculates the wall area. Draw the floors and ceilings to be removed as polygon areas, then count the doors, radiators or sanitary appliances with markers. - Convert to volumes and export
Export the table to CSV, multiply each area by its thickness in your spreadsheet to obtain the in-place volume, then apply your bulking factor and estimate the number of skips.
What the free version of the demolition take-off does not do
The studio does not detect the elements in yellow: you follow them by hand. It knows neither the real thicknesses nor the materials, applies no bulking and calculates neither weights nor the number of skips. Export is in CSV with the Art Construction notice; the session disappears when the tab is closed.
Soumissions takes the quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) saves layers and measurements, allows teamwork and exports without a watermark.
Frequently asked questions
What bulking factor should be used for demolition rubble?
It depends on the material and on how the skip is loaded: masonry bulks less than a mix of plaster, timber and coverings. The example takes 1.5 as an assumption. Use the value observed on your own jobs and write it into the quote.
How do you measure the elements to be demolished when the plan has no colour code?
Ask the architect for the alteration drawing. Failing that, draw on a dedicated layer the existing walls that are absent from the project and have this take-off approved before pricing.
Does the studio measure the volume of a partition from the plan?
It calculates the wall area from the length drawn and the height. The volume is obtained by multiplying that area by the thickness, measured on site or dimensioned on the plan.
Does the take-off allow for asbestos and other pollutants?
No. The studio measures quantities. In an old building, ask for the survey report before submitting a price and include a reservation in the quote: a contaminated material changes the method and the disposal.