For a facade contractor or a plasterer-painter, a quote for rendered external wall insulation hinges on a few figures: the net area of each facade, the length of the plinths, the developed length of reveals and lintels. These quantities are read off the elevations, and the documents usually arrive as PDFs.
The Take-Off & Métré studio opens these elevations in the browser, without sending anything. You calibrate the scale on a known dimension, draw each facade as a polygon area and subtract the openings with an adjustable deduction rule. Cumulative lengths give the plinths and reveals, one layer per CFC code keeps the works apart, and the summary table exports to CSV.
Worked example: facade take-off for a two-storey house with rendered external insulation
A two-storey house in French-speaking Switzerland, rectangular plan of 12.00 m by 9.00 m, facade height 6.20 m. Four elevations as PDFs at 1:100. The openings are deducted in full in this example; the rule to apply remains to be confirmed against the specification and measurement practice.
| Facade | Gross area (m²) | Openings (m²) | Net area (m²) |
|---|---|---|---|
| South, 12.00 m × 6.20 m | 74.40 | 18.60 | 55.80 |
| North, 12.00 m × 6.20 m | 74.40 | 6.40 | 68.00 |
| East, 9.00 m × 6.20 m | 55.80 | 9.20 | 46.60 |
| West, 9.00 m × 6.20 m | 55.80 | 7.80 | 48.00 |
| Total for the four facades | 260.40 | 42.00 | 218.40 |
Each facade is drawn as a rectangle, then its openings are subtracted: 74.40 m² less 18.60 m² gives 55.80 m² on the south side. The net envelope comes to 218.40 m² for 260.40 m² of gross area. The plinth is measured as a length: the perimeter of 42.00 m, less 2.00 m of doors, leaves 40.00 m; over a height of 0.50 m, that makes 20.00 m². The main facade area is therefore 218.40 m² less 20.00 m², i.e. 198.40 m².
The reveals and lintels of the fourteen openings are measured as a cumulative length: 86.00 m of developed length. With a depth of 0.20 m read from the section, that gives 17.20 m² of returns to insulate and render. These three quantities become three separate items in the quote.
Key figures: 198.40 m² of main facade, 20.00 m² of plinth and 86.00 m of reveals (17.20 m²), for a gross area of 260.40 m².
3 common mistakes in a facade and external insulation take-off
Measuring the facade on the floor plan
The floor plan gives lengths, not heights. A gable, a set-back attic storey or sloping ground changes the area by several square metres. The take-off is done on the elevations, with the height checked on the section.
Forgetting reveals, lintels and plinths
The net area says nothing about the returns in the reveals or about the plinth, which is often treated with a different material. These works need more cutting than the main facade: measure them as lengths on a separate layer.
Trusting the scale printed on a reduced PDF
An elevation at 1:100 that has been reduced to fit on a page is no longer at that scale. An error of 3% on lengths produces a difference of about 6% on areas. Calibrating on a known dimension corrects this.
How to measure a facade on a PDF elevation in 3 steps
- Open the elevations and calibrate the scale
Drop the PDF into the studio and display the first elevation. Calibrate on a known dimension; for a scanned plan, the separate X and Y calibration compensates for the distortion. Repeat on each page. - Draw the facades and subtract the openings
Create one layer per CFC code, draw each facade as a polygon area, then draw the windows and doors to be subtracted. Choose the deduction rule: none, all, or above a threshold. Then measure plinths and reveals as cumulative lengths. - Check the table and export to CSV
The summary table groups the measurements by layer and shows the formula for each line. Compare the gross area with a quick length times height calculation, then export to CSV to prepare the items of your quote.
What the free version of the facade take-off does not do
Measurements are made by hand: the studio recognises neither windows nor facades. It measures the elevation as drawn; a skewed or curved facade is measured on its developed view. Accuracy depends on the PDF and on the calibration. Export is limited to CSV, with the Art Construction notice, and the session disappears when the tab is closed.
Soumissions takes the quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) keeps layers and measurements, allows teamwork and produces exports without a watermark.
Frequently asked questions
Should all openings be deducted in a render or external insulation take-off?
It depends on the specification and on measurement practice: some rules only deduct openings above a given area, to offset the work on the returns. The studio offers three settings; state in the quote which one you have used.
How do you measure a gable or a facade under a pitched roof?
Draw the real outline of the gable point by point on the elevation: the triangle under the roof is then included in the area. Check the ridge height on the section.
Can window reveals be measured on the PDF elevation?
Yes, as a length: follow both sides and the lintel of each opening. The depth cannot be read on the elevation; take it from the section, then multiply in your spreadsheet.
Are my elevations sent to a server?
No. The PDF is read in your browser's memory. The trade-off is that closing the page erases the work: export the table to CSV before you leave.