Contractor lead times: what official Swiss data reveal

Construction order backlog reach and typical activity seasonality, based on KOF and the Federal Statistical Office. No lead times by trade or canton: no official data exists.

Free · no sign-up for the first 2 tries

Your project

  • 100 % server-side calculation: no reference price is ever sent to your browser.
  • Indicative results: they guide you, but do not replace a professional’s quote.

How long must you wait before a contractor starts your construction site? No official public statistics answer this question by trade or by canton, and this guide does not invent any. It presents the two official data series shedding light on the topic, their limitations, and the method to secure a firm date.

What official statistics say, and what they do not say

When a company announces it can start in three months, no public statistics allow you to know whether this is long or short for its trade or for your canton. As of November 21, 2026, we have found no official publication providing a waiting time by trade, by canton, or by major region. Existing surveys measure something other than the waiting time of a private individual.

Yet two public series shed light on the topic:

  • The order book reach recorded by KOF, the Swiss Economic Institute at ETH Zurich, among construction companies.
  • Quarterly construction activity published by the Federal Statistical Office (FSO), showing the sector's usual seasonality.

This guide presents them with their source, their time period, and their limitations. The barometer on this website displays nothing else: it does not estimate any lead time in weeks.

Order book reach: 5.6 months across Switzerland

Every quarter, KOF asks a panel of building construction, civil engineering, and specialised construction activities companies (more than one thousand in 2018) in its business tendency survey how many months of work their already signed orders secure for them, excluding seasonal variations. The latest published figure, for the 3rd quarter of 2026, indicates 5.6 months. One year earlier, the value was 6 months; the long-term average cited by KOF in 2024 is 5.2 months.

This figure has limitations that must be understood:

  • it applies to all of Switzerland, without any breakdown by canton, by major region, or by trade;
  • it blends large structural work companies and small craftspeople;
  • it describes work already ordered from companies, not the waiting time a private individual faces for their construction site.

In practice, an order backlog of 5.6 months means that on average companies have work secured for that duration: a company with a shorter order book has greater availability, while a company with a longer order book has less. This figure therefore serves as a market benchmark, never as a date promise. KOF cites this figure in the Baublatt magazine without a regular schedule: not all editions feature it.

Seasonality in building construction: activity varies sharply from quarter to quarter

The FSO publishes the construction turnover index each quarter, adjusted for working days, with and without seasonal adjustment. The ratio between the two highlights the usual seasonal pattern. Over the ten full years from 2016 to 2025, with an index base of 100 for an average quarter, invoiced activity for the construction sector as a whole stands at 82 in the 1st quarter, 102 in the 2nd, 103 in the 3rd, and 113 in the 4th.

Three findings emerge:

  • the low point falls in the 1st quarter across the three tracked groups of branches;
  • for specialised construction activities (electrical, plumbing, heating, insulation, plastering, painting, roofing), the index rises from 81 in the 1st quarter to 117 in the 4th;
  • for building construction, the peak occurs in the 2nd quarter (109) and the low point in the 1st (84).

These values are ten-year averages: any given year may deviate by a few points. They describe what companies invoice, not the waiting time for a client. Bad weather can disrupt outdoor construction sites in winter, but these numbers do not measure that.

Why there are no official lead times by trade or by canton

Official statistics group companies according to their primary activity and publish findings for the country as a whole. The FSO distinguishes building construction, civil engineering, and specialised construction activities; for this series, it publishes neither results by trade nor results by canton. A masonry firm may thus appear under building construction or under specialised construction activities, depending on its primary activity.

The barometer on this website reflects this reality. It lets you choose between total construction, building construction, and specialised construction activities, as these are the only distinctions permitted by official figures. It displays no lead time by trade or by canton, and no homemade estimate replaces them.

If you are looking for a date, the most reliable source remains a written quote from a company: it alone knows its actual order book.

Securing a firm date: the schedule to follow

Because no official figure replaces a direct response from companies, the safest approach is to compare written quotes. Here is the process to follow:

  1. Permits first: check with the building permit quiz whether an administrative procedure is required before starting, as it can delay the date.
  2. Budget and specification: calculate your envelope with the renovation budget simulator, then draft a single specification for all companies.
  3. Three written quotes: send this specification to at least three companies through a comparable call for tenders and request, in each quote, the proposed start date and the project duration.
  4. Custom materials: for windows, kitchens, or roof trusses, also ask for fabrication and delivery times.
  5. Sequence of trades: book them in the order of the construction site, as a delayed contractor pushes back all subsequent ones.

If your target quarter is usually very busy for that branch, request quotes earlier. If it is the quietest, it may be a favourable time to request dates, though only a written quote can confirm it.

Setting dates in the work contract

The work contract is governed by Art. 363 et seq. of the Swiss Code of Obligations (CO), which define the completion of a work for an agreed price between the client (building owner) and the contractor. In the contract, specify the start date of the construction site and the completion date, and clarify whether they are firm or purely indicative. The parties can also agree in writing on a penalty or delay clause.

Standard SIA 118 only applies if the parties have integrated it into the contract; it then provides rules regarding deadlines and the acceptance of works. Before signing, have the date and delivery terms reviewed with the quote scanner.

If a company promises to start structural work or a major renovation immediately, that warrants verification: request its order backlog, references, and insurance certificates, and do not pay a large advance payment before signing. You can then select your service providers in our Tenders section. These benchmarks are indicative; this guide does not constitute individual legal, tax, or technical advice.

What official sources measure (record of November 21, 2026)
Data pointWhat it measuresGeographical level
Order book reach (KOF)Months of work already ordered, reported by companies, seasonally adjustedSwitzerland, all trades combined
Total construction activity (FSO)Turnover by quarter: low in the 1st quarter, peak in the 4thSwitzerland
Building construction activity (FSO)Turnover by quarter: low in the 1st quarter, peak in the 2ndSwitzerland
Specialised construction activities (FSO)Turnover by quarter: low in the 1st quarter, peak in the 4thSwitzerland
Lead time by tradeNo official public statistics foundNone
Lead time by canton or major regionNo official public statistics foundNone

Frequently asked questions

Is there an official lead time by trade or by canton?

No. As of November 21, 2026, we have found no official public statistics showing the waiting time of a contractor by trade, by canton, or by major region. Available data cover Switzerland as a whole. To know a date, compare at least three written quotes.

What does an order book reach of 5.6 months mean?

According to KOF, construction companies have on average orders for 5.6 months of work in the 3rd quarter of 2026. This is a market benchmark for Switzerland across all trades combined. It is not the waiting time a private individual faces for their own construction site.

Which quarter is the quietest for construction?

Over the ten years from 2016 to 2025, invoiced construction activity was lowest in the 1st quarter across the three branch groups tracked by the FSO. It was highest in the 4th quarter, except for building construction where the peak fell in the 2nd. These numbers describe activity, not waiting times.

Is the lead time stated in a quote guaranteed?

No. To be binding on the contractor, the contract must state that the start and completion dates are firm. Without this clear mention, a timeframe remains indicative and may shift according to company constraints. Make sure to have dates confirmed in writing in the quote.

What should you do if the contractor repeatedly postpones the start?

First check whether the dates set in your contract are firm or indicative. Then send the company a written formal notice requiring work to start within a reasonable timeframe. The statutory work contract rules then apply to handle this delay.

Is a company promising to start right away reliable?

This is not a defect in itself, but it needs checking. Request the start date, expected duration, and the site manager's name in writing, along with the order backlog, references, and insurance certificates. For structural work, avoid paying a large advance payment before contract signing.

Updated on 2026-11-21