Tiling is sold mostly by the square metre, but it is paid by the hour. In between lie the laying output, the time for preparation, drying and cleaning, travel and the days without work. A firm that does not know its real hourly cost cannot tell whether its price per square metre leaves a margin or hides a loss.
The employer hourly cost simulator calculates in the browser the pure hourly cost price and a recommended daywork rate, from your wages, your charge rates, your allowances, equipment, overheads and margin. Converting to the square metre is then done by hand, with your own output. The starting values read at the source concern the CN for main construction: for tiling, you enter the data of your collective agreement.
Worked example: a skilled tiler’s hour and the laying price per m²
A tiling firm works out the cost of a skilled tiler. Example values, to be replaced by those of your agreement and your statements: 40 hours a week, 52.14 weeks, 5 weeks of holiday, 9 paid public holidays, 48 non-productive hours a year (waiting for screeds, preparation), base hourly wage CHF 32.00, holiday pay 10.64 %, 13th salary 8.33 %, combined employer charges 18 %, meal allowance CHF 16 per productive day, tools CHF 1’200 a year, overheads 20 %, margin 7 %. Example laying output: 1.4 m² per hour.
| Line | Calculation | Result |
|---|---|---|
| Productive hours per year | 40 × (52.14 − 5) − 9 × 8 − 48 | 1’765.60 h |
| Annual gross wage | 60’339.20 + 6’420.09 + 5’561.05 | CHF 72’320.34 |
| Employer charges (18 %) | 72’320.34 × 0.18 | CHF 13’017.66 |
| Allowances and tools | 16 × 220.70 days + 1’200 | CHF 4’731.20 |
| Pure hourly cost price | 90’069.20 ÷ 1’765.60 | CHF 51.01/h |
| Recommended daywork rate | 51.01 + 20 % = 61.21 ; + 7 % = 65.49 | CHF 65.50/h |
| Labour per m² (1.4 m²/h) | 65.50 ÷ 1.4 | CHF 46.79/m² |
The 1’885.60 hours paid at the base wage less 72 hours of public holidays and 48 non-productive hours give 1’765.60 productive hours, or 220.70 days. The annual base wage is 32.00 × 1’885.60 = CHF 60’339.20; with holiday pay and the 13th salary, the gross wage reaches CHF 72’320.34. Charges, allowances and tools bring the total annual cost to CHF 90’069.20, or CHF 51.01 per productive hour.
Converting to the square metre is done outside the simulator: the hourly rate divided by the output gives the labour per m², here CHF 46.79 for 1.4 m² per hour. If the tile format, the cutting or the substrate drops the output to 1.2 m² per hour, CHF 54.58 per m² is needed to cover the same hour. Material, adhesive and grout come on top.
With these example values, the tiler’s hour costs CHF 51.01, is billed at CHF 65.50 on daywork and needs at least CHF 46.79 of labour per m² at 1.4 m² per hour.
3 common mistakes in tiling hourly cost
Working out the per m² price on a catalogue output
The real output depends on the format, the cutting, cramped rooms and substrates that need reworking. An output that is too optimistic by 0.2 m² per hour loses several francs on every square metre laid.
Ignoring the hours spent waiting for drying
A screed that is not ready, a waterproofing layer that has to dry: these hours are paid. If they are not billed, enter them as non-productive hours so that they go into the cost of the hour.
Using the wrong agreement
Depending on the region, tiling falls under the collective agreement for the finishing trades of French-speaking Switzerland or a national agreement for the tiling trade: wages, early retirement and contributions differ. Check the scope before entering your rates.
How to use the simulator in 3 steps
- Enter the tiler and their hours
Choose a class as an input slot and the age. Enter the weekly working time of your agreement, the paid public holidays and the non-productive hours: unbilled waiting, preparation and cleaning. - Take wages, charges and early retirement from your statements
Enter the hourly wage, the rates from your statements and, if your agreement provides one, the early-retirement contribution in the FAR / RESOR field. Leave the Parifonds at 0 if it does not concern you. - Read the rate and convert it to m²
Note the pure hourly cost and the daywork rate, export the detail as CSV, then divide the rate by your real laying output to check your price per square metre.
What the free version does not do in tiling
The simulator does not calculate a price per square metre: the conversion is done by hand with your output. It does not contain the minimum wages of the tiling agreements, does not cost material or adhesive, and saves nothing: closing the page erases what you entered. The printout carries a watermark.
The Art Construction ERP links the hourly cost to the hours clocked per site: you compare the time actually spent with the square metres laid and adjust your outputs from one site to the next.
Frequently asked questions
Which collective agreement applies to tilers?
In French-speaking Switzerland, tiling falls, depending on the case, within the scope of the collective agreement for the finishing trades (CCT SOR), with the RESOR early-retirement scheme. Elsewhere, there is a national agreement for the tiling trade, whose scope and validity should be checked on the SECO list.
Why does my hourly rate look high against market prices per m²?
Because the price per m² often hides an optimistic output. Divide your rate by the output actually measured on your recent sites to know whether your prices cover the cost.
Do the screed layer and the tiler have the same hourly cost?
Not necessarily: wage, allowances and waiting hours differ. Use scenario B to calculate the second profile and compare the gaps.
Does the drying time of a screed count in the cost?
Drying itself is not working time. On the other hand, the paid hours during which the team waits without being able to progress are non-productive hours to be entered.