On a roof or a facade, two items weigh more heavily than elsewhere in the cost of the hour: the occupational accident insurance premium, higher for work at height, and the hours paid but lost to rain, wind or frost. A daywork rate copied from another building trade often forgets one or the other.
The employer hourly cost simulator calculates in the browser the pure hourly cost price and a recommended daywork rate. Occupational accident insurance has its own field there, in per mille with its ceiling, and bad-weather hours a dedicated field that takes them off the productive hours. The starting values read at the source concern the CN for main construction: for the building envelope, you enter the data of your collective agreement and your policy.
Worked example: a roofer’s daywork hour with 96 bad-weather hours
A roofing firm works out the cost of a skilled roofer. Example values, to be replaced by those of your agreement, your policy and your statements: 40 hours a week, 52.14 weeks, 5 weeks of holiday, 9 paid public holidays, 96 bad-weather hours a year, base hourly wage CHF 33.00, holiday pay 10.64 %, 13th salary 8.33 %, employer charges excluding LAA 15.5 %, occupational LAA premium 60 ‰, meal allowance CHF 16 per productive day, protective equipment and tools CHF 1’400 a year, overheads 22 %, margin 8 %.
| Line | Calculation | Result |
|---|---|---|
| Productive hours per year | 40 × (52.14 − 5) − 9 × 8 − 96 | 1’717.60 h |
| Annual gross wage | 62’224.80 + 6’620.72 + 5’734.83 | CHF 74’580.35 |
| Charges excluding LAA (15.5 %) | 74’580.35 × 0.155 | CHF 11’559.95 |
| Occupational LAA premium (60 ‰) | 74’580.35 × 0.060 | CHF 4’474.82 |
| Allowances and equipment | 16 × 214.70 days + 1’400 | CHF 4’835.20 |
| Pure hourly cost price | 95’450.32 ÷ 1’717.60 | CHF 55.57/h |
| Recommended daywork rate | 55.57 + 22 % = 67.80 ; + 8 % = 73.22 | CHF 73.20/h |
The 1’885.60 hours paid at the base wage less 72 hours of public holidays and 96 bad-weather hours leave 1’717.60 productive hours, or 214.70 days. The annual gross wage reaches CHF 74’580.35. The example LAA premium, 60 ‰, alone costs CHF 4’474.82 a year; the example wage stays below the maximum insured earnings, so the ceiling does not come into play.
The total annual cost is CHF 95’450.32, or CHF 55.57 per productive hour. With 48 bad-weather hours instead of 96, the productive hours would rise to 1’765.60 and the hourly cost would fall by about CHF 1.50: the weather shows directly in the rate. Overheads and margin bring the daywork rate to CHF 73.20 after rounding to 5 centimes.
With these example values, a roofer’s hour costs the firm CHF 55.57, of which about CHF 2.60 is LAA premium, and is billed at CHF 73.20 on daywork.
3 common mistakes in roofing and facade hourly cost
Copying the LAA premium of another trade
The accident insurance premium depends on the class and tariff level set for your firm. Take the rate from your policy: in this example, a gap of 30 ‰ changes the hourly cost by about CHF 1.30.
Counting rainy days as productive
Hours paid but lost to the weather must come out of the productive hours. Otherwise the hourly cost looks low and the rate does not cover the winter.
Forgetting the trade’s early-retirement scheme
The building envelope trade has an early-retirement agreement that provides for contributions. Enter the employer rate in the early-retirement field, according to the agreement that applies to your firm.
How to use the simulator in 3 steps
- Enter the roofer and the bad-weather hours
Choose a class as an input slot and the age, then the weekly working time of your agreement, the paid public holidays and the annual average of bad-weather hours recorded over your last few years. - Take charges, LAA premium and early retirement from your statements
Enter the rates from your statements, the occupational LAA premium in per mille and its ceiling, then the early-retirement contribution in the FAR / RESOR field. You can also enter a bad-weather provision as a percentage of the wage. - Compare a summer and a winter
Copy scenario A to B, change only the bad-weather hours and compare the two rates. Then export the detail as CSV for your calculation.
What the free version does not do for the building envelope
The simulator does not know your LAA premium: no insurer tariff is built in, the rate is entered by you. It does not contain the minimum wages of the building envelope agreement, does not cost scaffolding or collective protection, and saves nothing. The free printout carries a watermark.
The Art Construction ERP links the hourly cost to the hours clocked, bad-weather hours included, and tracks the daywork sheets and invoicing of your roofing and facade sites.
Frequently asked questions
Which collective agreement applies to building envelope firms?
The collective agreement for the Swiss building envelope trade, declared generally binding by the decree of 28 November 2023, in force from 1 January 2024 to 31 December 2027 according to SECO. Some cantons are excluded from its scope: check the text of the decree for your firm.
Is there an early-retirement scheme in the trade?
Yes, a collective agreement for an early-retirement model in the Swiss building envelope trade is declared generally binding, valid until 31 December 2028 according to SECO. The contribution rate must be taken from that agreement.
Where do I enter the accident insurance premium?
In the occupational accident insurance field, in per mille, with the maximum insured annual earnings as the ceiling. 60 ‰ corresponds to 6 % of the wage.
Do I need a bad-weather provision on top of the hours?
Bad-weather hours reduce the productive hours. The provision, as a percentage of the wage, covers a risk specific to your firm on top of these hours: do not count the same loss twice.