Employer hourly cost in masonry and civil engineering (CN): from wage class to daywork rate

A paid hour of masonry is not a billable hour: here is how to go from the CN wage class to the price of an hour charged on daywork.

Open the free studio →

Free, no account: your plans, schedules and figures stay in your browser.

In the main construction sector, the national collective agreement (CN, Landesmantelvertrag) sets the wage classes CE, Q, A, B and C, the annual working time, holidays by age, the 13th salary and the joint contributions. The employer or estimator who charges hours on daywork has to go further than the hourly wage, though: every productive hour also carries the hours that are paid but not worked (holidays, public holidays, bad weather), the employer’s social charges, the FAR early-retirement scheme, the Parifonds, meal and site allowances, equipment, and then overheads and margin.

The employer hourly cost simulator follows this chain in six steps: the worker (class and age, which give the weeks of holiday and the occupational pension age band), working time, wages and supplements, employer charges, allowances and expenses, then overheads and margin. The CN values and the federal social insurance values are read at the source and dated; the hourly wage, your insurance premiums and your fund rates remain your own entries. The calculation is shown line by line with its formula, and the result gives the pure hourly cost price and the recommended daywork rate, rounded to 5 centimes.

Worked example: hourly cost of a class Q bricklayer on daywork

A class Q bricklayer, aged 35 (five weeks of holiday), in a small structural works firm. Example values, to be replaced by those of your firm, your fund and your policies: hourly wage CHF 33.00, 40.5 hours a week over 52.14 weeks, 8 paid public holidays, 60 hours of bad weather a year, family allowances 2.0 %, occupational pension (LPP) 7.0 % after a coordination deduction of CHF 26’460, occupational accident insurance (LAA) 40 ‰, sickness daily allowance insurance 1.0 %, allowances of CHF 16 (meals) and CHF 4 (site) per productive day, PPE and tools CHF 900 a year, overheads 15 %, margin 8 %.

Annual cost and hourly cost of a class Q bricklayer (example values)
LineBasis of calculationCHF per yearCHF per productive hour
Annual gross wageBase 63’002.61 + holiday pay 10.6 % + 13th salary 8.3 %75’464.4042.29
Employer chargesAVS/AI/APG, AC, allowances, LPP, LAA, sickness, FAR 6 %, Parifonds 0.5 %18’447.7210.34
AllowancesCHF 20 × 220.29 productive days4’405.802.47
PPE and toolsAnnual amount entered900.000.50
Total annual costSum of the four lines99’217.9255.60
Overheads and margin15 % then 8 %13.46
Recommended daywork rateRounded to 5 centimes69.05

Hours first: 40.5 h × (52.14 − 5 weeks of holiday) = 1’909.17 hours paid at the base wage; take away 8 public holidays × 8.1 h = 64.8 h to get 1’844.37 hours worked, then 60 hours of bad weather: 1’784.37 productive hours remain, or 220.29 days of 8.1 h. The base wage is 33.00 × 1’909.17 = CHF 63’002.61; holiday pay 10.6 % × 63’002.61 = CHF 6’678.28; the 13th salary 8.3 % × (63’002.61 + 6’678.28) = CHF 5’783.51; the gross wage reaches CHF 75’464.40.

Employer charges add up AVS/AI/APG 5.3 % (3’999.61), unemployment insurance AC 1.1 % (830.11), family allowances 2.0 % (1’509.29), LPP 7 % × (75’464.40 − 26’460) = 3’430.31, LAA 40 ‰ (3’018.58), sickness daily allowance 1.0 % (754.64), FAR 6 % (4’527.86) and Parifonds 0.5 % (377.32), or CHF 18’447.72. With allowances and equipment, the annual cost reaches CHF 99’217.92; divided by 1’784.37 productive hours, it gives a pure hourly cost price of CHF 55.60. Overheads (15 %) bring it to CHF 63.94, the margin (8 %) to CHF 69.06, rounded to CHF 69.05.

For this class Q bricklayer, each productive hour costs the firm CHF 55.60 and the recommended daywork rate, with 15 % overheads and 8 % margin, is CHF 69.05 excluding VAT.

3 costly mistakes in a bricklayer’s hourly cost

Dividing the annual cost by the hours paid

Dividing by the 2’112 contractual hours instead of the productive hours lowers the hourly cost by several francs: holidays, public holidays and bad weather are paid but cannot be billed. In the example, the gap between 2’111.67 gross hours and 1’784.37 productive hours is more than 15 %.

Forgetting the FAR and the Parifonds

The FAR early-retirement scheme and the Parifonds are employer contributions specific to the main construction sector. Leaving them out removes nearly CHF 4’900 a year here. Also check whether your firm belongs to a regional joint fund that replaces the Parifonds.

Copying an accident or sickness rate from another firm

The occupational accident insurance premium depends on your firm’s class and tariff level, and the sickness daily allowance on your own policy. A rate copied from a colleague can distort the cost price by a franc an hour or more.

Working out a bricklayer’s daywork rate in 3 steps

  1. Choose the class and age
    In step 1, choose the worker’s CN class and age: the studio derives the weeks of holiday and the LPP age band from them. Then enter the working time, paid public holidays and your average bad-weather hours.
  2. Enter wages and the rates from your statements
    Enter the real hourly wage for the class, then the rates from your statements: family allowances, LPP by age band, LAA in per mille, sickness. The FAR and Parifonds lines show their source; mark them “checked by me” once you have verified them.
  3. Compare two scenarios and export
    Adjust overheads and margin, compare for instance a class Q worker and a class A worker in scenarios A and B, then print the sheet or export the detail as CSV for your pricing file.

Open the free studio →

What the free version does not do for masonry hourly cost

The simulator holds no minimum wage by zone or by class: the hourly wage is your entry. It does not calculate the pay the worker receives or the deductions from it, does not know your LAA premium or your fund rates, and a field left empty blocks the calculation rather than being counted as zero. Nothing is saved: closing the page erases what you entered. The result is an indicative simulation; the CN, your fund and your policies prevail.

The Art Construction ERP links this hourly cost to the hours actually clocked on each site, to signed daywork sheets and to invoicing, with documents carrying your firm’s letterhead and no watermark.

Frequently asked questions

What is the difference between pure hourly cost and daywork rate?

The pure hourly cost divides the worker’s annual cost (gross wage, charges, allowances, equipment) by their productive hours. The daywork rate adds your overheads and then your margin; it is the price excluding VAT of the hour billed to the client.

Does the simulator know the CN minimum wages?

No. The CN sets minimum wages by zone and by class, but the studio prefills no wage: you enter the wage your firm actually pays, which may be higher than the minimum.

Should bad-weather hours count as productive?

No. Bad-weather hours paid by the employer cannot be billed: the studio takes them off the hours worked to obtain the productive hours, which raises the cost of each hour sold.

Where can I find the current FAR rate?

The FAR foundation publishes its contributions on its website. The studio shows the value read at the source with its date; if your statement shows another rate, replace it and the line switches to “to be checked”.